1836 N SICHEL ST 1-27 90031

Certificate Information: 1836 N SICHEL ST 1-27 90031

Application / Permit
15010-10000-03555
Plan Check / Job No.
B15LA13948
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 27 UNIT AFFORDABLE APARTMENT. (With 11% very low income units for 35% bonus increase.)
Permit Issued
Issued on 4/14/2017
Issuing Office
Metro
Current Status
CofO Issued on 11/1/2018
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2015 APPLICANT
Disabled Access Plans Picked Up 10/15/2015 APPLICANT
Assigned to Plan Check Engineer 10/22/2015 LARRY LEE
Corrections Issued 10/28/2015 LARRY LEE
Quality Review Completed 11/5/2015 BILL STUTSMAN
Building Plans Picked Up 11/10/2015 APPLICANT
Green Plans Picked Up 11/10/2015 APPLICANT
Applicant returned to address corrections 3/24/2016 LARRY LEE
Applicant returned to address corrections 4/12/2016 LARRY LEE
Applicant returned to address corrections 5/10/2016 LARRY LEE
Applicant returned to address corrections 6/9/2016 LARRY LEE
Applicant returned to address corrections 6/14/2016 LARRY LEE
Applicant returned to address corrections 2/16/2017 LARRY LEE
Applicant returned to address corrections 3/31/2017 LARRY LEE
Plan Check Approved 4/5/2017 LARRY LEE
Issued 4/14/2017 LADBS
CofO in Progress 10/17/2018 ERNESTO CORRAL
CofO Issued 11/1/2018 RICKEY JACKSON
Permit Finaled 11/1/2018 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 11/16/2015 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/16/2015 LEE GUILBEAUX
Highway dedication Cleared 12/24/2015 JAMES MORALEZ
Frnt yard landscape/Water mgmt Cleared 1/8/2016 DANIEL SKOLNICK
Opn space landscape/Water mgmt Cleared 1/8/2016 DANIEL SKOLNICK
Hydrant and Access approval Cleared 2/10/2016 ROBERT DUFF
Internal circulation Cleared 2/10/2016 COLLINS ALLAN
Fire Marshall Fire Life Safety Cleared 10/19/2016 OSCAR SALGADO JR
Green Code Cleared 12/13/2016 JOHN KLARIN
Low Impact Development Cleared 12/21/2016 SAM NAVID
Stormwater Pollution Mitigatn Cleared 12/21/2016 SAM NAVID
Permit Cleared 12/22/2016 JAMES KHO
Roof/Waste drainage to street Cleared 12/22/2016 JAMES KHO
Sewer availability Cleared 12/22/2016 JAMES KHO
Housing density bonus Cleared 1/5/2017 MARITES CUNANAN
DAS Clearance Cleared 3/21/2017 WAI LAU

Contact Information

Contractor Tipping Development Inc; Lic. No.: 960202-B 911 S PRIMROSE AVE UNIT P      MONROVIA, CA 91016
Engineer Lota, Dante S; Lic. No.: S2314 19325 TRENTHAM AVE      CERRITOS, CA 90701

Inspector Information

LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JEFFREY FULTON, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Masonry 8/31/2017 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 8/31/2017 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 9/14/2017 Approved FELIX CEBALLOS
Deputy Reinf. Concrete 9/18/2017 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 9/19/2017 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 9/19/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 9/20/2017 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 9/29/2017 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 10/13/2017 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 10/20/2017 Partial Inspection ERNESTO CORRAL
Pre-Inspection 10/20/2017 Approved ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 10/27/2017 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 10/31/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/8/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/19/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/19/2017 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 1/18/2018 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 2/6/2018 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/14/2018 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 3/1/2018 Approved ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 3/13/2018 Partial Inspection ERNESTO CORRAL
Insulation 4/6/2018 Partial Inspection ERNESTO CORRAL
Insulation 4/27/2018 Partial Inspection ERNESTO CORRAL
Drywall Nailing 5/9/2018 Partial Inspection ERNESTO CORRAL
Insulation 5/10/2018 Partial Inspection ERNESTO CORRAL
Drywall Nailing 5/11/2018 Partial Inspection ERNESTO CORRAL
Drywall Nailing 5/22/2018 Partial Inspection ERNESTO CORRAL
Insulation 5/29/2018 Approved ERNESTO CORRAL
Interior/Exterior Lathing 5/29/2018 Approved ERNESTO CORRAL
Drywall Nailing 7/11/2018 Approved ERNESTO CORRAL
Green Building Rough 7/11/2018 Approved ERNESTO CORRAL
Verify Sprinkler Sign Off 7/11/2018 Approved ERNESTO CORRAL
Wood Frame 7/11/2018 Approved ERNESTO CORRAL
Final 9/24/2018 Partial Inspection ERNESTO CORRAL
Green Building Final 9/24/2018 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 9/24/2018 Approved ERNESTO CORRAL
Reinforced Masonry Frame 9/24/2018 Approved ERNESTO CORRAL
SGSOV-Seismic Gas S/O Valve 9/24/2018 SGSOV Approved ERNESTO CORRAL
Smoke Detectors 9/24/2018 Approved ERNESTO CORRAL
Final 9/28/2018 Partial Inspection ERNESTO CORRAL
Green Building Final 9/28/2018 Partial Inspection ERNESTO CORRAL
Final 10/17/2018 OK to Issue CofO ERNESTO CORRAL
Green Building Final 10/17/2018 Approved ERNESTO CORRAL