7329 S TRASK AVE 90293
Certificate Information: 7329 S TRASK AVE 90293
- Application / Permit
- 14010-10000-01402
- Plan Check / Job No.
- B14LA05905
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE.
- Permit Issued
- Issued on 8/24/2016
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/2/2019
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 5/7/2014 | APPLICANT |
Assigned to Plan Check Engineer | 5/29/2014 | ANKIT PATEL |
Corrections Issued | 6/9/2014 | ANKIT PATEL |
Quality Review Completed | 6/10/2014 | GARO TELMI |
Building Plans Picked Up | 6/13/2014 | APPLICANT |
Green Plans Picked Up | 6/13/2014 | APPLICANT |
Applicant returned to address corrections | 10/21/2014 | ANKIT PATEL |
Plan Check Approved | 6/15/2016 | PRANITA SHAH |
Issued | 8/24/2016 | LADBS |
CofO in Progress | 1/18/2019 | RONALD WEBER |
Permit Finaled | 2/2/2019 | DANIEL ORRANTE |
CofO Issued | 2/2/2019 | DANIEL ORRANTE |
Permit Finaled | 2/2/2019 | DANIEL ORRANTE |
Permit Application Clearance Information
Eng Process Fee Ord 176,300 | Cleared | 10/20/2014 | AVALYN KAMACHI |
Green Code | Cleared | 10/20/2014 | ROLLIN GETTLE III |
Hydrant and Access approval | Cleared | 10/20/2014 | ROBERT DUFF |
Permit | Cleared | 10/20/2014 | AVALYN KAMACHI |
Sewer availability | Cleared | 10/20/2014 | AVALYN KAMACHI |
Low Impact Development | Cleared | 3/11/2016 | MICHAEL SCADUTO |
Roof/Waste drainage to street | Cleared | 3/11/2016 | ARNULFO NUNO |
Coastal Zone | Cleared | 6/8/2016 | BRIDGETTE WOOTEN |
Contact Information
Architect | Gregory, William Lawrence; Lic. No.: C24302 | 5555 W 76TH STREET LOS ANGELES, CA 90045 |
Contractor | F S Design & Construction Inc; Lic. No.: 727272-B | 19625 VENTURA BLVD STE 200 TARZANA, CA 91356 |
Engineer | Mccullum, Eric William; Lic. No.: C68850 | 880 MANHATTAN BEACH BLVD 202 MANHATTAN BEACH, CA 90266 |
Inspector Information
JESUS PINEDA, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
JAYLIN GRAVITTE, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 11/7/2016 | Conditional Approval | RONALD WEBER |
METHANE-Barrier | 11/7/2016 | Partial Inspection | RONALD WEBER |
METHANE-Subgrade | 11/7/2016 | Conditional Approval | RONALD WEBER |
Floor/Roof Diaphrgm/Shear Wall | 12/1/2016 | Approved | RONALD WEBER |
PLUMBING-Rough | 12/1/2016 | Approved | RONALD WEBER |
Floor/Roof Diaphrgm/Shear Wall | 12/2/2016 | Approved | RONALD WEBER |
METHANE-Barrier | 12/2/2016 | Partial Inspection | RONALD WEBER |
METHANE-Subgrade | 12/2/2016 | Partial Inspection | RONALD WEBER |
Drywall Nailing | 12/6/2016 | No Access for Inspection | RONALD WEBER |
Green Building Rough | 12/6/2016 | Not Ready for Inspection | RONALD WEBER |
Drywall Nailing | 12/14/2016 | Not Ready for Inspection | RONALD WEBER |
Floor/Roof Diaphrgm/Shear Wall | 12/14/2016 | Approved | RONALD WEBER |
