Pre-Inspection
|
1/25/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
2/8/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
2/10/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
2/11/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
2/12/2016
|
Approved
|
MICHAEL KUHN
|
Piling/Pier/Caisson
|
2/16/2016
|
Partial Approval
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
2/23/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
2/24/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
2/26/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
2/29/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
3/2/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
3/3/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
3/16/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
3/17/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
3/22/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
3/24/2016
|
Approved
|
MICHAEL KUHN
|
Pre-Inspection
|
4/21/2016
|
Partial Inspection
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
5/4/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
5/6/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
5/9/2016
|
Approved
|
MICHAEL KUHN
|
Footing/Foundation/Slab
|
5/9/2016
|
Partial Approval
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
5/10/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
5/11/2016
|
Approved
|
MICHAEL KUHN
|
Footing/Foundation/Slab
|
5/11/2016
|
Partial Approval
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
5/12/2016
|
Approved
|
MICHAEL KUHN
|
Reinforced Concrete Frame
|
5/12/2016
|
Partial Approval
|
MICHAEL KUHN
|
Verify Sprinkler Sign Off
|
5/12/2016
|
Not Ready for Inspection
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
5/13/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Shotcrete
|
5/16/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Shotcrete
|
5/17/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
5/17/2016
|
Partial Approval
|
GREGORY POMISH
|
Verify Sprinkler Sign Off
|
5/17/2016
|
Not Ready for Inspection
|
GREGORY POMISH
|
Deputy Shotcrete
|
5/18/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Shotcrete
|
5/19/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Shotcrete
|
5/20/2016
|
Approved
|
MICHAEL KUHN
|
Footing/Foundation/Slab
|
5/20/2016
|
Partial Approval
|
MICHAEL KUHN
|
Reinforced Concrete Frame
|
5/20/2016
|
Partial Approval
|
MICHAEL KUHN
|
Verify Sprinkler Sign Off
|
5/20/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
5/23/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
5/24/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Drilled-In Anchors
|
5/25/2016
|
Approved
|
FELIX CEBALLOS
|
Deputy Reinf. Concrete
|
5/25/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
5/25/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
5/26/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
5/27/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
5/31/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
6/1/2016
|
Approved
|
MICHAEL KUHN
|
Reinforced Concrete Frame
|
6/1/2016
|
Partial Approval
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
6/2/2016
|
Approved
|
MICHAEL KUHN
|
Footing/Foundation/Slab
|
6/2/2016
|
Partial Approval
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
6/3/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
6/7/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
6/8/2016
|
Approved
|
MICHAEL KUHN
|
Reinforced Masonry Frame
|
6/8/2016
|
Partial Approval
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
6/9/2016
|
Approved
|
SAKO AGHAZARIAN
|
Reinforced Concrete Frame
|
6/9/2016
|
Partial Approval
|
SAKO AGHAZARIAN
|
Deputy Reinf. Concrete
|
6/10/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
6/13/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
6/13/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
6/14/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
6/15/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
6/16/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
6/17/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Shotcrete
|
7/7/2016
|
Approved
|
SAKO AGHAZARIAN
|
Footing/Foundation/Slab
|
7/7/2016
|
Partial Approval
|
SAKO AGHAZARIAN
|
Deputy Shotcrete
|
7/8/2016
|
Conditional Approval
|
LESLIE TRUJILLO
|
Deputy Reinf. Concrete
|
7/11/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Shotcrete
|
7/11/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Shotcrete
|
7/12/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Shotcrete
|
7/18/2016
|
Approved
|
MICHAEL KUHN
|
Reinforced Concrete Frame
|
7/18/2016
|
Partial Approval
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
7/19/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Shotcrete
|
7/19/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Shotcrete
|
7/20/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
7/20/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Shotcrete
|
7/21/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Shotcrete
|
7/22/2016
|
Approved
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
8/4/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
8/4/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
8/5/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
8/11/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
