899 S FRANCISCO ST 90017

Certificate Information: 899 S FRANCISCO ST 90017

Application / Permit
13010-10000-03023
Plan Check / Job No.
B13LA12210
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
Core and Shell only for a new 18-story hotel, including 350 guest rooms on 14 floors, a 4-story podium with a pool deck, meeting and ballrooms, restaurant/retail spaces, 2 levels of below grade parking, and rooftop mechanical areas.
Permit Issued
Issued on 2/25/2015
Issuing Office
Metro
Current Status
CofO Corrected on 5/9/2018
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2013 APPLICANT
Application Withdrawn 11/15/2013 APPLICANT
Re-Activate Applicaton 11/15/2013 APPLICANT
Assigned to Plan Check Engineer 11/21/2013 ALLEN MANALANSAN
Corrections Issued 12/3/2013 ALLEN MANALANSAN
Disabled Access Plans Picked Up 12/3/2013 APPLICANT
Quality Review Completed 12/4/2013 CHARLES CHANG
Building Plans Picked Up 12/4/2013 APPLICANT
Applicant returned to address corrections 4/30/2014 ALLEN MANALANSAN
Applicant returned to address corrections 5/13/2014 CHARLES CHANG
Applicant returned to address corrections 5/16/2014 ALLEN MANALANSAN
Applicant returned to address corrections 5/20/2014 CHARLES CHANG
Applicant returned to address corrections 5/27/2014 CHARLES CHANG
Applicant returned to address corrections 5/28/2014 CHARLES CHANG
Applicant returned to address corrections 6/10/2014 SAI KHUM
Applicant returned to address corrections 6/16/2014 CHARLES CHANG
Applicant returned to address corrections 6/17/2014 CHARLES CHANG
Applicant returned to address corrections 6/19/2014 CHARLES CHANG
Applicant returned to address corrections 7/10/2014 ALLEN MANALANSAN
Applicant returned to address corrections 7/10/2014 CHARLES CHANG
Applicant returned to address corrections 7/15/2014 CHARLES CHANG
Applicant returned to address corrections 7/22/2014 CHARLES CHANG
Applicant returned to address corrections 9/22/2014 ALLEN MANALANSAN
Applicant returned to address corrections 1/22/2015 SAI KHUM
Applicant returned to address corrections 2/4/2015 SAI KHUM
Applicant returned to address corrections 2/12/2015 SAI KHUM
Applicant returned to address corrections 2/12/2015 ALLEN MANALANSAN
Applicant returned to address corrections 2/13/2015 SAI KHUM
Plan Check Approved 2/25/2015 ALLEN MANALANSAN
Issued 2/25/2015 LADBS
TCO Issued (Expire Date: 09-05-2017) 3/9/2017 RICKEY JACKSON
TCO Issued (Expire Date: 10-21-2017) 4/24/2017 HAMID PISHEHVAR
TCO Issued (Expire Date: 03-04-2018) 9/5/2017 HENRY BAGHDASSARIAN
TCO Issued (Expire Date: 04-19-2018) 10/21/2017 RICKEY JACKSON
TCO Issued (Expire Date: 08-31-2018) 3/4/2018 HENRY BAGHDASSARIAN
CofO in Progress 4/2/2018 LESLIE TRUJILLO
CofO Issued-Status Void 4/3/2018 HAMID PISHEHVAR
Permit Finaled-Status Void 4/3/2018 HAMID PISHEHVAR
Re-Activate Permit 4/10/2018 RICKEY JACKSON
CofO Corrected-Status Void 4/10/2018 RICKEY JACKSON
Permit Finaled-Status Void 4/10/2018 RICKEY JACKSON
Re-Activate Permit 4/30/2018 RICKEY JACKSON
CofO Corrected 5/9/2018 RICKEY JACKSON
Permit Finaled 5/9/2018 RICKEY JACKSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/17/2013 AVALYN KAMACHI
Address approval Cleared 12/23/2013 ARMENIA HERNANDEZ
Hydrant and Access approval Cleared 1/16/2014 JOHN DALLAS
Construction within easement Cleared 1/29/2014 OSCAR CASTRO
DAS Clearance Cleared 2/5/2014 WAI LAU
Work Adjacent to Public Way Cleared 8/14/2014 ARMENIA HERNANDEZ
