1050 S GRAND AVE 90015

Certificate Information: 1050 S GRAND AVE 90015

Application / Permit
14010-10000-02426
Plan Check / Job No.
B14LA10143
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 22 story above grade 151 residential apartment units high-rise building (Type 1A construction) with 5,672 sf of commercial at grade level, 4 level above grade parkings and three level subterranean parkings. (Core-Shell for 2 penthouse units on Level 21&22 per bulletin 008)
Permit Issued
Issued on 6/9/2015
Issuing Office
Metro
Current Status
CofO Issued on 10/24/2017
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2014 APPLICANT
Assigned to Plan Check Engineer 8/28/2014 SUEN LIEU
Corrections Issued 9/10/2014 SUEN LIEU
Quality Review Completed 9/15/2014 CHARLES CHANG
Building Plans Picked Up 9/15/2014 APPLICANT
Applicant returned to address corrections 11/21/2014 SUEN LIEU
Applicant returned to address corrections 1/21/2015 SUEN LIEU
Applicant returned to address corrections 2/19/2015 SUEN LIEU
Applicant returned to address corrections 2/27/2015 SUEN LIEU
Applicant returned to address corrections 3/2/2015 SUEN LIEU
Applicant returned to address corrections 3/13/2015 SUEN LIEU
Applicant returned to address corrections 3/27/2015 SUEN LIEU
Applicant returned to address corrections 4/3/2015 SUEN LIEU
Applicant returned to address corrections 4/13/2015 SUEN LIEU
Applicant returned to address corrections 4/24/2015 SUEN LIEU
Applicant returned to address corrections 5/1/2015 SUEN LIEU
Applicant returned to address corrections 5/14/2015 SUEN LIEU
Applicant returned to address corrections 5/20/2015 SUEN LIEU
Applicant returned to address corrections 5/22/2015 SUEN LIEU
Applicant returned to address corrections 5/28/2015 SUEN LIEU
Applicant returned to address corrections 6/5/2015 SUEN LIEU
Plan Check Approved 6/9/2015 SUEN LIEU
Issued 6/9/2015 LADBS
TCO Issued (Expire Date: 08-15-2017) 2/16/2017 RICKEY JACKSON
TCO Issued (Expire Date: 02-11-2018) 8/15/2017 RICKEY JACKSON
CofO in Progress 10/5/2017 LESLIE TRUJILLO
Permit Finaled 10/24/2017 HAMID PISHEHVAR
CofO Issued 10/24/2017 HAMID PISHEHVAR
Permit Finaled 10/24/2017 HAMID PISHEHVAR

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/3/2014 ARMENIA HERNANDEZ
Highway dedication Cleared 12/18/2014 ARMENIA HERNANDEZ
Permit Cleared 12/18/2014 ARMENIA HERNANDEZ
Project located in CRA area Cleared 3/25/2015 JIM URQUHART
Low Impact Development Cleared 4/16/2015 IDA MEISAMI-FARD
Stormwater Pollution Mitigatn Cleared 4/16/2015 IDA MEISAMI-FARD
Internal circulation Cleared 4/17/2015 TAIMOUR TANAVOLI
Sewer availability Cleared 4/21/2015 ARMENIA HERNANDEZ
Roof/Waste drainage to street Cleared 4/23/2015 ARMENIA HERNANDEZ
Abandoned oil well Cleared 4/27/2015 JOHN DALLAS
Abandoned oil well approval Cleared 4/27/2015 JOHN DALLAS
Hydrant and Access approval Cleared 4/27/2015 JOHN DALLAS
"D" conditions Cleared 4/29/2015 MARITZA PRZEKOP
"Q" conditions Cleared 4/29/2015 MARITZA PRZEKOP
Opn space landscape/Water mgmt Cleared 4/29/2015 MARITZA PRZEKOP
Site Plan review Cleared 4/29/2015 MARITZA PRZEKOP
Tract Map conditions Cleared 4/29/2015 MARITZA PRZEKOP
ZA Case Cleared 4/29/2015 MARITZA PRZEKOP
ZA Case Cleared 4/29/2015 MARITZA PRZEKOP
Green Code Cleared 5/1/2015 MARCUS LEVIAS
Fire Marshall Fire Life Safety Cleared 5/14/2015 DAVE MYERS
Methane Ordinance Cleared 5/14/2015 DAVE MYERS
DAS Clearance Cleared 5/20/2015 SUEN LIEU
Encroachment in public way Cleared 5/21/2015 ARMENIA HERNANDEZ
Building over 3-story or 36-ft Cleared 5/22/2015 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 5/22/2015 CALOSHA APPROVED
Miscellaneous Cleared 5/28/2015 MARITZA PRZEKOP

Contact Information

Architect Metzger, George Russell; Lic. No.: C21930 17383 SUNSET BLVD.      PACIFIC PALISADES, CA 90272
Contractor Lend Lease (Us) Construction Inc; Lic. No.: 483550-B 200 PARK AVENUE 9TH FLOOR   ATTN GENERAL COUNSEL    NEW YORK, NY 10166
Engineer Arriola, Kirby Norman; Lic. No.: C31416 PO BOX 5566      OXNARD, CA 93031
Engineer Clandening, Kurtis James; Lic. No.: S3926 1518 18TH STREET #1      SANTA MONICA, CA 90404
Engineer Curtis, David Jesse; Lic. No.: C75791 609 S GRAND AVENUE      LOS ANGELES, CA 90017
Engineer Kim, Carl Chong-Soo; Lic. No.: GE2620 26532 VIA LA JOLLA      SAN JUAN CAPISTRANO, CA 92675
Landscape Architect Trust, Daniel Bryan; Lic. No.: LA2146 4930 CAMPUS DRIVE      NEWPORT BEACH, CA 92660

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 7/22/2015 Not Ready for Inspection WILLIAM THOMPSON
Reinforced Concrete Frame 7/22/2015 Partial Approval WILLIAM THOMPSON
Verify Sprinkler Sign Off 7/22/2015 Not Ready for Inspection WILLIAM THOMPSON
Deputy Reinf. Concrete 7/27/2015 Conditional Approval WILLIAM THOMPSON
Deputy Reinf. Concrete 7/28/2015 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/29/2015 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/30/2015 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/31/2015 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/3/2015 Conditional Approval WILLIAM THOMPSON
Deputy Reinf. Concrete 8/4/2015 Conditional Approval WILLIAM THOMPSON
Deputy Reinf. Concrete 8/5/2015 Conditional Approval WILLIAM THOMPSON
Deputy Reinf. Concrete 8/6/2015 Conditional Approval WILLIAM THOMPSON
Deputy Reinf. Concrete 8/7/2015 Conditional Approval WILLIAM THOMPSON
Deputy Reinf. Concrete 8/10/2015 Conditional Approval WILLIAM THOMPSON
Deputy Reinf. Concrete 8/11/2015 Conditional Approval WILLIAM THOMPSON
Deputy Reinf. Concrete 8/12/2015 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/13/2015 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/14/2015 Conditional Approval WILLIAM THOMPSON
Footing/Foundation/Slab 8/20/2015 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 8/20/2015 Approved LESLIE TRUJILLO
METHANE-Subgrade 8/20/2015 Approved LESLIE TRUJILLO
Deputy Reinf. Concrete 8/24/2015 Order to Comply Issued LESLIE TRUJILLO