8/26/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
8/30/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
9/2/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
9/6/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
9/6/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
9/7/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
9/9/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
9/12/2016
|
Conditional Approval
|
BARRY SILLS
|
Footing/Foundation/Slab
|
9/12/2016
|
Partial Approval
|
BARRY SILLS
|
Deputy Reinf. Concrete
|
9/16/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
9/16/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
9/23/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
9/29/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
9/30/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
10/3/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
10/3/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
10/3/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
10/4/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
10/4/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
10/5/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
10/5/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
10/6/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
10/6/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
10/7/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
10/7/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
10/7/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
10/7/2016
|
Not Ready for Inspection
|
GREGORY POMISH
|
Reinforced Masonry Frame
|
10/10/2016
|
Partial Approval
|
SAKO AGHAZARIAN
|
Deputy Reinf. Concrete
|
10/11/2016
|
Approved
|
SAKO AGHAZARIAN
|
Footing/Foundation/Slab
|
10/11/2016
|
Partial Approval
|
SAKO AGHAZARIAN
|
Deputy Reinf. Concrete
|
10/12/2016
|
Conditional Approval
|
NICK DANERI
|
Deputy Reinf. Concrete
|
10/13/2016
|
Approved
|
SAKO AGHAZARIAN
|
Reinforced Concrete Frame
|
10/13/2016
|
Partial Approval
|
SAKO AGHAZARIAN
|
Deputy Reinf. Concrete
|
10/17/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
10/17/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
10/18/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
10/18/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
10/19/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
10/20/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
10/20/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
10/20/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
10/21/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
10/25/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
10/25/2016
|
Conditional Approval
|
GREGORY POMISH
|
Green Building Rough
|
10/25/2016
|
Not Ready for Inspection
|
MICKEY YAMASHITA
|
Reinforced Concrete Frame
|
10/25/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
10/27/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
10/28/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
10/28/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
10/31/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
11/1/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
11/2/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Masonry Frame
|
11/2/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
11/3/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
11/4/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
11/7/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
11/8/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
11/9/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
11/9/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
11/9/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
11/10/2016
|
Approved
|
SAKO AGHAZARIAN
|
Deputy Reinf. Masonry
|
11/10/2016
|
Approved
|
SAKO AGHAZARIAN
|
Deputy Reinf. Concrete
|
11/15/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
11/15/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
11/15/2016
|
Partial Inspection
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
11/16/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
11/17/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
11/18/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
11/21/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
11/21/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Shotcrete
|
11/22/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
11/23/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Shotcrete
|
11/28/2016
|
Conditional Approval
|
GREGORY POMISH
|
Green Building Rough
|
11/28/2016
|
Not Ready for Inspection
|
MICKEY YAMASHITA
|
Reinforced Concrete Frame
|
11/28/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
11/29/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
11/29/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Other (see comments)
|
11/30/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/2/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
12/5/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/5/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/6/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Masonry Frame
|
12/6/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/7/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/8/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/9/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Masonry Frame
