4920-4920 1/2 E LA CALANDRIA WAY 90032
Certificate Information: 4920-4920 1/2 E LA CALANDRIA WAY 90032
- Application / Permit
- 13010-10005-02132
- Plan Check / Job No.
- B18LA13630
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO 13010-10000-02132 TO CONVERT UNUSED UNDERFLOOR SPACE TO NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229; AND CORRECT STRUCTURAL INVENTORY; CHANGE OF EOR TO AOR
- Permit Issued
- Issued on 5/24/2019
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 7/5/2018 | APPLICANT |
Assigned to Plan Check Engineer | 7/19/2018 | MOHAMMAD FIROUZBAKHT |
Corrections Issued | 7/23/2018 | MOHAMMAD FIROUZBAKHT |
Quality Review Completed | 7/24/2018 | DAVID CHANG |
Building Plans Picked Up | 7/31/2018 | APPLICANT |
Green Plans Picked Up | 7/31/2018 | APPLICANT |
Applicant returned to address corrections | 3/27/2019 | PRANITA SHAH |
Applicant returned to address corrections | 5/8/2019 | PRANITA SHAH |
Plan Check Approved | 5/20/2019 | PRANITA SHAH |
Issued | 5/24/2019 | LADBS |
Permit Finaled | 9/13/2024 | ALIZAH MAYAGOITIA |
Permit Application Clearance Information
Address approval | Cleared | 8/6/2018 | MICHAEL CASTILLO |
Eng Process Fee Ord 176,300 | Cleared | 8/6/2018 | MICHAEL CASTILLO |
Sewer availability | Cleared | 8/6/2018 | MICHAEL CASTILLO |
Street width determination | Cleared | 8/6/2018 | MICHAEL CASTILLO |
Green Code | Cleared | 9/7/2018 | KHEDER ALRAZAA |
Hydrant and Access approval | Cleared | 9/7/2018 | JOHN CONNEALLY |
"D" conditions | Cleared | 2/20/2019 | SANTOS SANCHEZ |
"Q" conditions | Cleared | 2/20/2019 | SANTOS SANCHEZ |
ZI | Cleared | 2/20/2019 | SANTOS SANCHEZ |
GPI Written Notices | Cleared | 5/8/2019 | MOHAMMAD FIROUZBAKHT |
Grading Pre-Inspection | Cleared | 5/8/2019 | MOHAMMAD FIROUZBAKHT |
GPI Written Notices | Cleared | 5/20/2019 | PRANITA SHAH |
Contact Information
Architect | Ian, Marr; Lic. No.: C37239 | 535 W ALLEN AVE #23 SAN DIMAS, CA 91773 |
Contractor | Owner-Builder | , |
Engineer | Lee, Jack C; Lic. No.: GE2153 | 576 E LAMBERT RD BREA, CA 92821 |
Inspector Information
AMY COLIN, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
LILIANA PORTILLO, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
DEVON JACKSON, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
KELVIN MARTINEZ, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
IVAN SARABIA, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
CHRISTOPHER MORFIN, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
ROBERT MAGCALAS, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
GEM DE OCAMPO, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 5/29/2019 | Approved | ENRIQUE MIRELES |
Piling/Pier/Caisson | 9/24/2019 | Approved | ENRIQUE MIRELES |
PLUMBING-Rough | 10/16/2019 | Partial Approval | ENRIQUE MIRELES |
Footing/Foundation/Slab | 10/22/2019 | Approved | ENRIQUE MIRELES |
ELECTRICAL-Rough | 11/25/2019 | Approved | ENRIQUE MIRELES |
PLUMBING-Rough | 12/19/2019 | Corrections Issued | ENRIQUE MIRELES |
PLUMBING-Rough | 1/28/2020 | Approved | ENRIQUE MIRELES |
HVAC-Rough | 2/24/2020 | Approved | ENRIQUE MIRELES |
Insulation | 3/3/2020 | Approved | ENRIQUE MIRELES |
BUILDING-Rough-Frame | 3/24/2020 | Approved | ENRIQUE MIRELES |
Green Building Rough | 3/24/2020 | Approved | ENRIQUE MIRELES |
Verify Sprinkler Sign Off | 3/24/2020 | Approved | ENRIQUE MIRELES |
Drywall Nailing | 6/16/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
Drywall Nailing | 6/18/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
Drywall Nailing | 6/23/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
Drywall Nailing | 7/1/2020 | Approved | CHRISTOPHER DELLEFIELD |
Gas Test | 10/9/2020 | Corrections Issued | CRAIG VAUGHAN |
Interior/Exterior Lathing | 9/3/2021 | Not Ready for Inspection | CALEB MEISTER |
Interior/Exterior Lathing | 9/13/2021 | Approved | JESUS PINEDA |
ELECTRICAL-Final | 12/18/2023 | Not Ready for Inspection | AMY COLIN |
PLUMBING-Final | 12/18/2023 | Approved | AMY COLIN |
ELECTRICAL-Final | 12/20/2023 | Approved | AMY COLIN |
ELECTRICAL-Final | 2/2/2024 | Approved | ALIZAH MAYAGOITIA |
HVAC-Final | 2/13/2024 | Approved | LILIANA PORTILLO |
Final | 9/13/2024 | Permit Finaled | ALIZAH MAYAGOITIA |
Green Building Final | 9/13/2024 | Approved | ALIZAH MAYAGOITIA |
Smoke Detectors | 9/13/2024 | Approved | ALIZAH MAYAGOITIA |