1157 S BUNDY DR 90049

Certificate Information: 1157 S BUNDY DR 90049

Application / Permit
14010-30000-02466
Plan Check / Job No.
B14WL03285
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 33 unit 4 story type V-A apartment over one level of type I-A at ground floor and one level of type I-A subterenean garage. ( 3 VERY LOW INCOME UNIT)
Permit Issued
Issued on 9/2/2015
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/13/2017
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2014 APPLICANT
Assigned to Plan Check Engineer 8/7/2014 KAMRAN GHOTBI RAVANDI
Corrections Issued 8/11/2014 KAMRAN GHOTBI RAVANDI
Quality Review Completed 8/11/2014 ARA SARGSYAN
Building Plans Picked Up 8/26/2014 APPLICANT
Applicant returned to address corrections 1/15/2015 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/31/2015 KAMRAN GHOTBI RAVANDI
Plan Check Approved 9/1/2015 KAMRAN GHOTBI RAVANDI
Issued 9/2/2015 LADBS
TCO Issued (Expire Date: 11-28-2017) 6/1/2017 DAVID TSAU
CofO in Progress 6/12/2017 DANIEL MC AULIFFE
Permit Finaled 6/13/2017 JAMES GARRISON
CofO Issued 6/13/2017 JAMES GARRISON
Permit Finaled 6/13/2017 JAMES GARRISON

Permit Application Clearance Information

Low Impact Development Cleared 8/14/2014 AYMAN JABBOURI
DAS Clearance Cleared 1/29/2015 FARUK SEZER
Hydrant and Access approval Cleared 2/4/2015 ROBERT DUFF
Fire Marshall Fire Life Safety Cleared 2/10/2015 ANDREW KO
Construction near power lines Cleared 2/13/2015 LUCIO FERRER
Address approval Cleared 3/23/2015 KELTON KIRBY
Eng Process Fee Ord 176,300 Cleared 3/23/2015 KELTON KIRBY
Sewer availability Cleared 3/23/2015 KELTON KIRBY
Work Adjacent to Public Way Cleared 3/26/2015 TAO YANG
Permit Cleared 4/1/2015 TAO YANG
Roof/Waste drainage to street Cleared 4/1/2015 TAO YANG
Highway dedication Cleared 6/3/2015 TAO YANG
Housing density bonus Cleared 6/4/2015 REX LEE
Driveway location Cleared 6/18/2015 CLIVE GRAWE
Internal circulation Cleared 6/18/2015 CLIVE GRAWE
Green Code Cleared 6/23/2015 KAMRAN GHOTBI RAVANDI
Housing rent stabilization Cleared 6/23/2015 RICHARD BRINSON
Miscellaneous Cleared 7/2/2015 RICK TORRES
ZA Case Cleared 7/2/2015 RICK TORRES
ZA Case Cleared 7/2/2015 RICK TORRES
Building over 3-story or 36-ft Cleared 7/31/2015 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 7/31/2015 CALOSHA APPROVED

Contact Information

Architect Iman, Mehrdad; Lic. No.: C12570 1770 SAWTELLE BLVD      LOS ANGELES, CA 90025
Contractor Kennedy James Construction Company; Lic. No.: 924552-B 12402 CUMPSTON STREET      VALLEY VILLAGE, CA 91607
Engineer Dejban, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316
Engineer Vidal, Juan Alonso; Lic. No.: GE861 15331 DOGWOOD ST      WESTMINSTER, CA 92683