Highway dedication Cleared 12/29/2014 ARMENIA HERNANDEZ
"T" removal Cleared 1/16/2015 MARITZA PRZEKOP
CPC Cleared 1/16/2015 MARITZA PRZEKOP
CPC Cleared 1/16/2015 MARITZA PRZEKOP
Frnt yard landscape/Water mgmt Cleared 1/16/2015 MARITZA PRZEKOP
Miscellaneous Cleared 1/16/2015 MARITZA PRZEKOP
Prkng lot landscape/Water mgmt Cleared 1/16/2015 MARITZA PRZEKOP
Tract Map conditions Cleared 1/16/2015 MARITZA PRZEKOP
Tract Map conditions Cleared 1/16/2015 MARITZA PRZEKOP
Tract Map conditions Cleared 1/16/2015 MARITZA PRZEKOP
ZA Case Cleared 1/16/2015 MARITZA PRZEKOP
ZA Case Cleared 1/16/2015 MARITZA PRZEKOP
ZA Case Cleared 1/16/2015 MARITZA PRZEKOP
ZA Case Cleared 1/16/2015 MARITZA PRZEKOP
ZA Case Cleared 1/16/2015 MARITZA PRZEKOP
Driveway location Cleared 1/23/2015 TAIMOUR TANAVOLI
Internal circulation Cleared 1/23/2015 TAIMOUR TANAVOLI
Sewer availability Cleared 1/29/2015 KARAN PATEL
Low Impact Development Cleared 2/10/2015 AMMAR ELTAWIL
Stormwater Pollution Mitigatn Cleared 2/10/2015 AMMAR ELTAWIL
Food Service Establishment Cleared 2/11/2015 WILFREDO VALDEZ
Project located in CRA area Cleared 2/11/2015 JIM URQUHART
Green Code Cleared 2/12/2015 RUSSELL KELLY
"D" conditions Cleared 2/13/2015 MARITZA PRZEKOP
Building over 3-story or 36-ft Cleared 2/13/2015 CALOSHA APPROVED
DAS Clearance Cleared 2/13/2015 WAI LAU
Excavation more than 5-ft deep Cleared 2/13/2015 CALOSHA APPROVED
Permit Cleared 2/13/2015 WESLEY TANIJIRI
Roof/Waste drainage to street Cleared 2/13/2015 WESLEY TANIJIRI
Site Plan review Cleared 2/13/2015 MARITZA PRZEKOP
Tract Map conditions Cleared 2/13/2015 MARITZA PRZEKOP
ZA Case Cleared 2/13/2015 MARITZA PRZEKOP
ZI Cleared 2/13/2015 MARITZA PRZEKOP
ZI Cleared 2/13/2015 MARITZA PRZEKOP
ZI Cleared 2/13/2015 MARITZA PRZEKOP
Title 19 building approval Cleared 2/17/2015 HANI MALKI

Contact Information

Architect Cohen, Andrew Phillip; Lic. No.: C12855 500 S FIGUEROA STREET      LOS ANGELES, CA 90071
Architect Wicksman, Warwick Ian; Lic. No.: C23350 22844 DOLOROSA ST      WOODLAND HILLS, CA 91367
Contractor Webcor Construction L P; Lic. No.: 899242-A 1751 HARBOR BAY PARKWAY #200      ALAMEDA, CA 94502
Engineer Davis, Richard Hays; Lic. No.: C48082 2015 CANTATA DR      LOS ANGELES, CA 90068
Engineer Islam, Mohammed Saiful; Lic. No.: S4083 155 N LAKE AVE SUITE 600      PASADENA, CA 91101
Engineer Tatusian, Sarkis Vortik; Lic. No.: GE2118 24 VISTA DEL SOL      LAGUNA BEACH, CA 92651
Engineer Wahl, Douglas Aaron James; Lic. No.: C74422 10381 MEADS AVE UNIT G      ORANGE, CA 92869
Landscape Architect Packer, Jennifer Leigh; Lic. No.: LA4933 27206 SYCAMORE MEADOW DRIVE      VALENCIA, CA 91381

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 3/16/2015 Partial Approval WILLIAM THOMPSON
Footing/Foundation/Slab 3/18/2015 Partial Approval WILLIAM THOMPSON
SWPPP-Const. Storm Water 3/18/2015 Completed WILLIAM THOMPSON
Footing/Foundation/Slab 3/25/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 3/27/2015 Partial Approval WILLIAM THOMPSON
Footing/Foundation/Slab 4/2/2015 Partial Approval WILLIAM THOMPSON
Deputy Reinf. Concrete 4/3/2015 Conditional Approval WILLIAM THOMPSON
Footing/Foundation/Slab 4/8/2015 Partial Approval WILLIAM THOMPSON
Footing/Foundation/Slab 4/16/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 4/22/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 4/24/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 4/28/2015 Partial Approval WILLIAM THOMPSON
