2585 S SEPULVEDA BLVD 90064
Certificate Information: 2585 S SEPULVEDA BLVD 90064
- Application / Permit
- 13010-20000-04681
- Plan Check / Job No.
- B13VN15212
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 2-STORY 7-UNIT APT OVER BASEMENT 7-CAR GARAGE (20% density bonus (one low income), parking reduction option 1 per LAMC 12.22A25)
- Permit Issued
- Issued on 12/30/2014
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/6/2016
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 12/31/2013 | APPLICANT |
Assigned to Plan Check Engineer | 2/20/2014 | NILOOFAR MEHRAIN |
Corrections Issued | 2/28/2014 | NILOOFAR MEHRAIN |
Quality Review Completed | 2/28/2014 | TAMERA SVETICH |
Building Plans Picked Up | 3/12/2014 | APPLICANT |
Disabled Access Plans Picked Up | 3/12/2014 | APPLICANT |
Green Plans Picked Up | 3/12/2014 | APPLICANT |
Applicant returned to address corrections | 4/9/2014 | NILOOFAR MEHRAIN |
Applicant returned to address corrections | 6/12/2014 | NILOOFAR MEHRAIN |
Applicant returned to address corrections | 6/24/2014 | NILOOFAR MEHRAIN |
Applicant returned to address corrections | 8/11/2014 | NILOOFAR MEHRAIN |
Applicant returned to address corrections | 8/27/2014 | NILOOFAR MEHRAIN |
Applicant returned to address corrections | 9/11/2014 | NILOOFAR MEHRAIN |
Applicant returned to address corrections | 9/24/2014 | NILOOFAR MEHRAIN |
Applicant returned to address corrections | 10/2/2014 | NILOOFAR MEHRAIN |
Plan Check Approved | 10/16/2014 | NILOOFAR MEHRAIN |
Issued | 12/30/2014 | LADBS |
CofO in Progress | 6/30/2016 | DERRICK SPENCER |
Permit Finaled | 7/6/2016 | DAVID TSAU |
CofO Issued | 7/6/2016 | DAVID TSAU |
Permit Finaled | 7/6/2016 | DAVID TSAU |
Permit Application Clearance Information
Address approval | Cleared | 4/11/2014 | ANGEL SALCEDO |
Eng Process Fee Ord 176,300 | Cleared | 4/11/2014 | ANGEL SALCEDO |
Metro Rail approval | Cleared | 6/12/2014 | THAN WIN |
Highway dedication | Cleared | 6/19/2014 | OSCAR GUTIERREZ |
Housing rent stabilization | Cleared | 6/19/2014 | CARLOS PELAEZ |
Permit | Cleared | 6/19/2014 | OSCAR GUTIERREZ |
DAS Clearance | Cleared | 6/25/2014 | FARUK SEZER |
Specific Plan | Cleared | 6/30/2014 | PEDRO AYALA |
Grading Pre-Inspection | Cleared | 8/11/2014 | NILOOFAR MEHRAIN |
Mailing Labels | Cleared | 8/11/2014 | NILOOFAR MEHRAIN |
Hydrant and Access approval | Cleared | 8/12/2014 | ROBERT DUFF |
Opn space landscape/Water mgmt | Cleared | 8/12/2014 | DENNIS CHEW |
Excavation more than 5-ft deep | Cleared | 8/27/2014 | CALOSHA APPROVED |
Green Code | Cleared | 9/18/2014 | MICHAEL AYERS |
Low Impact Development | Cleared | 9/18/2014 | AYMAN JABBOURI |
Roof/Waste drainage to street | Cleared | 9/18/2014 | SANDRA FIGUEROA |
Sewer availability | Cleared | 9/18/2014 | SANDRA FIGUEROA |
Housing density bonus | Cleared | 10/10/2014 | MARITES CUNANAN |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Basma, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 3/10/2015 | Corrections Issued | TERRY DRIBIN |
METHANE-Barrier | 3/10/2015 | Not Ready for Inspection | TERRY DRIBIN |
METHANE-Subgrade | 3/10/2015 | Not Ready for Inspection | TERRY DRIBIN |