Floor/Roof Diaphrgm/Shear Wall | 1/24/2017 | Approved | RONALD WEBER |
Floor/Roof Diaphrgm/Shear Wall | 4/24/2017 | Approved | RONALD WEBER |
HVAC-Rough | 4/24/2017 | Not Ready for Inspection | RONALD WEBER |
HVAC-Rough | 5/18/2017 | Not Ready for Inspection | RONALD WEBER |
Interior/Exterior Lathing | 5/18/2017 | Not Ready for Inspection | RONALD WEBER |
HVAC-Rough | 5/19/2017 | Approved | RONALD WEBER |
Interior/Exterior Lathing | 5/19/2017 | Approved | RONALD WEBER |
ELECTRICAL-Rough | 6/15/2017 | Approved | RONALD WEBER |
PLUMBING-Rough | 6/15/2017 | Approved | RONALD WEBER |
BUILDING-Rough-Frame | 6/22/2017 | Not Ready for Inspection | CRAIG DAVIS |
Gas Test | 6/22/2017 | Not Ready for Inspection | CRAIG DAVIS |
Green Building Rough | 6/22/2017 | Not Ready for Inspection | CRAIG DAVIS |
METHANE-Rough | 6/22/2017 | Not Ready for Inspection | CRAIG DAVIS |
Verify Sprinkler Sign Off | 6/22/2017 | Not Ready for Inspection | CRAIG DAVIS |
BUILDING-Rough-Frame | 7/3/2017 | Conditional Approval | RONALD WEBER |
Green Building Rough | 7/3/2017 | Approved | RONALD WEBER |
METHANE-Rough | 7/3/2017 | Partial Inspection | RONALD WEBER |
Verify Sprinkler Sign Off | 7/3/2017 | Approved | RONALD WEBER |
Insulation | 7/18/2017 | Approved | RONALD WEBER |
Shower Pan | 7/18/2017 | Approved | RONALD WEBER |
Drywall Nailing | 8/2/2017 | Approved | RONALD WEBER |
Shower Pan | 8/4/2017 | Approved | RONALD WEBER |
Interior/Exterior Lathing | 8/11/2017 | Approved | RONALD WEBER |
ELECTRICAL-Final | 6/22/2018 | Not Ready for Inspection | RONALD WEBER |
Service/Power Release | 6/22/2018 | Approved | RONALD WEBER |
Gas Test | 8/9/2018 | Approved | RONALD WEBER |
SGSOV-Seismic Gas S/O Valve | 8/9/2018 | SGSOV Not Ready | RONALD WEBER |
BUILDING-Rough-Frame | 8/10/2018 | Approved | RONALD WEBER |
Final | 8/10/2018 | Not Ready for Inspection | RONALD WEBER |
Footing/Foundation/Slab | 8/10/2018 | Approved | RONALD WEBER |
Green Building Final | 8/10/2018 | Not Ready for Inspection | RONALD WEBER |
METHANE-Barrier | 8/10/2018 | Approved | RONALD WEBER |
METHANE-Final | 8/10/2018 | Approved | RONALD WEBER |
METHANE-Rough | 8/10/2018 | Approved | RONALD WEBER |
METHANE-Subgrade | 8/10/2018 | Approved | RONALD WEBER |
Smoke Detectors | 8/10/2018 | Approved | RONALD WEBER |
Final | 8/27/2018 | Not Ready for Inspection | RONALD WEBER |
Green Building Final | 8/27/2018 | Corrections Issued | RONALD WEBER |
SGSOV-Seismic Gas S/O Valve | 8/27/2018 | SGSOV Approved | RONALD WEBER |
Final | 11/2/2018 | Conditional Approval | RONALD WEBER |
Green Building Final | 11/2/2018 | Approved | RONALD WEBER |
ELECTRICAL-Final | 1/17/2019 | Approved | RONALD WEBER |
Final | 1/17/2019 | OK to Issue CofO | RONALD WEBER |
HVAC-Final | 1/17/2019 | Approved | RONALD WEBER |
PLUMBING-Final | 1/17/2019 | Approved | RONALD WEBER |