1002 W CHILDS WAY 90089

Certificate Information: 1002 W CHILDS WAY 90089

Application / Permit
15010-10000-00299
Plan Check / Job No.
B15LA01036
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
NEW OFFICE/RESEARCH AND LABRATORY BUILDING. 4-STORIES WITH BASEMENT.
Permit Issued
Issued on 8/19/2015
Issuing Office
Metro
Current Status
CofO Issued on 2/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2015 APPLICANT
Disabled Access Plans Picked Up 2/5/2015 APPLICANT
Green Plans Picked Up 2/5/2015 APPLICANT
Assigned to Plan Check Engineer 2/13/2015 JOE VO
Corrections Issued 2/27/2015 JOE VO
Quality Review Completed 3/9/2015 LINCOLN LEE
Plan Check Approved 8/18/2015 JOE VO
Issued 8/19/2015 LADBS
Re-Activate Permit 6/2/2017 JOEY BUCHANAN
Permit Expired-Status Void 6/2/2017 JOEY BUCHANAN
TCO Issued (Expire Date: 03-31-2018) 10/2/2017 HAMID PISHEHVAR
TCO Issued (Expire Date: 09-27-2018) 3/31/2018 RICKEY JACKSON
TCO Issued (Expire Date: 03-26-2019) 9/27/2018 HAMID PISHEHVAR
TCO Issued (Expire Date: 09-22-2019) 3/26/2019 WINSTON DUNNING
TCO Issued (Expire Date: 03-20-2020) 9/22/2019 WINSTON DUNNING
CofO in Progress 2/24/2020 JAMES POWERS
CofO Issued 2/24/2020 TERRY HERR
Permit Finaled 2/24/2020 TERRY HERR

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/6/2015 ARMENIA HERNANDEZ
ZA Case Cleared 4/7/2015 RALPH AVILA
ZI Cleared 4/7/2015 RALPH AVILA
Hydrant and Access approval Cleared 6/5/2015 JOHN DALLAS
Project located in CRA area Cleared 6/17/2015 JIM URQUHART
Sewer availability Cleared 6/23/2015 JOSHUA LOPEZ
Specific Plan Cleared 6/30/2015 ANN CHOI
Site Plan review Cleared 7/6/2015 ALFREDO PEREZ
DAS Clearance Cleared 7/9/2015 WAI LAU
Green Code Cleared 7/14/2015 MARCUS LEVIAS
Chemical processes Cleared 7/21/2015 SCAQMD APPROVED
Combustion equipment Cleared 7/21/2015 SCAQMD APPROVED
Internal combustion engine Cleared 7/21/2015 SCAQMD APPROVED
Organic liquids and gases Cleared 7/21/2015 SCAQMD APPROVED
Solvents/fuels Cleared 7/21/2015 SCAQMD APPROVED
Fire Marshall Fire Life Safety Cleared 7/28/2015 ANDREW KO
CPC Cleared 8/11/2015 ALFREDO PEREZ
Stormwater Pollution Mitigatn Cleared 8/17/2015 AMMAR ELTAWIL
Building over 3-story or 36-ft Cleared 8/18/2015 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 8/18/2015 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 8/18/2015 ARMENIA HERNANDEZ

Contact Information

Architect Cull, Robert Ashley; Lic. No.: C22223 2255 CLOVERFIELD BLVD      SANTA MONICA, CA 90405
Contractor D P R Construction A General Partnership; Lic. No.: 953749-B P O BOX 5614      REDWOOD CITY, CA 94063
Engineer Clandening, Kurtis James; Lic. No.: S3926 1518 18TH STREET #1      SANTA MONICA, CA 90404
Engineer Hill, Edward Foster; Lic. No.: GE2126 GEOTECH 439 WESTERN AVE      GLENDALE, CA 91201

Inspector Information

JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/24/2015 Partial Approval JAMES POWERS
METHANE-Barrier 9/24/2015 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 9/24/2015 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/30/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/1/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/2/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/5/2015 Partial Approval JAMES POWERS
Deputy Methane Barrier 10/6/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/6/2015 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/6/2015 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 10/6/2015 Partial Approval JAMES POWERS
METHANE-Subgrade 10/6/2015 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/7/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/8/2015 Approved LESLIE TRUJILLO
Deputy Reinf. Concrete 10/9/2015 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/13/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/14/2015 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/14/2015 Partial Approval JAMES POWERS
METHANE-Barrier 10/14/2015 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 10/14/2015 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/15/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/16/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/19/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/20/2015 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/20/2015 Partial Approval JAMES POWERS
METHANE-Barrier 10/20/2015 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 10/20/2015 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/21/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/22/2015 Partial Approval JAMES POWERS
Deputy Methane Barrier 10/23/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/23/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/26/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 10/26/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/27/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 10/27/2015 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/27/2015 Partial Approval JAMES POWERS
METHANE-Barrier 10/27/2015 Partial Approval JAMES POWERS
METHANE-Subgrade 10/27/2015 Not Ready for Inspection JAMES POWERS
Pre-Inspection 10/27/2015 Approved JAMES POWERS
Deputy Methane Barrier 10/28/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/28/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 10/28/2015 Partial Approval JAMES POWERS
Pre-Inspection 10/28/2015 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/29/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 10/29/2015 Partial Approval JAMES POWERS
Deputy Methane Barrier 10/30/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/30/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 10/30/2015 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/30/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/2/2015 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/2/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/3/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 11/3/2015 Partial Approval JAMES POWERS
Deputy Methane Barrier 11/4/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/4/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 11/4/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/5/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 11/5/2015 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 11/5/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/6/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 11/6/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/9/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 11/9/2015 Partial Approval JAMES POWERS
Pre-Inspection 11/9/2015 Approved JAMES POWERS
Reinforced Concrete Frame 11/12/2015 Partial Approval BARRY SILLS
Deputy Reinf. Concrete 11/16/2015 Partial Approval JAMES POWERS
Pre-Inspection 11/16/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/17/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 11/17/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/18/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 11/18/2015 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/18/2015 Partial Approval JAMES POWERS
Deputy Methane Barrier 11/19/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/19/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 11/19/2015 Partial Approval JAMES POWERS
Deputy Methane Barrier 11/20/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/20/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 11/20/2015 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/20/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/23/2015 Approved BYRON FUENTES
Deputy Shotcrete 11/23/2015 Approved BYRON FUENTES
Deputy Reinf. Concrete 11/24/2015 Approved BYRON FUENTES
Deputy Shotcrete 11/24/2015 Approved BYRON FUENTES
Deputy Reinf. Concrete 11/25/2015 Conditional Approval WILLIAM THOMPSON
Deputy Shotcrete 11/25/2015 Conditional Approval WILLIAM THOMPSON
Deputy Reinf. Concrete 11/30/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 11/30/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/1/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/1/2015 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/1/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/2/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/2/2015 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/2/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/3/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/3/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/4/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/4/2015 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/4/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/7/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/7/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/8/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/8/2015 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/8/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/9/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/9/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/10/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/10/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/11/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/11/2015 Partial Approval JAMES POWERS
Deputy Methane Barrier 12/21/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/21/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/21/2015 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/21/2015 Partial Approval JAMES POWERS
Deputy Methane Barrier 12/22/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/22/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/22/2015 Partial Approval JAMES POWERS
Deputy Methane Barrier 12/23/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/23/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/23/2015 Partial Approval JAMES POWERS
Deputy Methane Barrier 12/24/2015 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/24/2015 Partial Approval JAMES POWERS
Deputy Shotcrete 12/24/2015 Partial Approval JAMES POWERS
Deputy Methane Barrier 12/28/2015 Partial Approval JAMES POWERS
Deputy Methane Barrier 12/29/2015 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/31/2015 Partial Approval JAMES POWERS
METHANE-Barrier 12/31/2015 Partial Approval JAMES POWERS
