Excavation/Setback/Form/Re-Bar
|
5/17/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
5/23/2017
|
Approved
|
NICK LAROCCA
|
Excavation/Setback/Form/Re-Bar
|
5/23/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
5/24/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
6/1/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
6/1/2017
|
Partial Approval
|
NICK LAROCCA
|
METHANE-Barrier
|
6/1/2017
|
Not Ready for Inspection
|
NICK LAROCCA
|
METHANE-Subgrade
|
6/1/2017
|
Not Ready for Inspection
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
6/5/2017
|
Partial Approval
|
NICK LAROCCA
|
METHANE-Barrier
|
6/5/2017
|
Not Ready for Inspection
|
NICK LAROCCA
|
METHANE-Subgrade
|
6/5/2017
|
Not Ready for Inspection
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
6/6/2017
|
Approved
|
NICK LAROCCA
|
Deputy Shotcrete
|
6/8/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
6/8/2017
|
Partial Approval
|
NICK LAROCCA
|
METHANE-Barrier
|
6/8/2017
|
Not Ready for Inspection
|
NICK LAROCCA
|
METHANE-Subgrade
|
6/8/2017
|
Not Ready for Inspection
|
NICK LAROCCA
|
Deputy Shotcrete
|
6/9/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
6/12/2017
|
Approved
|
NICK LAROCCA
|
Deputy Shotcrete
|
6/12/2017
|
Approved
|
NICK LAROCCA
|
Deputy Shotcrete
|
6/13/2017
|
Approved
|
NICK LAROCCA
|
Deputy Shotcrete
|
6/14/2017
|
Approved
|
NICK LAROCCA
|
METHANE-Rough
|
6/14/2017
|
Not Ready for Inspection
|
NICK LAROCCA
|
Reinforced Concrete Frame
|
6/14/2017
|
Partial Approval
|
NICK LAROCCA
|
Verify Sprinkler Sign Off
|
6/14/2017
|
Not Ready for Inspection
|
NICK LAROCCA
|
Deputy Shotcrete
|
6/15/2017
|
Approved
|
NICK LAROCCA
|
Deputy Shotcrete
|
6/16/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
6/19/2017
|
Approved
|
NICK LAROCCA
|
Deputy Shotcrete
|
6/19/2017
|
Approved
|
NICK LAROCCA
|
Deputy Other (see comments)
|
6/20/2017
|
Approved
|
NICK LAROCCA
|
Deputy Shotcrete
|
6/20/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
6/21/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
6/22/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
6/23/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
6/26/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
6/27/2017
|
Approved
|
NICK LAROCCA
|
Masonry Wall/Backfill
|
6/27/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
6/28/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
7/13/2017
|
Partial Approval
|
NICK LAROCCA
|
METHANE-Barrier
|
7/13/2017
|
Approved
|
NICK LAROCCA
|
METHANE-Subgrade
|
7/13/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
7/18/2017
|
Approved
|
NICK LAROCCA
|
Masonry Wall/Backfill
|
7/18/2017
|
Corrections Issued
|
NICK LAROCCA
|
Masonry Wall/Backfill
|
8/2/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
8/10/2017
|
Conditional Approval
|
JONATHAN ALLEN
|
Green Building Rough
|
8/16/2017
|
Not Ready for Inspection
|
BRYAN MEYER
|
METHANE-Rough
|
8/16/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
8/18/2017
|
Approved
|
NICK LAROCCA
|
Excavation/Setback/Form/Re-Bar
|
8/18/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
8/22/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
8/23/2017
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
9/26/2017
|
Partial Inspection
|
NICK LAROCCA
|
Deputy Wood Construction
|
9/27/2017
|
Approved
|
NICK LAROCCA
|
Deputy Wood Construction
|
10/3/2017
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
10/3/2017
|
Partial Inspection
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
10/3/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Wood Construction