Inspector Information

DANIEL VARNUM, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/9/2015 Approved DAVID TSAU
Excavation/Setback/Form/Re-Bar 10/22/2015 Partial Approval DAVID TSAU
Excavation/Setback/Form/Re-Bar 10/26/2015 Partial Approval DAVID TSAU
Deputy Shotcrete 10/27/2015 Approved DAVID TSAU
Excavation/Setback/Form/Re-Bar 10/27/2015 Not Ready for Inspection DAVID TSAU
Footing/Foundation/Slab 10/27/2015 Partial Approval DAVID TSAU
Footing/Foundation/Slab 10/29/2015 Partial Approval DAVID TSAU
Deputy Shotcrete 11/2/2015 Approved DAVID TSAU
Excavation/Setback/Form/Re-Bar 11/2/2015 Partial Approval DAVID TSAU
Deputy Shotcrete 11/4/2015 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 11/4/2015 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 11/10/2015 Partial Approval DAVID TSAU
Deputy Shotcrete 11/12/2015 Approved DAVID TSAU
Excavation/Setback/Form/Re-Bar 11/12/2015 Partial Approval DAVID TSAU
Deputy Shotcrete 11/13/2015 Conditional Approval DAVID TSAU
Deputy Shotcrete 11/19/2015 Approved DAVID TSAU
Excavation/Setback/Form/Re-Bar 11/19/2015 Partial Approval DAVID TSAU
Deputy Shotcrete 11/20/2015 Approved DAVID TSAU
Excavation/Setback/Form/Re-Bar 11/20/2015 Partial Inspection DAVID TSAU
Footing/Foundation/Slab 11/24/2015 Partial Approval DAVID TSAU
Footing/Foundation/Slab 12/8/2015 Partial Inspection DAVID TSAU
Deputy Reinf. Concrete 12/10/2015 Approved DAVID TSAU
Footing/Foundation/Slab 12/10/2015 Partial Approval DAVID TSAU
Deputy Reinf. Masonry 12/15/2015 Approved DAVID TSAU
Excavation/Setback/Form/Re-Bar 12/15/2015 Partial Approval DAVID TSAU
Deputy Reinf. Masonry 12/16/2015 Approved DAVID TSAU
Masonry Wall/Backfill 12/16/2015 Partial Approval DAVID TSAU
Deputy Reinf. Masonry 12/17/2015 Approved DAVID TSAU
Green Building Rough 12/17/2015 Not Ready for Inspection BRYAN MEYER
Reinforced Masonry Frame 12/17/2015 Partial Approval DAVID TSAU
Verify Sprinkler Sign Off 12/17/2015 Not Ready for Inspection DAVID TSAU
Footing/Foundation/Slab 12/18/2015 Partial Approval DAVID TSAU
Deputy Reinf. Masonry 12/22/2015 Approved DAVID TSAU
Green Building Rough 12/22/2015 Not Ready for Inspection RICHARD DOCKUS
Reinforced Masonry Frame 12/22/2015 Partial Approval DAVID TSAU
Verify Sprinkler Sign Off 12/22/2015 Not Ready for Inspection DAVID TSAU
Footing/Foundation/Slab 12/23/2015 Not Ready for Inspection DAVID TSAU
Reinforced Concrete Frame 12/23/2015 Partial Approval DAVID TSAU
Footing/Foundation/Slab 12/24/2015 Partial Approval DAVID TSAU
Footing/Foundation/Slab 12/30/2015 Partial Approval DAVID TSAU
Footing/Foundation/Slab 1/4/2016 Partial Inspection DAVID TSAU
Footing/Foundation/Slab 1/13/2016 Partial Approval DAVID TSAU
Footing/Foundation/Slab 1/27/2016 Not Ready for Inspection DAVID TSAU
Footing/Foundation/Slab 2/3/2016 Partial Approval DAVID TSAU
Footing/Foundation/Slab 2/12/2016 Partial Approval DERRICK SPENCER
Green Building Rough 2/26/2016 Not Ready for Inspection BRYAN MEYER
Verify Sprinkler Sign Off 2/26/2016 Not Ready for Inspection DAVID TSAU
Wood Frame 2/26/2016 Partial Inspection DAVID TSAU
Deputy Wood Construction 3/3/2016 Approved DERRICK SPENCER
Green Building Rough 3/3/2016 Not Ready for Inspection BRYAN MEYER
Verify Sprinkler Sign Off 3/3/2016 Approved DERRICK SPENCER
Wood Frame 3/3/2016 Partial Approval DERRICK SPENCER
Green Building Rough 3/22/2016 Partial Inspection BRYAN MEYER
Wood Frame 3/22/2016 Partial Approval DANIEL MC AULIFFE
Deputy Wood Construction 3/29/2016 Conditional Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 3/30/2016 Partial Approval DAVID TSAU
Green Building Rough 3/30/2016 Not Ready for Inspection BRYAN MEYER