METHANE-Subgrade 12/31/2015 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 1/4/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/4/2016 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/4/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/5/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/5/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/6/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/6/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/7/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/7/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/8/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/8/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/11/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/11/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/12/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/12/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/13/2016 Partial Approval JAMES POWERS
Deputy Methane Barrier 1/13/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/13/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/14/2016 Partial Approval JAMES POWERS
Deputy Methane Barrier 1/14/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/14/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/15/2016 Partial Approval JAMES POWERS
Deputy Methane Barrier 1/15/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/15/2016 Partial Approval JAMES POWERS
Deputy Methane Barrier 1/19/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/19/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/20/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/21/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/22/2016 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 1/25/2016 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 1/26/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/27/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/28/2016 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/28/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/29/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/1/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/2/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/3/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/4/2016 Conditional Approval BARRY SILLS
Deputy Reinf. Concrete 2/5/2016 Partial Approval JAMES POWERS
Deputy Methane Barrier 2/8/2016 Partial Approval JAMES POWERS
Deputy Methane Barrier 2/9/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/9/2016 Partial Approval JAMES POWERS
Deputy Methane Barrier 2/10/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/10/2016 Partial Approval JAMES POWERS
Deputy Methane Barrier 2/11/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/11/2016 Partial Approval JAMES POWERS
Deputy Methane Barrier 2/12/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/12/2016 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 2/16/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/17/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/18/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/19/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/22/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/22/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/23/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/24/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/25/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/26/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/29/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/1/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/2/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/2/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/3/2016 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 3/4/2016 Conditional Approval WINSTON DUNNING
Pre-Inspection 3/7/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/8/2016 Partial Approval JAMES POWERS
Pre-Inspection 3/9/2016 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 3/10/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/11/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/14/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/15/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/16/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/17/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/17/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/18/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/21/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/22/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/23/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/24/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/25/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/29/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/30/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/31/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/1/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/4/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/5/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/6/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/7/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/8/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/11/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/12/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/12/2016 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 4/13/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/14/2016 Partial Approval JAMES POWERS
Pre-Inspection 4/14/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/15/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/18/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/19/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/20/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/21/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/21/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/22/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/25/2016 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 4/26/2016 Conditional Approval BARRY SILLS
Deputy Reinf. Concrete 4/27/2016 Approved MICHAEL KUHN
Deputy Reinf. Concrete 4/28/2016 Conditional Approval TED RIES
Deputy Steel/Welding 4/28/2016 Conditional Approval TED RIES
Deputy Reinf. Concrete 4/29/2016 Conditional Approval BARRY SILLS
Deputy Steel/Welding 4/29/2016 Conditional Approval BARRY SILLS
Deputy Reinf. Concrete 5/2/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/3/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/4/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/5/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/6/2016 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/6/2016 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 5/6/2016 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 5/6/2016 Not Ready for Inspection JAMES POWERS
Pre-Inspection 5/6/2016 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/9/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/10/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/11/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/12/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/13/2016 No Access for Inspection JAMES POWERS
Deputy Reinf. Concrete 5/17/2016 Approved BYRON FUENTES
Deputy Reinf. Concrete 5/18/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/19/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/20/2016 Conditional Approval GREGORY POMISH
Reinforced Concrete Frame 5/23/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/24/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/25/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/26/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/27/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/1/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/1/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/2/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/3/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/7/2016 Conditional Approval BARRY SILLS
Deputy Reinf. Concrete 6/8/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/9/2016 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 6/9/2016 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/10/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/13/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/14/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/15/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/16/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/17/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/21/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/21/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/22/2016 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/22/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/23/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/24/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/28/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/29/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/30/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/30/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/1/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/6/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/7/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/8/2016 Conditional Approval DANIEL COLLINS
Pre-Inspection 7/8/2016 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 7/11/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/11/2016 Order to Comply Issued JAMES POWERS
Deputy Reinf. Concrete 7/12/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/13/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/14/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/15/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/19/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/20/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/21/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/21/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/21/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/22/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/22/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/22/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/25/2016 Partial Approval JAMES POWERS
Deputy Fireproofing 7/25/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/25/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/26/2016 Partial Approval JAMES POWERS
Deputy Fireproofing 7/26/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/26/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/27/2016 Partial Approval JAMES POWERS
