2025 S AVENUE OF THE STARS 90067

Certificate Information: 2025 S AVENUE OF THE STARS 90067

Application / Permit
14014-10040-05098
Plan Check / Job No.
B19LA22564
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment Hotel
Work Description
SUPPLEMENTAL TO PERMIT #14014-10000-05098 TI TO (E) RETAIL PAVILIONS TO INCLUDE INTERIOR WALL/FLOOR/CEILING FINISHES
Permit Issued
Issued on 3/3/2020
Issuing Office
Valley
Current Status
Permit Finaled on 11/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 GARO TELMI
Corrections Issued 11/13/2019 GARO TELMI
Quality Review Completed 11/14/2019 KEN GILL
Disabled Access Plans Picked Up 11/21/2019 APPLICANT
Building Plans Picked Up 11/26/2019 APPLICANT
Plan Check Approved 2/25/2020 GARO TELMI
Issued 3/3/2020 LADBS
Permit Finaled 11/12/2021 PAUL DAVIDSON

Permit Application Clearance Information

CPC Cleared 2/5/2020 SARAH GOLDMAN
Specific Plan Cleared 2/5/2020 SARAH GOLDMAN
DAS Clearance Cleared 2/11/2020 GARO TELMI
Green Code Cleared 2/18/2020 DONALD CRICHLOW

Contact Information

Architect Wicksman, Warwick Ian; Lic. No.: C23350 22844 DOLOROSA ST      WOODLAND HILLS, CA 91367
Contractor J R M Construction Management West Llc; Lic. No.: 1013928-B 959 SOUTH COAST DR #495      COSTA MESA, CA 92626

Inspector Information

RICARDO ROBLES, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/11/2020 Partial Approval PAUL DAVIDSON
Pre-Inspection 2/1/2021 Approved PAUL DAVIDSON
Structural Steel Frame 5/20/2021 Partial Inspection PAUL DAVIDSON
Light Gage Steel Frame 5/27/2021 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 6/1/2021 Partial Approval PAUL DAVIDSON
Drywall Nailing 6/4/2021 Partial Approval DERRICK SPENCER
Drywall Nailing 6/8/2021 Not Ready for Inspection PAUL DAVIDSON
Drywall Nailing 6/9/2021 Partial Approval PAUL DAVIDSON
Final 6/11/2021 Not Ready for Inspection PAUL DAVIDSON
Smoke Detectors 6/11/2021 Not Ready for Inspection PAUL DAVIDSON
Light Gage Steel Frame 6/18/2021 Approved DERRICK SPENCER
Drywall Nailing 6/28/2021 Partial Approval PAUL DAVIDSON
Drywall Nailing 7/9/2021 Not Ready for Inspection PAUL DAVIDSON
Light Gage Steel Frame 7/9/2021 Not Ready for Inspection PAUL DAVIDSON
Drywall Nailing 7/22/2021 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 7/22/2021 Approved PAUL DAVIDSON
Smoke Detectors 11/8/2021 Not Ready for Inspection PAUL DAVIDSON
Final 11/12/2021 Permit Finaled PAUL DAVIDSON
Smoke Detectors 11/12/2021 Approved PAUL DAVIDSON