Wood Frame 3/30/2016 Not Ready for Inspection DAVID TSAU
Green Building Rough 4/13/2016 Not Ready for Inspection BRYAN MEYER
Wood Frame 4/13/2016 Not Ready for Inspection DAVID TSAU
Deputy Wood Construction 4/18/2016 Conditional Approval DAVID TSAU
Green Building Rough 4/18/2016 Not Ready for Inspection BRYAN MEYER
Wood Frame 4/18/2016 Partial Approval DAVID TSAU
Deputy Wood Construction 5/11/2016 Conditional Approval DAVID TSAU
Floor/Roof Diaphrgm/Shear Wall 5/11/2016 Partial Approval DAVID TSAU
Green Building Rough 5/16/2016 Not Ready for Inspection BRYAN MEYER
Wood Frame 5/16/2016 Partial Approval DAVID TSAU
Deputy Wood Construction 5/17/2016 Conditional Approval DAVID TSAU
Green Building Rough 5/20/2016 Not Ready for Inspection BRYAN MEYER
Wood Frame 5/20/2016 Partial Approval MILLARD ARDOIN
Deputy Wood Construction 5/26/2016 Approved MILLARD ARDOIN
Green Building Rough 5/26/2016 Not Ready for Inspection BRYAN MEYER
Wood Frame 5/26/2016 Partial Approval MILLARD ARDOIN
Deputy Wood Construction 6/2/2016 Approved MILLARD ARDOIN
Green Building Rough 6/3/2016 Partial Inspection BRYAN MEYER
Wood Frame 6/3/2016 Partial Approval MILLARD ARDOIN
Drywall Nailing 6/8/2016 Partial Approval DERRICK SPENCER
Green Building Rough 6/8/2016 Not Ready for Inspection BRYAN MEYER
Insulation 6/13/2016 Partial Inspection MILLARD ARDOIN
Insulation 6/15/2016 Partial Inspection MILLARD ARDOIN
Deputy Wood Construction 7/12/2016 Approved MILLARD ARDOIN
Wood Frame 7/12/2016 Partial Approval MILLARD ARDOIN
Wood Frame 7/25/2016 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 8/8/2016 Partial Approval MILLARD ARDOIN
Interior/Exterior Lathing 8/15/2016 Partial Approval MILLARD ARDOIN
Green Building Rough 8/17/2016 Corrections Issued BRYAN MEYER
Drywall Nailing 8/19/2016 Partial Inspection MILLARD ARDOIN
Green Building Rough 8/19/2016 Not Ready for Inspection ROLLIN GETTLE III
Insulation 8/24/2016 Order to Comply Issued MILLARD ARDOIN
Drywall Nailing 8/26/2016 Partial Approval DAVID TSAU
Green Building Rough 8/26/2016 Corrections Issued BRYAN MEYER
Drywall Nailing 9/2/2016 Partial Approval MILLARD ARDOIN
Green Building Rough 9/2/2016 Not Ready for Inspection BRYAN MEYER
Drywall Nailing 9/8/2016 Partial Approval MILLARD ARDOIN
Green Building Rough 9/8/2016 Partial Approval BRYAN MEYER
Light Gage Steel Frame 9/13/2016 Partial Approval MILLARD ARDOIN
Green Building Rough 9/14/2016 Partial Inspection BRYAN MEYER
Light Gage Steel Frame 9/14/2016 Partial Approval MILLARD ARDOIN
Green Building Rough 9/21/2016 Partial Approval BRYAN MEYER
Drywall Nailing 9/27/2016 Partial Approval MILLARD ARDOIN
Green Building Rough 9/27/2016 Partial Inspection BRYAN MEYER
Light Gage Steel Frame 9/27/2016 Partial Approval MILLARD ARDOIN
Light Gage Steel Frame 9/30/2016 Partial Approval MILLARD ARDOIN
Special/Order Compliance 11/15/2016 Partial Inspection DANIEL MC AULIFFE
Green Building Rough 1/12/2017 Partial Approval BRYAN MEYER
Insulation 1/17/2017 Partial Approval DANIEL MC AULIFFE
Drywall Nailing 1/23/2017 Partial Approval DANIEL MC AULIFFE
Green Building Rough 1/23/2017 Partial Inspection BRYAN MEYER
Footing/Foundation/Slab 1/26/2017 Partial Approval DANIEL MC AULIFFE
Green Building Rough 1/27/2017 Not Ready for Inspection BRYAN MEYER
Masonry Wall/Backfill 1/27/2017 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 1/30/2017 Partial Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 1/31/2017 Partial Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 2/1/2017 Partial Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 2/3/2017 Partial Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 2/6/2017 Partial Approval DANIEL MC AULIFFE