|
12/9/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/12/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/13/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/14/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/15/2016
|
Approved
|
SAKO AGHAZARIAN
|
Footing/Foundation/Slab
|
12/15/2016
|
Partial Approval
|
SAKO AGHAZARIAN
|
Reinforced Masonry Frame
|
12/15/2016
|
Partial Approval
|
SAKO AGHAZARIAN
|
Deputy Reinf. Masonry
|
12/16/2016
|
Conditional Approval
|
BARRY SILLS
|
Deputy Reinf. Concrete
|
12/19/2016
|
Approved
|
SAKO AGHAZARIAN
|
Deputy Reinf. Concrete
|
12/19/2016
|
Conditional Approval
|
DAVID BURKHEAD
|
Deputy Reinf. Masonry
|
12/19/2016
|
Approved
|
SAKO AGHAZARIAN
|
Deputy Reinf. Masonry
|
12/20/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/21/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/22/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
12/22/2016
|
Not Ready for Inspection
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
12/23/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/23/2016
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Masonry Frame
|
12/23/2016
|
Partial Inspection
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
12/27/2016
|
Conditional Approval
|
GREGORY POMISH
|
Green Building Rough
|
12/27/2016
|
Not Ready for Inspection
|
MICKEY YAMASHITA
|
Reinforced Concrete Frame
|
12/27/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
12/28/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
12/28/2016
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
12/28/2016
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
12/29/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
12/30/2016
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
1/3/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/3/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
1/4/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/4/2017
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
1/4/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/5/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Steel/Welding
|
1/5/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/6/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Steel/Welding
|
1/6/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
1/9/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/13/2017
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Masonry Frame
|
1/13/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/17/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/18/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/19/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Steel/Welding
|
1/19/2017
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Masonry Frame
|
1/19/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
1/20/2017
|
Approved
|
SAKO AGHAZARIAN
|
Deputy Reinf. Masonry
|
1/20/2017
|
Approved
|
SAKO AGHAZARIAN
|
Deputy Steel/Welding
|
1/20/2017
|
Approved
|
SAKO AGHAZARIAN
|
Footing/Foundation/Slab
|
1/20/2017
|
Partial Approval
|
SAKO AGHAZARIAN
|
Deputy Reinf. Masonry
|
1/24/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
1/25/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/25/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/26/2017
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
1/26/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
1/27/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/27/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Steel/Welding
|
1/27/2017
|
Conditional Approval
|
GREGORY POMISH
|
Green Building Rough
|
1/30/2017
|
Not Ready for Inspection
|
MICKEY YAMASHITA
|
Reinforced Concrete Frame
|
1/30/2017
|
Not Ready for Inspection
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/31/2017
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
1/31/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
2/2/2017
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
2/2/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
2/3/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Steel/Welding
|
2/7/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
2/8/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Steel/Welding
|
2/8/2017
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
2/22/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
2/23/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
2/27/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
2/28/2017
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
2/28/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
3/1/2017
|
Approved
|
SAKO AGHAZARIAN
|
Footing/Foundation/Slab
|
3/1/2017
|
Partial Approval
|
BARRY SILLS
|
Deputy Reinf. Concrete
|
3/2/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Steel/Welding
|
3/6/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
3/7/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
3/7/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Steel/Welding
|
3/7/2017
|
Conditional Approval
|
GREGORY POMISH
|
Green Building Rough
|
3/7/2017
|
Not Ready for Inspection
|
RICHARD DOCKUS
|
Reinforced Concrete Frame
|
3/7/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
3/8/2017
|
Conditional Approval