Deputy Reinf. Concrete 8/25/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/26/2015 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/26/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/27/2015 Partial Approval LESLIE TRUJILLO
METHANE-Rough 8/27/2015 Approved LESLIE TRUJILLO
Reinforced Concrete Frame 8/27/2015 Not Ready for Inspection LESLIE TRUJILLO
Verify Sprinkler Sign Off 8/27/2015 Approved LESLIE TRUJILLO
Deputy Reinf. Concrete 8/28/2015 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/28/2015 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/1/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/2/2015 Partial Approval LESLIE TRUJILLO
Masonry Wall/Backfill 9/2/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/3/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/4/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/8/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/9/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/10/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/11/2015 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 9/11/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/17/2015 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/17/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/18/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/22/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/23/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/24/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/25/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/28/2015 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/28/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/29/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/30/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/1/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/2/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/5/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/6/2015 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/6/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/7/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/8/2015 Approved LESLIE TRUJILLO
Deputy Reinf. Concrete 10/9/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/13/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/14/2015 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/14/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/15/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/16/2015 Partial Approval LESLIE TRUJILLO
Pre-Inspection 10/16/2015 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 10/20/2015 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/21/2015 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 10/21/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/22/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/23/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/27/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/28/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/29/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/30/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/3/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/4/2015 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/5/2015 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 11/5/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/6/2015 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/9/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/10/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/12/2015 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 11/12/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/13/2015 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/20/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/23/2015 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 11/23/2015 Partial Approval SAKO AGHAZARIAN
Masonry Wall/Backfill 11/23/2015 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 11/24/2015 Conditional Approval WILLIAM THOMPSON
Deputy Reinf. Concrete 11/25/2015 Conditional Approval WILLIAM THOMPSON
Reinforced Concrete Frame 12/5/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/7/2015 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/10/2015 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/11/2015 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 12/14/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/15/2015 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/16/2015 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/17/2015 Conditional Approval LESLIE TRUJILLO
Masonry Wall/Backfill 12/17/2015 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/18/2015 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/23/2015 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 12/23/2015 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 12/29/2015 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/30/2015 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 12/30/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/31/2015 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/11/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 1/11/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/12/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 1/12/2016 Conditional Approval LESLIE TRUJILLO
Masonry Wall/Backfill 1/12/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/13/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 1/13/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/14/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 1/14/2016 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/14/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/15/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 1/15/2016 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/21/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/25/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/26/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/27/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/28/2016 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/28/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/29/2016 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/3/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/4/2016 Partial Approval MICHAEL KUHN