Deputy Fireproofing 7/27/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/27/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/27/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/28/2016 Partial Approval JAMES POWERS
Deputy Fireproofing 7/28/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/28/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/28/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/29/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/2/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/3/2016 Partial Approval JAMES POWERS
Pre-Inspection 8/3/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/4/2016 Partial Approval JAMES POWERS
Pre-Inspection 8/4/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/5/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/8/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/9/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/9/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/10/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/10/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/11/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/11/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/15/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/15/2016 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/15/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/16/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/17/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/18/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/19/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/23/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/24/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/25/2016 Partial Approval JAMES POWERS
Pre-Inspection 8/25/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/26/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/30/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/30/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/30/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/31/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/31/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/31/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/1/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/1/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/1/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/2/2016 Partial Approval JAMES POWERS
Deputy Fireproofing 9/2/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/2/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/2/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/6/2016 Partial Approval JAMES POWERS
Deputy Fireproofing 9/6/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/6/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/6/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/8/2016 Partial Approval JAMES POWERS
Deputy Fireproofing 9/8/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/8/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/8/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/9/2016 Conditional Approval NICK DANERI
Deputy Fireproofing 9/9/2016 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/9/2016 Conditional Approval NICK DANERI
Deputy Steel/Welding 9/9/2016 Conditional Approval NICK DANERI
Deputy Steel/Welding 9/12/2016 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/12/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/13/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/14/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/15/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/16/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/19/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/19/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/20/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/20/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/20/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/20/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/21/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/21/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/21/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/21/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/22/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/22/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/22/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/22/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/23/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/23/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/23/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/23/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/26/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/26/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/27/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/27/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/27/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/27/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/28/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/28/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/28/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/28/2016 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/28/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/29/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/29/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/29/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/29/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/30/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/30/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/30/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/30/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/5/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/6/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/7/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/11/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/12/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/12/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/12/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/13/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/13/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/13/2016 Partial Approval JAMES POWERS
Drywall Nailing 10/13/2016 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/13/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/14/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/14/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/14/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/17/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/17/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/17/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/18/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/18/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/18/2016 Partial Approval JAMES POWERS
Insulation 10/18/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/19/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/19/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/19/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/20/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/20/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/20/2016 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/20/2016 Partial Approval JAMES POWERS
Insulation 10/20/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/24/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/24/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/24/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/25/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/27/2016 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/27/2016 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/27/2016 Partial Approval JAMES POWERS
Insulation 10/27/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/28/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/31/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/31/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/31/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 11/1/2016 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/1/2016 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 11/1/2016 Conditional Approval ERNESTO CORRAL
Drywall Nailing 11/1/2016 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 11/1/2016 Partial Inspection ERNESTO CORRAL
Green Building Rough 11/1/2016 Not Ready for Inspection JOHN KLARIN
Insulation 11/1/2016 Partial Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 11/2/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/2/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/2/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 11/3/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/3/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/3/2016 Partial Approval JAMES POWERS
Drywall Nailing 11/3/2016 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/3/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 11/4/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/4/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/4/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/4/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 11/7/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/7/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/7/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/7/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 11/8/2016 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/8/2016 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 11/8/2016 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/8/2016 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 11/9/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/9/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/9/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/9/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 11/10/2016 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/10/2016 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/10/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/10/2016 Partial Approval JAMES POWERS
Drywall Nailing 11/14/2016 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/14/2016 Partial Approval JAMES POWERS
Insulation 11/14/2016 Not Ready for Inspection JAMES POWERS