|
GREGORY POMISH
|
Drywall Nailing
|
3/8/2017
|
Partial Inspection
|
GREGORY POMISH
|
Light Gage Steel Frame
|
3/8/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
3/9/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
3/9/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Drilled-In Anchors
|
3/10/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
3/10/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
3/10/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
3/14/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
3/15/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
3/16/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
3/16/2017
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
3/16/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
3/17/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
3/17/2017
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
3/17/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
3/20/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
3/21/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
3/22/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
3/24/2017
|
Approved
|
SAKO AGHAZARIAN
|
Deputy Reinf. Masonry
|
3/24/2017
|
Approved
|
SAKO AGHAZARIAN
|
Deputy Reinf. Concrete
|
3/28/2017
|
Approved
|
SAKO AGHAZARIAN
|
Deputy Reinf. Masonry
|
3/28/2017
|
Approved
|
SAKO AGHAZARIAN
|
Footing/Foundation/Slab
|
3/28/2017
|
Partial Approval
|
SAKO AGHAZARIAN
|
Deputy Reinf. Masonry
|
3/29/2017
|
Approved
|
SAKO AGHAZARIAN
|
Reinforced Masonry Frame
|
3/29/2017
|
Partial Approval
|
SAKO AGHAZARIAN
|
Deputy Reinf. Concrete
|
3/30/2017
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Masonry
|
3/30/2017
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Masonry
|
3/31/2017
|
Conditional Approval
|
JEFFREY FULTON
|
Deputy Reinf. Masonry
|
4/3/2017
|
Conditional Approval
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
4/3/2017
|
Partial Inspection
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/4/2017
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Masonry Frame
|
4/4/2017
|
Partial Inspection
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
4/5/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/5/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/6/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/7/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/10/2017
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Masonry Frame
|
4/10/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/11/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/12/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/13/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/14/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/17/2017
|
Conditional Approval
|
GREGORY POMISH
|
Drywall Nailing
|
4/17/2017
|
Partial Approval
|
GREGORY POMISH
|
Light Gage Steel Frame
|
4/17/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/18/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/19/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/20/2017
|
Conditional Approval
|
GREGORY POMISH
|
Drywall Nailing
|
4/20/2017
|
Partial Inspection
|
GREGORY POMISH
|
Light Gage Steel Frame
|
4/20/2017
|
Partial Inspection
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
4/21/2017
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Steel/Welding
|
4/21/2017
|
Conditional Approval
|
GREGORY POMISH
|
Reinforced Masonry Frame
|
4/21/2017
|
Partial Approval
|
GREGORY POMISH
|
Drywall Nailing
|
5/3/2017
|
Partial Approval
|
GREGORY POMISH
|
Interior/Exterior Lathing
|
5/3/2017
|
Not Ready for Inspection
|
GREGORY POMISH
|
Light Gage Steel Frame
|
5/3/2017
|
Partial Approval
|
GREGORY POMISH
|
Interior/Exterior Lathing
|
5/18/2017
|
Partial Approval
|
GREGORY POMISH
|
Interior/Exterior Lathing
|
5/22/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Steel/Welding
|
5/30/2017
|
Conditional Approval
|
GREGORY POMISH
|
Interior/Exterior Lathing
|
6/6/2017
|
Partial Approval
|
GREGORY POMISH
|
Drywall Nailing
|
6/26/2017
|
Partial Approval
|
GREGORY POMISH
|
Deputy Reinf. Concrete
|
7/20/2017
|
Conditional Approval
|
GREGORY POMISH
|
Drywall Nailing
|
9/18/2017
|
Partial Approval
|
GREGORY POMISH
|
Interior/Exterior Lathing
|
11/27/2017
|
Partial Approval
|
GREGORY POMISH
|
Final
|
12/11/2017
|
Partial Inspection
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
12/11/2017
|
Approved
|
GREGORY POMISH
|
Green Building Final
|
12/11/2017
|
Partial Inspection
|
GREGORY POMISH
|
Green Building Rough
|
12/11/2017
|
Approved
|
GREGORY POMISH
|
Reinforced Concrete Frame
|
12/11/2017
|
Approved
|
GREGORY POMISH
|
SGSOV-Seismic Gas S/O Valve
|
12/11/2017
|
SGSOV Approved
|
GREGORY POMISH
|
Smoke Detectors
|
12/11/2017
|
Partial Inspection
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/9/2018
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/10/2018
|
Conditional Approval
|
GREGORY POMISH
|
Deputy Reinf. Masonry
|
1/17/2018
|
Conditional Approval
|
GREGORY POMISH
|
Final
|
2/28/2018
|
Partial Inspection
|
GREGORY POMISH
|
Green Building Final
|
2/28/2018
|
Partial Approval
|
GREGORY POMISH
|
Smoke Detectors
|
2/28/2018
|
Approved
|
GREGORY POMISH
|
Final
|
3/12/2018
|
OK to Issue CofO
|
GREGORY POMISH
|
Green Building Final
|
3/12/2018
|
Approved
|
GREGORY POMISH
|