Footing/Foundation/Slab 2/11/2016 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 2/18/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/22/2016 No Access for Inspection LESLIE TRUJILLO
Light Gage Steel Frame 2/22/2016 No Access for Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 2/23/2016 Conditional Approval LESLIE TRUJILLO
Insulation 2/23/2016 Not Ready for Inspection LESLIE TRUJILLO
Light Gage Steel Frame 2/23/2016 Not Ready for Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 2/24/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/25/2016 Conditional Approval LESLIE TRUJILLO
Insulation 2/25/2016 Partial Inspection LESLIE TRUJILLO
Light Gage Steel Frame 2/25/2016 Partial Inspection LESLIE TRUJILLO
Pre-Inspection 2/25/2016 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 2/26/2016 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 2/26/2016 Partial Approval LESLIE TRUJILLO
Insulation 3/2/2016 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 3/3/2016 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 3/10/2016 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 3/15/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 3/15/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/16/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 3/16/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/17/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 3/17/2016 Conditional Approval LESLIE TRUJILLO
Insulation 3/17/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 3/17/2016 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 3/18/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 3/18/2016 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 3/21/2016 No Access for Inspection LESLIE TRUJILLO
Drywall Nailing 3/23/2016 Not Ready for Inspection LESLIE TRUJILLO
Pre-Inspection 3/23/2016 Partial Inspection LESLIE TRUJILLO
Insulation 3/24/2016 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/29/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/29/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 3/29/2016 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/30/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/30/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 3/30/2016 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 3/30/2016 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/31/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/31/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 3/31/2016 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/1/2016 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 4/1/2016 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 4/1/2016 Conditional Approval WINSTON DUNNING
Deputy Pre-Stress Concrete 4/4/2016 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 4/4/2016 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 4/4/2016 Conditional Approval WINSTON DUNNING
Deputy Pre-Stress Concrete 4/5/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/5/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/5/2016 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/6/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/6/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/6/2016 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/7/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/7/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/7/2016 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 4/7/2016 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/8/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/8/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/8/2016 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/11/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/11/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/11/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/11/2016 Conditional Approval LESLIE TRUJILLO
Light Gage Steel Frame 4/11/2016 Partial Inspection LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/12/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/12/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/12/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/12/2016 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/13/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/13/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/13/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/13/2016 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/14/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/14/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/14/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/14/2016 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/15/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/15/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/15/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/15/2016 Conditional Approval LESLIE TRUJILLO
Insulation 4/15/2016 Corrections Issued LESLIE TRUJILLO
Reinforced Concrete Frame 4/15/2016 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/18/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/18/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/18/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/18/2016 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/19/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/19/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/19/2016 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/20/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/20/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/20/2016 Conditional Approval LESLIE TRUJILLO