Insulation 11/17/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/21/2016 Conditional Approval WINSTON DUNNING
Deputy Steel/Welding 11/22/2016 Conditional Approval LESLIE TRUJILLO
Deputy Drilled-In Anchors 11/29/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/29/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 11/30/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/30/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/1/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/1/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/2/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/2/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/5/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/5/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/6/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/7/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/8/2016 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 12/16/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/22/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/22/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/23/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/23/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/28/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/28/2016 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/28/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/29/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/29/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 12/30/2016 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/30/2016 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/10/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/10/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/10/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/10/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/11/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/11/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/11/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/11/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/11/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/12/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/12/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/12/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/12/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/13/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/13/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/13/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/13/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/17/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/17/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/17/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/17/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/17/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/18/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/18/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/18/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/18/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/19/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/19/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/19/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/19/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/20/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/20/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/20/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/20/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/23/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/23/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/23/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/23/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/24/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/24/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/24/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/24/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/25/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/25/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/25/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/25/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/26/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/26/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/26/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/26/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/27/2017 Approved JOEY BUCHANAN
Deputy Fireproofing 1/27/2017 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 1/27/2017 Approved JOEY BUCHANAN
Deputy Steel/Welding 1/27/2017 Approved JOEY BUCHANAN
Light Gage Steel Frame 1/27/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 1/30/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/30/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/30/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/31/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 1/31/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/31/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/1/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 2/1/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/1/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/2/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 2/2/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/2/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/3/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 2/3/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/3/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/7/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 2/7/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/7/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/8/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 2/8/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/8/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/9/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 2/9/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/9/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/10/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 2/10/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/10/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/13/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 2/13/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/13/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/13/2017 Partial Approval JAMES POWERS
Drywall Nailing 2/13/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/13/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/14/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 2/14/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/14/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/14/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/15/2017 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 2/15/2017 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 2/15/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 2/15/2017 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 2/15/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 2/16/2017 Conditional Approval ERNESTO CORRAL
Deputy Fireproofing 2/16/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/16/2017 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 2/16/2017 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 2/17/2017 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 2/17/2017 No Access for Inspection JOEY BUCHANAN
Deputy Reinf. Concrete 2/17/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 2/17/2017 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 2/17/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 2/21/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/21/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/21/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/22/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/22/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/22/2017 Partial Approval JAMES POWERS
Drywall Nailing 2/22/2017 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 2/22/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/23/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/23/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/23/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/24/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/24/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/24/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/28/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/28/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/1/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/1/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/2/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/2/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/3/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/3/2017 Partial Approval JAMES POWERS
Drywall Nailing 3/3/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/3/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/6/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/6/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/7/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 3/7/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 3/8/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/8/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/9/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/9/2017 Partial Approval JAMES POWERS
Drywall Nailing 3/9/2017 Partial Approval JAMES POWERS
Green Building Rough 3/9/2017 Partial Approval JOHN KLARIN
Light Gage Steel Frame 3/9/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/10/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/10/2017 Partial Approval JAMES POWERS
Pre-Inspection 3/10/2017 Approved JAMES POWERS
Deputy Drilled-In Anchors 3/13/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 3/13/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/13/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/14/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 3/14/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/14/2017 Partial Approval JAMES POWERS
Drywall Nailing 3/14/2017 Partial Approval JAMES POWERS
Green Building Rough 3/14/2017 Not Ready for Inspection JOHN KLARIN