Footing/Foundation/Slab 4/29/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 4/30/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/1/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/5/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/8/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/12/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/14/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/18/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/19/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/20/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/21/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/22/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/28/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 6/2/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 6/10/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 6/11/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 6/12/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 7/1/2015 Partial Approval WILLIAM THOMPSON
Footing/Foundation/Slab 7/8/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 7/9/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 7/15/2015 Partial Approval WILLIAM THOMPSON
Masonry Wall/Backfill 7/22/2015 Partial Approval WILLIAM THOMPSON
Light Gage Steel Frame 7/28/2015 Partial Approval WILLIAM THOMPSON
Masonry Wall/Backfill 7/28/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 7/30/2015 Partial Approval WILLIAM THOMPSON
Light Gage Steel Frame 7/30/2015 Partial Approval WILLIAM THOMPSON
Masonry Wall/Backfill 7/30/2015 Partial Approval WILLIAM THOMPSON
Light Gage Steel Frame 8/7/2015 Partial Approval WILLIAM THOMPSON
Masonry Wall/Backfill 8/7/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 8/12/2015 Partial Approval WILLIAM THOMPSON
Masonry Wall/Backfill 8/12/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 8/17/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 8/20/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 9/1/2015 Partial Approval WILLIAM THOMPSON
Light Gage Steel Frame 9/10/2015 Partial Approval WILLIAM THOMPSON
Light Gage Steel Frame 9/11/2015 Partial Approval WILLIAM THOMPSON
Light Gage Steel Frame 9/14/2015 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/21/2015 Partial Approval WILLIAM THOMPSON
Floor/Roof Diaphrgm/Shear Wall 10/22/2015 Partial Approval WILLIAM THOMPSON
Drywall Nailing 11/19/2015 Partial Approval WILLIAM THOMPSON
Excavation/Setback/Form/Re-Bar 11/19/2015 Partial Approval WILLIAM THOMPSON
Reinforced Concrete Frame 11/19/2015 Partial Approval WILLIAM THOMPSON
SWPPP-Const. Storm Water 11/19/2015 Completed WILLIAM THOMPSON
Verify Sprinkler Sign Off 11/19/2015 Partial Approval WILLIAM THOMPSON
Insulation 11/20/2015 Partial Approval WILLIAM THOMPSON
Drywall Nailing 11/23/2015 Partial Approval WILLIAM THOMPSON
Excavation/Setback/Form/Re-Bar 11/24/2015 Partial Approval WILLIAM THOMPSON
Reinforced Concrete Frame 11/25/2015 Partial Approval WILLIAM THOMPSON
Verify Sprinkler Sign Off 11/25/2015 Partial Approval WILLIAM THOMPSON
Wall Anchors 11/30/2015 Partial Approval SAKO AGHAZARIAN
Reinforced Concrete Frame 12/7/2015 Partial Approval SAKO AGHAZARIAN
Verify Sprinkler Sign Off 12/7/2015 Approved SAKO AGHAZARIAN
Light Gage Steel Frame 2/1/2016 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 2/3/2016 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 2/5/2016 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 2/9/2016 Partial Inspection SAKO AGHAZARIAN
