125 W 4TH ST 90013

Certificate Information: 125 W 4TH ST 90013

Application / Permit
12016-10008-06979
Plan Check / Job No.
B19LA21301
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(27) Joint Living and Working Quarters
Work Description
PROPOSED CHANGE OF ARCHITECT OF RECORD FOR THE WORK PERMITTED UNDER THIS PERMIT. THE ORIGINAL ARCHITECT OF RECORD HAS DRAFTED AND SUBMITTED A LETTER ALLOWING THE USE OF THE APPROVED PLANS BY THE NEW ARCHITECT. ORIG WORK DESC=CONVERSION OF AN EXISTING 10 STORY OFFICE/RETAIL BUILDING TO 188 JOINT LIVE/WORK UNITS (TIER ONE OPTION PER 12.21C9), RETAIL AND RESTAURANTS W/ BARS (ADAPTIVE RE-USE PROJECT). ADDITIONS OF 2ND FLOOR AND 11TH FLOOR LEVELS TO CREATE A 12 STORY BUILDING, ADDITION OF AMENITIES (RESTAURANT, RECREATION ROOM, POOL, LOUNGE AND FITNESS ROOM) LEVEL ABOVE THE 10TH FLOOR. MAINTAINING EXISTING 21 PARKING SPACES PER THE PLANNING CASE. PC EXTENDED TILL 10-9-15 W/ 2011 CODE. POOL, STAIRS (SPIRAL/STARIGHT RUN), RAILS ARE DEFERRED APPROVAL
Permit Issued
Issued on 10/10/2019
Issuing Office
Metro
Current Status
Permit Finaled on 12/13/2019
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 10/7/2019 JOHN VASQUEZ
Issued 10/10/2019 LADBS
Permit Finaled 12/13/2019 ERNESTO CORRAL

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Dua,, Anuj; Lic. No.: C37444 1050 LATIN WAY      LOS ANGELES, CA 90065
Contractor Owner-Builder       ,
Engineer Youssef, Nabih Fouad Guirg; Lic. No.: S2026 550 S HOPE ST SUITE 1700      LOS ANGELES, CA 90017

Inspector Information

KATY RAMIREZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BAZERKANIAN, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 11/22/2019 Not Ready for Inspection GRANT WOODS
Light Gage Steel Frame 11/22/2019 Not Ready for Inspection GRANT WOODS
Final 12/2/2019 Partial Inspection ERNESTO CORRAL
Pre-Inspection 12/3/2019 Partial Inspection ERNESTO CORRAL
Pre-Inspection 12/5/2019 Partial Inspection DANIEL COLLINS
Pre-Inspection 12/6/2019 Partial Inspection ERNESTO CORRAL
Final 12/10/2019 Partial Inspection ERNESTO CORRAL
Pre-Inspection 12/11/2019 Partial Inspection ERNESTO CORRAL
Pre-Inspection 12/12/2019 Partial Inspection ERNESTO CORRAL
Pre-Inspection 12/13/2019 Partial Inspection ERNESTO CORRAL