Light Gage Steel Frame 3/14/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/15/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 3/15/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/15/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/16/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 3/16/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/16/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/17/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 3/17/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/17/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/20/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 3/20/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/20/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/21/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 3/21/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/21/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/22/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 3/22/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/22/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/23/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 3/23/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/23/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/23/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/24/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 3/24/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/24/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/29/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/4/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/4/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/5/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/5/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/5/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/6/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/6/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/7/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/7/2017 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/7/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/7/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/10/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/11/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/12/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/13/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/14/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/14/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/17/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/17/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/18/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/18/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/19/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/19/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/20/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/25/2017 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 4/25/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 4/25/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 4/26/2017 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 4/26/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 4/26/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 4/27/2017 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 4/27/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 4/27/2017 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 4/27/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 4/28/2017 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 4/28/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 4/28/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 5/1/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 5/1/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/1/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/1/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/2/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 5/2/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/2/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/2/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/3/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 5/3/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/3/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/3/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/4/2017 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 5/4/2017 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 5/4/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 5/4/2017 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 5/4/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 5/5/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 5/5/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/5/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/5/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/8/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/8/2017 Partial Approval JAMES POWERS
Green Building Rough 5/8/2017 Partial Inspection JOHN KLARIN
Deputy Drilled-In Anchors 5/9/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/9/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/10/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/10/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/11/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/11/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/12/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/12/2017 Partial Approval JAMES POWERS
Drywall Nailing 5/18/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/18/2017 Partial Approval JAMES POWERS
T-Bar Ceiling 5/19/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/22/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/22/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/23/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/23/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/24/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/24/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/24/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/25/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/25/2017 Partial Approval JAMES POWERS
T-Bar Ceiling 5/25/2017 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 5/26/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/26/2017 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/30/2017 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/31/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/1/2017 Partial Approval JOEY BUCHANAN
T-Bar Ceiling 6/1/2017 Partial Approval JOEY BUCHANAN
Deputy Reinf. Masonry 6/5/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/6/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/6/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/7/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/7/2017 Partial Approval JAMES POWERS
Drywall Nailing 6/7/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/7/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/8/2017 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 6/8/2017 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 6/9/2017 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 6/9/2017 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 6/12/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 6/12/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/12/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/12/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/13/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 6/13/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/13/2017 Partial Approval JAMES POWERS
Green Building Rough 6/13/2017 Partial Inspection JOHN KLARIN
Light Gage Steel Frame 6/13/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/14/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 6/14/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/14/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/14/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/15/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 6/15/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/15/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/16/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 6/16/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/16/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/16/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/23/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/26/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/26/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/26/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/27/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/27/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/27/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/28/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/28/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/28/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/29/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/29/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/29/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/30/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/30/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/30/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/3/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/3/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/3/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/3/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/5/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/5/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/5/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/5/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/6/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/6/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/6/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/6/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/7/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/7/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/7/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/7/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/7/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/10/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/10/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/10/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/10/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/11/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/11/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/11/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/11/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/12/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/12/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/12/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/12/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/13/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/13/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/13/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/13/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/14/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/14/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/14/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/14/2017 Partial Approval JAMES POWERS
