1026 S BROADWAY 90015

Certificate Information: 1026 S BROADWAY 90015

Application / Permit
10030-10000-01380
Plan Check / Job No.
G10LA00054
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
GRADING PERMIT FOR A NEW PARKING LOT. CUT = FILL = 253 CU. YDS.
Permit Issued
Issued on 6/30/2010
Issuing Office
Metro
Current Status
Permit Finaled on 8/3/2011

Permit Application Status History

Submitted 3/18/2010 APPLICANT
Assigned to Plan Check Engineer 3/22/2010 FREDERICK WONG
Corrections Issued 3/22/2010 FREDERICK WONG
Plan Check Approved 6/30/2010 FRED WONG
Issued 6/30/2010 LADBS
Permit Finaled 8/2/2011 JOHNNY KAZARIAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/7/2010 VALENTINO PUEBLOS
Permit Cleared 4/7/2010 VALENTINO PUEBLOS
Roof/Waste drainage to street Cleared 4/7/2010 VALENTINO PUEBLOS
Stormwater Pollution Mitigatn Cleared 6/3/2010 AYMAN JABBOURI
Grading Pre-Inspection Cleared 6/4/2010 JOHNNY KAZARIAN

Contact Information

Contractor Santa Ana Creek Development Company; Lic. No.: 266187-B 2288 NORTH BATAVIA      ORANGE, CA 92865
Engineer Cruikshank, John Michael; Lic. No.: C50792 411 N HARBOR BLVD SUITE 201      SAN PEDRO, CA 90731

Inspector Information

JONATHAN HOM, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 7/7/2010 Approved JOHNNY KAZARIAN
Initial Grading 7/12/2010 Approved JOHNNY KAZARIAN
Bottom/Toe 9/22/2010 Partial Approval JEFFREY DURAN
METHANE-Barrier 9/22/2010 Not Ready for Inspection JEFFREY DURAN
METHANE-Subgrade 9/22/2010 Not Ready for Inspection JEFFREY DURAN
Drainage Devices/Catch Basin 9/27/2010 Partial Approval SERGIO VALENZUELA
Drainage Devices/Catch Basin 9/29/2010 Partial Approval SERGIO VALENZUELA
Bottom/Toe 10/28/2010 Partial Approval JOHNNY KAZARIAN
METHANE-Barrier 10/28/2010 Partial Inspection JOHNNY KAZARIAN
METHANE-Subgrade 10/28/2010 Partial Inspection JOHNNY KAZARIAN
Drainage Devices/Catch Basin 6/10/2011 Partial Approval JOHNNY KAZARIAN
Rough 6/29/2011 Partial Inspection JOHNNY KAZARIAN
Bottom/Toe 6/30/2011 Partial Inspection JOHNNY KAZARIAN
Bottom/Toe 8/2/2011 Partial Approval JOHNNY KAZARIAN
Drainage Devices/Catch Basin 8/2/2011 Approved JOHNNY KAZARIAN
Excavation 8/2/2011 Partial Approval JOHNNY KAZARIAN
Final 8/2/2011 Permit Finaled JOHNNY KAZARIAN
METHANE-Barrier 8/2/2011 Partial Inspection JOHNNY KAZARIAN
METHANE-Subgrade 8/2/2011 Partial Inspection JOHNNY KAZARIAN
Rough 8/2/2011 Approved JOHNNY KAZARIAN