2585 S SEPULVEDA BLVD 90064

Certificate Information: 2585 S SEPULVEDA BLVD 90064

Application / Permit
13010-20000-04681
Plan Check / Job No.
B13VN15212
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 2-STORY 7-UNIT APT OVER BASEMENT 7-CAR GARAGE (20% density bonus (one low income), parking reduction option 1 per LAMC 12.22A25)
Permit Issued
Issued on 12/30/2014
Issuing Office
Valley
Current Status
CofO Issued on 7/6/2016
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2013 APPLICANT
Assigned to Plan Check Engineer 2/20/2014 NILOOFAR MEHRAIN
Corrections Issued 2/28/2014 NILOOFAR MEHRAIN
Quality Review Completed 2/28/2014 TAMERA SVETICH
Building Plans Picked Up 3/12/2014 APPLICANT
Disabled Access Plans Picked Up 3/12/2014 APPLICANT
Green Plans Picked Up 3/12/2014 APPLICANT
Applicant returned to address corrections 4/9/2014 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/12/2014 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/24/2014 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/11/2014 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/27/2014 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/11/2014 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/24/2014 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/2/2014 NILOOFAR MEHRAIN
Plan Check Approved 10/16/2014 NILOOFAR MEHRAIN
Issued 12/30/2014 LADBS
CofO in Progress 6/30/2016 DERRICK SPENCER
Permit Finaled 7/6/2016 DAVID TSAU
CofO Issued 7/6/2016 DAVID TSAU
Permit Finaled 7/6/2016 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 4/11/2014 ANGEL SALCEDO
Eng Process Fee Ord 176,300 Cleared 4/11/2014 ANGEL SALCEDO
Metro Rail approval Cleared 6/12/2014 THAN WIN
Highway dedication Cleared 6/19/2014 OSCAR GUTIERREZ
Housing rent stabilization Cleared 6/19/2014 CARLOS PELAEZ
Permit Cleared 6/19/2014 OSCAR GUTIERREZ
DAS Clearance Cleared 6/25/2014 FARUK SEZER
Specific Plan Cleared 6/30/2014 PEDRO AYALA
Grading Pre-Inspection Cleared 8/11/2014 NILOOFAR MEHRAIN
Mailing Labels Cleared 8/11/2014 NILOOFAR MEHRAIN
Hydrant and Access approval Cleared 8/12/2014 ROBERT DUFF
Opn space landscape/Water mgmt Cleared 8/12/2014 DENNIS CHEW
Excavation more than 5-ft deep Cleared 8/27/2014 CALOSHA APPROVED
Green Code Cleared 9/18/2014 MICHAEL AYERS
Low Impact Development Cleared 9/18/2014 AYMAN JABBOURI
Roof/Waste drainage to street Cleared 9/18/2014 SANDRA FIGUEROA
Sewer availability Cleared 9/18/2014 SANDRA FIGUEROA
Housing density bonus Cleared 10/10/2014 MARITES CUNANAN

Contact Information

Contractor Owner-Builder       ,
Engineer Basma, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/10/2015 Corrections Issued TERRY DRIBIN
METHANE-Barrier 3/10/2015 Not Ready for Inspection TERRY DRIBIN
METHANE-Subgrade 3/10/2015 Not Ready for Inspection TERRY DRIBIN
Footing/Foundation/Slab 3/16/2015 Partial Approval JASON MARKOWSKI
METHANE-Barrier 3/16/2015 Partial Approval JASON MARKOWSKI
METHANE-Subgrade 3/16/2015 Partial Approval JASON MARKOWSKI
Deputy Reinf. Concrete 7/13/2015 Approved DERRICK SPENCER
Deputy Wood Construction 8/5/2015 Approved DERRICK SPENCER
METHANE-Rough 8/12/2015 Approved DERRICK SPENCER
Verify Sprinkler Sign Off 8/12/2015 Not Ready for Inspection DERRICK SPENCER
Wood Frame 8/12/2015 Partial Approval DERRICK SPENCER
Verify Sprinkler Sign Off 8/28/2015 Not Ready for Inspection DERRICK SPENCER
Wood Frame 8/28/2015 Partial Approval DERRICK SPENCER
Green Building Rough 9/18/2015 Not Ready for Inspection DONALD CRICHLOW
Verify Sprinkler Sign Off 9/18/2015 Not Ready for Inspection DERRICK SPENCER
Wood Frame 9/18/2015 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 9/29/2015 Partial Approval DERRICK SPENCER
METHANE-Barrier 9/29/2015 Approved DERRICK SPENCER
METHANE-Subgrade 9/29/2015 Approved DERRICK SPENCER
Green Building Rough 10/21/2015 Partial Inspection BRYAN MEYER
Verify Sprinkler Sign Off 10/21/2015 Not Ready for Inspection DERRICK SPENCER
Wood Frame 10/21/2015 Partial Approval DERRICK SPENCER
Green Building Rough 12/8/2015 Partial Approval BRYAN MEYER
Verify Sprinkler Sign Off 12/14/2015 Not Ready for Inspection DERRICK SPENCER
Wood Frame 12/14/2015 Partial Approval DERRICK SPENCER
Insulation 12/17/2015 Partial Approval DERRICK SPENCER
Drywall Nailing 12/23/2015 Partial Approval MAURICE MARTINEZ
Verify Sprinkler Sign Off 1/21/2016 Not Ready for Inspection DERRICK SPENCER
Wood Frame 1/21/2016 Partial Approval DERRICK SPENCER
Drywall Nailing 1/28/2016 Partial Approval DERRICK SPENCER
Final 3/16/2016 Partial Inspection DANIEL MC AULIFFE
Interior/Exterior Lathing 3/17/2016 Not Ready for Inspection JASON MARKOWSKI
Interior/Exterior Lathing 3/21/2016 Approved DERRICK SPENCER
Drywall Nailing 5/24/2016 Not Ready for Inspection DERRICK SPENCER
Final 5/24/2016 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 5/24/2016 Approved DERRICK SPENCER
Green Building Rough 5/24/2016 Partial Inspection BRYAN MEYER
Reinforced Concrete Frame 5/24/2016 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 5/24/2016 SGSOV Approved DERRICK SPENCER
Smoke Detectors 5/24/2016 Approved DERRICK SPENCER
Verify Sprinkler Sign Off 5/24/2016 Approved DERRICK SPENCER
Wood Frame 5/24/2016 Approved DERRICK SPENCER
Green Building Final 6/2/2016 Partial Approval BRYAN MEYER
Green Building Final 6/6/2016 Approved BRYAN MEYER
Drywall Nailing 6/8/2016 Approved DERRICK SPENCER
Final 6/8/2016 OK to Issue CofO DERRICK SPENCER
Green Building Rough 6/8/2016 Approved BRYAN MEYER
Reinforced Concrete Frame 6/8/2016 Approved DERRICK SPENCER
Wood Frame 6/8/2016 Approved DERRICK SPENCER