Green Building Rough 7/17/2017 Partial Inspection JOHN KLARIN
Deputy Drilled-In Anchors 7/18/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/18/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/18/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/18/2017 Partial Approval JAMES POWERS
T-Bar Ceiling 7/18/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/19/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/19/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/19/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/19/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/20/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/20/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/20/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/21/2017 Partial Approval JAMES POWERS
Deputy Fireproofing 7/21/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/21/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/24/2017 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 7/24/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 7/24/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 7/25/2017 Conditional Approval ERNESTO CORRAL
Deputy Fireproofing 7/25/2017 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 7/25/2017 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 7/26/2017 Conditional Approval NICK DANERI
Deputy Fireproofing 7/26/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 7/26/2017 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 7/27/2017 Conditional Approval ERNESTO CORRAL
Deputy Fireproofing 7/27/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/27/2017 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 7/27/2017 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 7/28/2017 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 7/28/2017 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 7/28/2017 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 7/31/2017 Partial Approval JOEY BUCHANAN
T-Bar Ceiling 7/31/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 8/1/2017 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 8/1/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 8/1/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 8/2/2017 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 8/2/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 8/2/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 8/3/2017 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 8/3/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 8/3/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 8/4/2017 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 8/4/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 8/4/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 8/8/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/8/2017 Partial Approval JAMES POWERS
Special/Order Compliance 8/8/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/9/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/9/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/10/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/10/2017 Partial Approval JAMES POWERS
T-Bar Ceiling 8/10/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/11/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/11/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/11/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/14/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/14/2017 Partial Approval JAMES POWERS
T-Bar Ceiling 8/14/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/15/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/15/2017 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/15/2017 Partial Inspection JAMES POWERS
Deputy Drilled-In Anchors 8/16/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/16/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/17/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/17/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/18/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/18/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/21/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/21/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/22/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/22/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/23/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 8/23/2017 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 8/23/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 8/24/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/24/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/24/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/25/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/25/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/25/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/28/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/28/2017 Partial Approval JAMES POWERS
Pre-Inspection 8/29/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/30/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/31/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/1/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/5/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/5/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/5/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/6/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/6/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/6/2017 Partial Approval JAMES POWERS
Pre-Inspection 9/6/2017 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 9/7/2017 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 9/7/2017 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 9/7/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 9/8/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/8/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/8/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/11/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/11/2017 Partial Approval JAMES POWERS
Green Building Rough 9/11/2017 Partial Inspection JOHN KLARIN
Light Gage Steel Frame 9/11/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/12/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/12/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/13/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/13/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/13/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/14/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/14/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/14/2017 Partial Approval JAMES POWERS
Pre-Inspection 9/14/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/15/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/15/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/15/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/18/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/18/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/18/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/19/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/19/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/19/2017 Partial Approval JAMES POWERS
Pre-Inspection 9/19/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/20/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/20/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/20/2017 Partial Approval JAMES POWERS
Pre-Inspection 9/20/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/21/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/21/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/21/2017 Partial Approval JAMES POWERS
Pre-Inspection 9/21/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/22/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/22/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/22/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/28/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/29/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/2/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/3/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/4/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/5/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/6/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/11/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/17/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/17/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/18/2017 Partial Approval JAMES POWERS
Pre-Inspection 1/8/2018 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 3/7/2018 Approved JAMES POWERS
Special/Order Compliance 9/5/2018 Approved JAMES POWERS
Special/Order Compliance 2/26/2019 Partial Approval JAMES POWERS
Special/Order Compliance 9/9/2019 Approved JAMES POWERS
Drywall Nailing 2/24/2020 Approved JAMES POWERS
Final 2/24/2020 OK to Issue CofO JAMES POWERS
Footing/Foundation/Slab 2/24/2020 Approved JAMES POWERS
Green Building Final 2/24/2020 Approved JAMES POWERS
Green Building Rough 2/24/2020 Approved JAMES POWERS
METHANE-Barrier 2/24/2020 Approved JAMES POWERS
METHANE-Final 2/24/2020 Approved JAMES POWERS
METHANE-Rough 2/24/2020 Approved JAMES POWERS
METHANE-Subgrade 2/24/2020 Approved JAMES POWERS
Reinforced Concrete Frame 2/24/2020 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 2/24/2020 SGSOV Approved JAMES POWERS
Smoke Detectors 2/24/2020 Approved JAMES POWERS
Special/Order Compliance 2/24/2020 Approved JAMES POWERS
Verify Sprinkler Sign Off 2/24/2020 Approved JAMES POWERS