|
10/4/2017
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
10/5/2017
|
Not Ready for Inspection
|
NICK LAROCCA
|
Deputy Wood Construction
|
10/6/2017
|
Approved
|
NICK LAROCCA
|
Deputy Wood Construction
|
10/13/2017
|
Approved
|
NICK LAROCCA
|
Deputy Wood Construction
|
10/20/2017
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
10/20/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Wood Construction
|
10/25/2017
|
Approved
|
NICK LAROCCA
|
Deputy Wood Construction
|
11/17/2017
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
11/17/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Wood Construction
|
11/20/2017
|
Approved
|
NICK LAROCCA
|
Wood Frame
|
11/20/2017
|
Partial Inspection
|
NICK LAROCCA
|
Deputy Wood Construction
|
12/19/2017
|
Approved
|
NICK LAROCCA
|
Deputy Wood Construction
|
1/18/2018
|
Corrections Issued
|
NICK LAROCCA
|
Deputy Wood Construction
|
2/7/2018
|
Conditional Approval
|
NICK LAROCCA
|
Green Building Rough
|
2/8/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Verify Sprinkler Sign Off
|
2/8/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Wood Frame
|
2/8/2018
|
Partial Inspection
|
NICK LAROCCA
|
Deputy Wood Construction
|
2/16/2018
|
Conditional Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
2/16/2018
|
Partial Inspection
|
NICK LAROCCA
|
Deputy Wood Construction
|
2/22/2018
|
Conditional Approval
|
NICK LAROCCA
|
Deputy Wood Construction
|
2/23/2018
|
Conditional Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
3/1/2018
|
Partial Inspection
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
3/2/2018
|
Partial Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
5/2/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Pre-Inspection
|
5/2/2018
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
5/3/2018
|
Partial Approval
|
NICK LAROCCA
|
Pre-Inspection
|
5/3/2018
|
Approved
|
NICK LAROCCA
|
Deputy Wood Construction
|
5/17/2018
|
Conditional Approval
|
NICK LAROCCA
|
Green Building Rough
|
6/7/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Wood Frame
|
6/7/2018
|
Corrections Issued
|
NICK LAROCCA
|
Wood Frame
|
6/22/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
6/29/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
7/3/2018
|
Partial Approval
|
DERRICK SPENCER
|
Pre-Inspection
|
7/3/2018
|
Approved
|
DERRICK SPENCER
|
Insulation
|
7/5/2018
|
Corrections Issued
|
NICK LAROCCA
|
Insulation
|
7/6/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
7/9/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
7/12/2018
|
Partial Approval
|
NICK LAROCCA
|
Wood Frame
|
7/25/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
7/31/2018
|
Partial Inspection
|
NICK LAROCCA
|
T-Bar Ceiling
|
7/31/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Wood Frame
|
7/31/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
8/2/2018
|
Partial Approval
|
NICK LAROCCA
|
Wood Frame
|
8/2/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
8/7/2018
|
No Access for Inspection
|
NICK LAROCCA
|
Wood Frame
|
8/9/2018
|
Partial Approval
|
NICK LAROCCA
|
Drywall Nailing
|
8/14/2018
|
Partial Approval
|
DERRICK SPENCER
|
Green Building Rough
|
8/14/2018
|
Approved
|
DERRICK SPENCER
|
Insulation
|
8/28/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
8/30/2018
|
Partial Approval
|
NICK LAROCCA
|
Interior/Exterior Lathing
|
8/31/2018
|
Approved
|
NICK LAROCCA
|
Drywall Nailing
|
9/5/2018
|
Partial Approval
|
NICK LAROCCA
|
Drywall Nailing
|
9/14/2018
|
Partial Inspection
|
NICK LAROCCA
|