Drywall Nailing 2/7/2017 Partial Approval DANIEL MC AULIFFE
Light Gage Steel Frame 2/8/2017 Partial Inspection DANIEL MC AULIFFE
Masonry Wall/Backfill 2/9/2017 Partial Approval DANIEL MC AULIFFE
Wood Frame 2/21/2017 Partial Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 2/23/2017 Partial Inspection DANIEL MC AULIFFE
Masonry Wall/Backfill 3/2/2017 Partial Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 3/3/2017 Partial Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 3/8/2017 Partial Inspection DANIEL MC AULIFFE
Reinforced Masonry Frame 3/13/2017 Partial Approval DANIEL MC AULIFFE
Interior/Exterior Lathing 3/24/2017 Partial Inspection DANIEL MC AULIFFE
Masonry Wall/Backfill 3/28/2017 Partial Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 3/30/2017 Partial Inspection DANIEL MC AULIFFE
Reinforced Masonry Frame 4/3/2017 Partial Inspection DANIEL MC AULIFFE
Light Gage Steel Frame 4/7/2017 Partial Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 4/10/2017 Partial Inspection DANIEL MC AULIFFE
Masonry Wall/Backfill 4/13/2017 Partial Inspection DANIEL MC AULIFFE
Drywall Nailing 4/17/2017 Partial Inspection DANIEL MC AULIFFE
Final 4/17/2017 Partial Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 4/17/2017 Approved DANIEL MC AULIFFE
Green Building Final 4/17/2017 Partial Inspection BRYAN MEYER
Green Building Rough 4/17/2017 Partial Inspection BRYAN MEYER
Reinforced Concrete Frame 4/17/2017 Partial Inspection DANIEL MC AULIFFE
Reinforced Masonry Frame 4/17/2017 Partial Inspection DANIEL MC AULIFFE
SGSOV-Seismic Gas S/O Valve 4/17/2017 SGSOV Approved DANIEL MC AULIFFE
Smoke Detectors 4/17/2017 Approved DANIEL MC AULIFFE
Wood Frame 4/17/2017 Partial Inspection DANIEL MC AULIFFE
Drywall Nailing 4/19/2017 Partial Inspection DANIEL MC AULIFFE
Structural Steel Frame 4/20/2017 Partial Inspection DANIEL MC AULIFFE
Drywall Nailing 4/24/2017 Partial Inspection DANIEL MC AULIFFE
Green Building Rough 4/24/2017 Not Ready for Inspection BRYAN MEYER
Insulation 4/25/2017 Partial Inspection DANIEL MC AULIFFE
Special/Order Compliance 4/25/2017 Partial Inspection JOHN DODGE
Drywall Nailing 4/27/2017 Partial Inspection DANIEL MC AULIFFE
Drywall Nailing 5/1/2017 Partial Inspection DANIEL MC AULIFFE
Green Building Rough 5/1/2017 Not Ready for Inspection BRYAN MEYER
Drywall Nailing 5/4/2017 Partial Inspection DANIEL MC AULIFFE
Drywall Nailing 5/10/2017 Partial Inspection DANIEL MC AULIFFE
Final 5/10/2017 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 5/10/2017 Partial Inspection DANIEL MC AULIFFE
Reinforced Masonry Frame 5/10/2017 Partial Inspection DANIEL MC AULIFFE
Wood Frame 5/10/2017 Partial Inspection DANIEL MC AULIFFE
Drywall Nailing 5/17/2017 Partial Inspection DANIEL MC AULIFFE
Final 5/17/2017 Partial Inspection DANIEL MC AULIFFE
Green Building Final 5/17/2017 Partial Inspection BRYAN MEYER
Green Building Rough 5/17/2017 Approved BRYAN MEYER
Reinforced Concrete Frame 5/17/2017 Partial Inspection DANIEL MC AULIFFE
Reinforced Masonry Frame 5/17/2017 Partial Inspection DANIEL MC AULIFFE
Wood Frame 5/17/2017 Partial Inspection DANIEL MC AULIFFE
Green Building Final 5/22/2017 No Access for Inspection ROLLIN GETTLE III
Drywall Nailing 5/23/2017 Partial Inspection DANIEL MC AULIFFE
Final 5/23/2017 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 5/23/2017 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 5/23/2017 Approved DANIEL MC AULIFFE
Wood Frame 5/23/2017 Approved DANIEL MC AULIFFE
Green Building Final 5/24/2017 Partial Inspection BRYAN MEYER
Green Building Final 5/31/2017 Approved BRYAN MEYER
Drywall Nailing 6/8/2017 Approved DANIEL MC AULIFFE
Final 6/8/2017 Conditional Approval DANIEL MC AULIFFE