Insulation 4/20/2016 Partial Inspection LESLIE TRUJILLO
Light Gage Steel Frame 4/20/2016 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/21/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/21/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/21/2016 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/22/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/22/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/22/2016 Conditional Approval LESLIE TRUJILLO
Light Gage Steel Frame 4/22/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/25/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/25/2016 Conditional Approval LESLIE TRUJILLO
Insulation 4/25/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/26/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/26/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/27/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/27/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/28/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/28/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 4/28/2016 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 4/29/2016 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 4/29/2016 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 5/3/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/3/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 5/3/2016 Partial Approval LESLIE TRUJILLO
Insulation 5/3/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 5/3/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/4/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/4/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 5/4/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/5/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/5/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/6/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/6/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/9/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/9/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/10/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/10/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 5/10/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/11/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/11/2016 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 5/11/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/12/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/12/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/13/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/13/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 5/13/2016 Partial Approval LESLIE TRUJILLO
Insulation 5/13/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 5/13/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/16/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/16/2016 Conditional Approval LESLIE TRUJILLO
Grading Pre-Inspection 5/16/2016 Partial Inspection LESLIE TRUJILLO
Light Gage Steel Frame 5/16/2016 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 5/17/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/17/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 5/17/2016 Partial Approval LESLIE TRUJILLO
Insulation 5/17/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 5/17/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/18/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/18/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/19/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/19/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/20/2016 Approved MICHAEL KUHN
Deputy Reinf. Masonry 5/20/2016 Approved MICHAEL KUHN
Drywall Nailing 5/20/2016 Partial Inspection TIMOTHY LYNN
Insulation 5/20/2016 Partial Inspection TIMOTHY LYNN
Light Gage Steel Frame 5/20/2016 Partial Inspection TIMOTHY LYNN
Deputy Reinf. Concrete 5/23/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/23/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 5/23/2016 Partial Approval LESLIE TRUJILLO
Insulation 5/23/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 5/23/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/24/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/24/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/25/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/25/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 5/25/2016 Partial Approval LESLIE TRUJILLO
Insulation 5/25/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 5/25/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/26/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/26/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/27/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/27/2016 Conditional Approval LESLIE TRUJILLO
Light Gage Steel Frame 5/31/2016 Partial Inspection LESLIE TRUJILLO
Drywall Nailing 6/2/2016 Partial Approval LESLIE TRUJILLO
Insulation 6/2/2016 Partial Approval LESLIE TRUJILLO
Interior/Exterior Lathing 6/2/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 6/2/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/6/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/6/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/7/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/7/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/8/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/8/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 6/8/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/9/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/9/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 6/9/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 6/9/2016 Partial Approval LESLIE TRUJILLO
