4501 S BROADWAY 90037
Certificate Information: 4501 S BROADWAY 90037
- Application / Permit
- 08010-10000-02520
- Plan Check / Job No.
- B08LA09675
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (4) Community Center operated by philanthropic organization
- Work Description
- Two story Philantropic Institution (None profit Community Center). Includes space for offices, multipurpose rooms, gymnasium for youth activities, and activity rooms.
- Permit Issued
- Issued on 6/9/2014
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 10/6/2008 | APPLICANT |
Assigned to Plan Check Engineer | 10/10/2008 | RICARDO TRES |
Corrections Issued | 10/16/2008 | RICARDO TRES |
Quality Review Completed | 10/20/2008 | CHARMIE HUYNH |
Building Plans Picked Up | 11/14/2008 | APPLICANT |
Disabled Access Plans Picked Up | 11/14/2008 | APPLICANT |
Applicant returned to address corrections | 1/7/2009 | RICARDO TRES |
Applicant returned to address corrections | 3/12/2009 | RICARDO TRES |
Plan Check Approved | 3/22/2010 | RICARDO TRES |
Plan Check Approved | 3/17/2014 | RICARDO TRES |
Issued | 6/9/2014 | LADBS |
Permit Finaled | 1/31/2023 | JAMES POWERS |
Permit Application Clearance Information
Address approval | Cleared | 11/21/2008 | THEIN HTAY |
"Q" conditions | Cleared | 12/3/2008 | ONDREA TYE |
Eng Process Fee Ord 176,300 | Cleared | 1/2/2009 | NATALIE MOORE |
Sewer availability | Cleared | 1/2/2009 | NATALIE MOORE |
Driveway location | Cleared | 1/8/2009 | TAIMOUR TANAVOLI |
Hydrant and Access approval | Cleared | 1/8/2009 | ROBERT DUFF |
Highway dedication | Cleared | 1/13/2009 | THEIN HTAY |
Project located in CRA area | Cleared | 1/13/2009 | JIM URQUHART |
Comm Cor/Mini-Mall | Cleared | 2/9/2009 | GREGORY SHOOP |
Prkng lot landscape/Water mgmt | Cleared | 2/9/2009 | GREGORY SHOOP |
Comm Cor/Mini-Mall | Cleared | 2/24/2009 | GREGORY SHOOP |
Permit | Cleared | 3/23/2009 | VALENTINO PUEBLOS |
Roof/Waste drainage to street | Cleared | 3/23/2009 | VALENTINO PUEBLOS |
Stormwater Pollution Mitigatn | Cleared | 3/23/2009 | MAJID SADEGHI |
Encroachment in public way | Cleared | 4/6/2009 | SANDY MCCLELLAN |
Work Adjacent to Public Way | Cleared | 3/24/2010 | JASON CHANG |
Low Impact Development | Cleared | 5/15/2013 | IDA MEISAMI-FARD |
Green Code | Cleared | 6/18/2013 | MARCUS LEVIAS |
Comm Cor/Mini-Mall | Cleared | 1/30/2014 | PHYLLIS PARKER |
Title 19 building approval | Cleared | 2/24/2014 | DAVE MYERS |
DAS Clearance | Cleared | 2/25/2014 | RICARDO TRES |
Contact Information
Architect | Brown, Dale William; Lic. No.: C17744 | 16 NORTH MARENGO AVENUE SUITE 702 PASADENA, CA 91101 |
Contractor | Cal-City Construction Inc; Lic. No.: 539265-B | 16605 NORWALK BLVD CERRITOS, CA 90703 |
Engineer | Ekmekji, Samir Dikran; Lic. No.: S2289 | 4314 GAYLE DR TARZANA, CA 91356 |
Inspector Information
JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 6/8/2015 | Not Ready for Inspection | JAMES POWERS |
Footing/Foundation/Slab | 6/23/2015 | Not Ready for Inspection | JAMES POWERS |
Reinforced Concrete Frame | 6/24/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 6/26/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 7/24/2015 | Partial Approval | JAMES POWERS |
Floor/Roof Diaphrgm/Shear Wall | 7/28/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 7/30/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 7/31/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 8/4/2015 | Partial Approval | JAMES POWERS |
Reinforced Masonry Frame | 8/6/2015 | Partial Inspection | WILLIAM GARCIA |
Deputy Reinf. Masonry | 8/7/2015 | Partial Approval | JAMES POWERS |
Footing/Foundation/Slab | 8/14/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 8/17/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 9/9/2015 | Partial Approval | JAMES POWERS |
Footing/Foundation/Slab | 9/10/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 9/11/2015 | Partial Approval | WILLIAM GARCIA |
Deputy Reinf. Masonry | 9/24/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 9/30/2015 | Partial Approval | JAMES POWERS |
Reinforced Masonry Frame | 9/30/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 10/1/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 10/5/2015 | Partial Approval | JAMES POWERS |
Reinforced Masonry Frame | 10/5/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 10/6/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 10/9/2015 | Partial Approval | LESLIE TRUJILLO |
Reinforced Masonry Frame | 10/9/2015 | Partial Approval | LESLIE TRUJILLO |
Deputy Reinf. Masonry | 10/14/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 10/16/2015 | Partial Approval | JAMES POWERS |
Reinforced Masonry Frame | 10/16/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 10/19/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 10/20/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 10/22/2015 | Partial Approval | JAMES POWERS |
Reinforced Masonry Frame | 10/22/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 10/26/2015 | Partial Approval | JAMES POWERS |
Reinforced Masonry Frame | 10/26/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 10/27/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 10/28/2015 | Partial Approval | JAMES POWERS |
Reinforced Masonry Frame | 10/28/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 10/29/2015 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 10/30/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 11/9/2015 | Partial Approval | JAMES POWERS |
Reinforced Masonry Frame | 11/9/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 11/10/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 11/12/2015 | Partial Approval | LESLIE TRUJILLO |
Deputy Reinf. Masonry | 11/16/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 11/17/2015 | Partial Approval | JAMES POWERS |
Reinforced Masonry Frame | 11/17/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 11/19/2015 | Partial Approval | JAMES POWERS |
Reinforced Masonry Frame | 11/19/2015 | Partial Approval | JAMES POWERS |
Deputy Reinf. Masonry | 11/23/2015 | Conditional Approval | BYRON FUENTES |
Deputy Steel/Welding | 12/2/2015 | Approved | BYRON FUENTES |
Deputy Steel/Welding | 12/8/2015 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 12/9/2015 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 12/10/2015 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 12/18/2015 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 1/5/2016 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 1/11/2016 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 1/12/2016 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 1/13/2016 | Partial Approval | JAMES POWERS |
Structural Steel Frame | 1/13/2016 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 1/14/2016 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 1/15/2016 | Partial Approval | JAMES POWERS |
Green Building Rough | 1/15/2016 | Not Ready for Inspection | JOHN KLARIN |
Deputy Steel/Welding | 1/20/2016 | Partial Approval | JAMES POWERS |
Pre-Inspection | 2/26/2019 | Partial Approval | JAMES POWERS |