Wood Frame
|
9/14/2018
|
Corrections Issued
|
NICK LAROCCA
|
Drywall Nailing
|
9/25/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Insulation
|
9/25/2018
|
Partial Inspection
|
NICK LAROCCA
|
Verify Sprinkler Sign Off
|
10/2/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Wood Frame
|
10/2/2018
|
Corrections Issued
|
NICK LAROCCA
|
Drywall Nailing
|
10/10/2018
|
Partial Approval
|
DERRICK SPENCER
|
Insulation
|
10/10/2018
|
Partial Approval
|
DERRICK SPENCER
|
Insulation
|
10/17/2018
|
Partial Approval
|
DERRICK SPENCER
|
T-Bar Ceiling
|
10/17/2018
|
Partial Approval
|
DERRICK SPENCER
|
Insulation
|
10/19/2018
|
Partial Approval
|
NICK LAROCCA
|
T-Bar Ceiling
|
10/19/2018
|
Partial Approval
|
NICK LAROCCA
|
Drywall Nailing
|
10/24/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
10/24/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Insulation
|
10/25/2018
|
Approved
|
NICK LAROCCA
|
Drywall Nailing
|
11/1/2018
|
Partial Approval
|
NICK LAROCCA
|
Interior/Exterior Lathing
|
11/13/2018
|
Approved
|
NICK LAROCCA
|
Wood Frame
|
11/21/2018
|
Partial Approval
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
2/7/2019
|
Corrections Issued
|
NICK LAROCCA
|
Excavation/Setback/Form/Re-Bar
|
4/2/2019
|
Partial Approval
|
NICK LAROCCA
|
Masonry Wall/Backfill
|
4/8/2019
|
Partial Approval
|
NICK LAROCCA
|
Pre-Inspection
|
5/17/2019
|
Not Ready for Inspection
|
TONY HARTONO
|
Pre-Inspection
|
5/21/2019
|
Corrections Issued
|
NICK LAROCCA
|
Pre-Inspection
|
8/9/2019
|
Corrections Issued
|
NICK LAROCCA
|
Light Gage Steel Frame
|
8/14/2019
|
Partial Approval
|
NICK LAROCCA
|
Drywall Nailing
|
8/20/2019
|
Approved
|
NICK LAROCCA
|
Final
|
8/30/2019
|
Not Ready for Inspection
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
8/30/2019
|
Not Ready for Inspection
|
NICK LAROCCA
|
Green Building Final
|
8/30/2019
|
Approved
|
NICK LAROCCA
|
Reinforced Concrete Frame
|
8/30/2019
|
Not Ready for Inspection
|
NICK LAROCCA
|
Reinforced Masonry Frame
|
8/30/2019
|
Not Ready for Inspection
|
NICK LAROCCA
|
SGSOV-Seismic Gas S/O Valve
|
8/30/2019
|
SGSOV Approved
|
NICK LAROCCA
|
Smoke Detectors
|
8/30/2019
|
Approved
|
NICK LAROCCA
|
Structural Steel Frame
|
8/30/2019
|
Approved
|
NICK LAROCCA
|
Verify Sprinkler Sign Off
|
8/30/2019
|
Approved
|
NICK LAROCCA
|
Wood Frame
|
8/30/2019
|
Not Ready for Inspection
|
NICK LAROCCA
|
Final
|
9/17/2019
|
Partial Inspection
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
9/17/2019
|
Approved
|
NICK LAROCCA
|
Reinforced Concrete Frame
|
9/17/2019
|
Approved
|
NICK LAROCCA
|
Reinforced Masonry Frame
|
9/17/2019
|
Not Ready for Inspection
|
NICK LAROCCA
|
Wood Frame
|
9/17/2019
|
Not Ready for Inspection
|
NICK LAROCCA
|
Final
|
9/20/2019
|
Not Ready for Inspection
|
NICK LAROCCA
|
Reinforced Masonry Frame
|
9/20/2019
|
Not Ready for Inspection
|
NICK LAROCCA
|
Wood Frame
|
9/20/2019
|
Not Ready for Inspection
|
NICK LAROCCA
|
Final
|
10/3/2019
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Reinforced Masonry Frame
|
10/3/2019
|
Approved
|
DERRICK SPENCER
|
Wood Frame
|
10/3/2019
|
Approved
|
DERRICK SPENCER
|
Final
|
10/10/2019
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Final
|
10/16/2019
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Final
|
10/21/2019
|
Partial Approval
|
DERRICK SPENCER
|
Final
|
10/28/2019
|
Not Ready for Inspection
|
NICK LAROCCA
|
Final
|
10/30/2019
|
Partial Inspection
|
NICK LAROCCA
|
Light Gage Steel Frame
|
11/1/2019
|
Partial Approval
|
NICK LAROCCA
|
Final
|
11/6/2019
|
Partial Approval
|
NICK LAROCCA
|