Insulation 6/9/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 6/9/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/10/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/10/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 6/10/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/13/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/13/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/14/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/14/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/15/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/15/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/16/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/16/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 6/16/2016 Partial Approval LESLIE TRUJILLO
Insulation 6/16/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 6/16/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/17/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/17/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/20/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/20/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/21/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/21/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/22/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/22/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 6/22/2016 Partial Approval LESLIE TRUJILLO
Insulation 6/22/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 6/22/2016 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 6/23/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/23/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/24/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 6/24/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 6/29/2016 Partial Approval LESLIE TRUJILLO
Insulation 6/29/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 6/29/2016 Partial Approval LESLIE TRUJILLO
Drywall Nailing 7/7/2016 Partial Approval LESLIE TRUJILLO
Insulation 7/7/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 7/7/2016 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/8/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/11/2016 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 7/13/2016 Conditional Approval LESLIE TRUJILLO
Insulation 7/13/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 7/13/2016 Partial Approval LESLIE TRUJILLO
Drywall Nailing 7/20/2016 Partial Approval LESLIE TRUJILLO
Insulation 7/20/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 7/20/2016 Partial Approval LESLIE TRUJILLO
Special/Order Compliance 7/29/2016 Corrections Issued LESLIE TRUJILLO
Drywall Nailing 8/1/2016 Partial Approval JAMES POWERS
Insulation 8/1/2016 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/1/2016 Partial Approval JAMES POWERS
Drywall Nailing 8/5/2016 Partial Approval JAMES POWERS
Insulation 8/5/2016 Partial Approval JAMES POWERS
Drywall Nailing 8/17/2016 Partial Approval JAMES POWERS
Insulation 8/17/2016 Partial Approval JAMES POWERS
Drywall Nailing 8/26/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 8/26/2016 Partial Approval LESLIE TRUJILLO
Insulation 8/31/2016 Corrections Issued LESLIE TRUJILLO
Insulation 9/7/2016 Not Ready for Inspection LESLIE TRUJILLO
Light Gage Steel Frame 9/7/2016 Partial Approval LESLIE TRUJILLO
Insulation 9/12/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 9/15/2016 Not Ready for Inspection LESLIE TRUJILLO
Drywall Nailing 9/19/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 9/19/2016 Partial Approval LESLIE TRUJILLO
Drywall Nailing 9/23/2016 Partial Approval LESLIE TRUJILLO
Insulation 9/23/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 9/23/2016 Partial Approval LESLIE TRUJILLO
Drywall Nailing 10/7/2016 Not Ready for Inspection NICK DANERI
Insulation 10/7/2016 Not Ready for Inspection NICK DANERI
Light Gage Steel Frame 10/7/2016 Not Ready for Inspection NICK DANERI
Pre-Inspection 10/7/2016 Not Ready for Inspection NICK DANERI
Drywall Nailing 10/12/2016 Partial Approval LESLIE TRUJILLO
Insulation 10/12/2016 Not Ready for Inspection LESLIE TRUJILLO
Light Gage Steel Frame 10/12/2016 Partial Approval LESLIE TRUJILLO
Pre-Inspection 10/13/2016 Partial Inspection LESLIE TRUJILLO
Light Gage Steel Frame 10/17/2016 Partial Approval LESLIE TRUJILLO
Insulation 10/19/2016 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 11/16/2016 Partial Approval LESLIE TRUJILLO
Green Building Final 11/18/2016 Partial Inspection DONALD CRICHLOW
Special/Order Compliance 12/14/2016 Conditional Approval LESLIE TRUJILLO
Special/Order Compliance 1/11/2017 Not Ready for Inspection WINSTON DUNNING
Special/Order Compliance 1/12/2017 Partial Inspection LESLIE TRUJILLO
Special/Order Compliance 1/20/2017 Partial Inspection LESLIE TRUJILLO
Special/Order Compliance 1/24/2017 Corrections Issued LESLIE TRUJILLO
Special/Order Compliance 1/26/2017 Partial Inspection LESLIE TRUJILLO
Special/Order Compliance 1/31/2017 Partial Inspection LESLIE TRUJILLO
Final 2/6/2017 Not Ready for Inspection LESLIE TRUJILLO
Footing/Foundation/Slab 2/6/2017 Approved LESLIE TRUJILLO
Green Building Final 2/6/2017 Partial Approval DONALD CRICHLOW
Reinforced Concrete Frame 2/6/2017 Approved LESLIE TRUJILLO
SGSOV-Seismic Gas S/O Valve 2/6/2017 SGSOV Approved LESLIE TRUJILLO
Smoke Detectors 2/6/2017 Approved LESLIE TRUJILLO
Green Building Rough 2/7/2017 Approved DONALD CRICHLOW
Final 2/8/2017 Partial Inspection LESLIE TRUJILLO
Green Building Final 2/8/2017 Corrections Issued DONALD CRICHLOW
Reinforced Concrete Frame 2/8/2017 Approved LESLIE TRUJILLO
Special/Order Compliance 2/8/2017 Partial Inspection LESLIE TRUJILLO
Green Building Final 2/10/2017 Partial Approval DONALD CRICHLOW
Special/Order Compliance 2/10/2017 Conditional Approval LESLIE TRUJILLO
Green Building Final 3/9/2017 Partial Inspection DONALD CRICHLOW
Green Building Final 6/2/2017 Partial Approval RICHARD DOCKUS
Green Building Final 6/21/2017 Conditional Approval DONALD CRICHLOW
Green Building Final 6/22/2017 Approved DONALD CRICHLOW
Special/Order Compliance 7/24/2017 Partial Inspection LESLIE TRUJILLO
Final 7/25/2017 Partial Inspection LESLIE TRUJILLO
Final 10/2/2017 Partial Inspection LESLIE TRUJILLO
Final 10/4/2017 OK to Issue CofO LESLIE TRUJILLO