Footing/Foundation/Slab | 3/16/2015 | Partial Approval | JASON MARKOWSKI |
METHANE-Barrier | 3/16/2015 | Partial Approval | JASON MARKOWSKI |
METHANE-Subgrade | 3/16/2015 | Partial Approval | JASON MARKOWSKI |
Deputy Reinf. Concrete | 7/13/2015 | Approved | DERRICK SPENCER |
Deputy Wood Construction | 8/5/2015 | Approved | DERRICK SPENCER |
METHANE-Rough | 8/12/2015 | Approved | DERRICK SPENCER |
Verify Sprinkler Sign Off | 8/12/2015 | Not Ready for Inspection | DERRICK SPENCER |
Wood Frame | 8/12/2015 | Partial Approval | DERRICK SPENCER |
Verify Sprinkler Sign Off | 8/28/2015 | Not Ready for Inspection | DERRICK SPENCER |
Wood Frame | 8/28/2015 | Partial Approval | DERRICK SPENCER |
Green Building Rough | 9/18/2015 | Not Ready for Inspection | DONALD CRICHLOW |
Verify Sprinkler Sign Off | 9/18/2015 | Not Ready for Inspection | DERRICK SPENCER |
Wood Frame | 9/18/2015 | Partial Approval | DERRICK SPENCER |
Footing/Foundation/Slab | 9/29/2015 | Partial Approval | DERRICK SPENCER |
METHANE-Barrier | 9/29/2015 | Approved | DERRICK SPENCER |
METHANE-Subgrade | 9/29/2015 | Approved | DERRICK SPENCER |
Green Building Rough | 10/21/2015 | Partial Inspection | BRYAN MEYER |
Verify Sprinkler Sign Off | 10/21/2015 | Not Ready for Inspection | DERRICK SPENCER |
Wood Frame | 10/21/2015 | Partial Approval | DERRICK SPENCER |
Green Building Rough | 12/8/2015 | Partial Approval | BRYAN MEYER |
Verify Sprinkler Sign Off | 12/14/2015 | Not Ready for Inspection | DERRICK SPENCER |
Wood Frame | 12/14/2015 | Partial Approval | DERRICK SPENCER |
Insulation | 12/17/2015 | Partial Approval | DERRICK SPENCER |
Drywall Nailing | 12/23/2015 | Partial Approval | MAURICE MARTINEZ |
Verify Sprinkler Sign Off | 1/21/2016 | Not Ready for Inspection | DERRICK SPENCER |
Wood Frame | 1/21/2016 | Partial Approval | DERRICK SPENCER |
Drywall Nailing | 1/28/2016 | Partial Approval | DERRICK SPENCER |
Final | 3/16/2016 | Partial Inspection | DANIEL MC AULIFFE |
Interior/Exterior Lathing | 3/17/2016 | Not Ready for Inspection | JASON MARKOWSKI |
Interior/Exterior Lathing | 3/21/2016 | Approved | DERRICK SPENCER |
Drywall Nailing | 5/24/2016 | Not Ready for Inspection | DERRICK SPENCER |
Final | 5/24/2016 | Not Ready for Inspection | DERRICK SPENCER |
Footing/Foundation/Slab | 5/24/2016 | Approved | DERRICK SPENCER |
Green Building Rough | 5/24/2016 | Partial Inspection | BRYAN MEYER |
Reinforced Concrete Frame | 5/24/2016 | Approved | DERRICK SPENCER |
SGSOV-Seismic Gas S/O Valve | 5/24/2016 | SGSOV Approved | DERRICK SPENCER |
Smoke Detectors | 5/24/2016 | Approved | DERRICK SPENCER |
Verify Sprinkler Sign Off | 5/24/2016 | Approved | DERRICK SPENCER |
Wood Frame | 5/24/2016 | Approved | DERRICK SPENCER |
Green Building Final | 6/2/2016 | Partial Approval | BRYAN MEYER |
Green Building Final | 6/6/2016 | Approved | BRYAN MEYER |
Drywall Nailing | 6/8/2016 | Approved | DERRICK SPENCER |
Final | 6/8/2016 | OK to Issue CofO | DERRICK SPENCER |
Green Building Rough | 6/8/2016 | Approved | BRYAN MEYER |
Reinforced Concrete Frame | 6/8/2016 | Approved | DERRICK SPENCER |
Wood Frame | 6/8/2016 | Approved | DERRICK SPENCER |