Light Gage Steel Frame 2/26/2016 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 3/10/2016 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 3/31/2016 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 4/8/2016 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 4/21/2016 Partial Approval SAKO AGHAZARIAN
Pre-Inspection 5/3/2016 Partial Inspection SAKO AGHAZARIAN
Light Gage Steel Frame 5/4/2016 Partial Approval SAKO AGHAZARIAN
Insulation 5/5/2016 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 5/10/2016 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 5/10/2016 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 5/20/2016 Partial Approval SAKO AGHAZARIAN
Green Building Rough 5/20/2016 Partial Inspection DONALD CRICHLOW
Insulation 5/20/2016 Partial Approval SAKO AGHAZARIAN
Insulation 6/8/2016 Partial Approval SAKO AGHAZARIAN
Insulation 6/13/2016 Partial Inspection SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 6/29/2016 Partial Inspection SAKO AGHAZARIAN
Light Gage Steel Frame 7/6/2016 Partial Inspection SAKO AGHAZARIAN
Light Gage Steel Frame 7/28/2016 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 8/9/2016 Partial Approval SAKO AGHAZARIAN
Green Building Rough 8/9/2016 Not Ready for Inspection DONALD CRICHLOW
Green Building Rough 8/24/2016 Not Ready for Inspection DONALD CRICHLOW
Insulation 8/24/2016 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 8/24/2016 Partial Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 11/8/2016 Partial Approval SAKO AGHAZARIAN
SWPPP-Const. Storm Water 11/8/2016 Completed SAKO AGHAZARIAN
Light Gage Steel Frame 11/18/2016 Partial Approval SAKO AGHAZARIAN
T-Bar Ceiling 11/29/2016 Partial Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 11/30/2016 Partial Approval SAKO AGHAZARIAN
T-Bar Ceiling 12/5/2016 Partial Approval SAKO AGHAZARIAN
Insulation 1/18/2017 Partial Inspection SAKO AGHAZARIAN
Light Gage Steel Frame 1/18/2017 Partial Inspection SAKO AGHAZARIAN
Pre-Inspection 2/16/2017 Approved SAKO AGHAZARIAN
Pre-Inspection 2/23/2017 Approved SAKO AGHAZARIAN
Pre-Inspection 3/2/2017 Approved SAKO AGHAZARIAN
Green Building Final 3/3/2017 Partial Inspection JOHN KLARIN
Green Building Rough 3/6/2017 Approved JOHN KLARIN
Green Building Final 3/8/2017 Approved JOHN KLARIN
Light Gage Steel Frame 4/5/2017 Approved SAKO AGHAZARIAN
Pre-Inspection 4/19/2017 Partial Approval JAMES POWERS
Drywall Nailing 5/2/2017 Approved SAKO AGHAZARIAN
Final 5/2/2017 Partial Inspection SAKO AGHAZARIAN
Footing/Foundation/Slab 5/2/2017 Approved SAKO AGHAZARIAN
Reinforced Concrete Frame 5/2/2017 Approved SAKO AGHAZARIAN
SGSOV-Seismic Gas S/O Valve 5/2/2017 SGSOV Approved SAKO AGHAZARIAN
SUSMP-Std. Urban Storm Water 5/2/2017 Approved SAKO AGHAZARIAN
Smoke Detectors 5/2/2017 Approved SAKO AGHAZARIAN
Special/Order Compliance 5/10/2017 Approved SAKO AGHAZARIAN
Special/Order Compliance 8/9/2017 Approved SAKO AGHAZARIAN
Special/Order Compliance 2/7/2018 Conditional Approval LESLIE TRUJILLO
Final 3/12/2018 Partial Inspection LESLIE TRUJILLO
SWPPP-Const. Storm Water 3/12/2018 Completed LESLIE TRUJILLO
Final 3/15/2018 Not Ready for Inspection LESLIE TRUJILLO
Final 3/16/2018 Corrections Issued LESLIE TRUJILLO
Special/Order Compliance 3/29/2018 Partial Inspection LESLIE TRUJILLO
Final 4/2/2018 OK to Issue CofO LESLIE TRUJILLO