953 N SYCAMORE AVE 90038

Certificate Information: 953 N SYCAMORE AVE 90038

Application / Permit
15010-10000-03563
Plan Check / Job No.
B15LA13964
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(21) Motion Picture Production
Work Description
8-Story Media Production Office Building with 2-levels of Subterranean Parking
Permit Issued
Issued on 8/15/2016
Issuing Office
Metro
Current Status
CofO Issued on 5/28/2019
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2015 APPLICANT
Assigned to Plan Check Engineer 10/29/2015 ALLEN MANALANSAN
Corrections Issued 11/18/2015 ALLEN MANALANSAN
Quality Review Completed 12/3/2015 JOHN VASQUEZ
Building Plans Picked Up 12/3/2015 APPLICANT
Applicant returned to address corrections 1/15/2016 ALLEN MANALANSAN
Applicant returned to address corrections 2/8/2016 ALLEN MANALANSAN
Applicant returned to address corrections 3/1/2016 ALLEN MANALANSAN
Applicant returned to address corrections 5/2/2016 ALLEN MANALANSAN
Applicant returned to address corrections 5/10/2016 ALLEN MANALANSAN
Applicant returned to address corrections 5/17/2016 ALLEN MANALANSAN
Applicant returned to address corrections 7/21/2016 ALLEN MANALANSAN
Applicant returned to address corrections 7/22/2016 ALLEN MANALANSAN
Plan Check Approved 8/15/2016 ALLEN MANALANSAN
Issued 8/15/2016 LADBS
TCO Issued (Expire Date: 09-17-2019) 3/21/2019 DAVID TSAU
CofO in Progress 5/23/2019 JEFF BYTHEWAY
Permit Finaled 5/28/2019 TERRY HERR
CofO Issued 5/28/2019 TERRY HERR
Permit Finaled 5/28/2019 TERRY HERR

Permit Application Clearance Information

Site Plan review Cleared 12/7/2015 MARITZA PRZEKOP
Address approval Cleared 12/11/2015 ADRIAN HERNANDEZ
Permit Cleared 12/11/2015 ADRIAN HERNANDEZ
Driveway location Cleared 3/25/2016 TAIMOUR TANAVOLI
Eng Process Fee Ord 176,300 Cleared 3/25/2016 ARNULFO NUNO
Highway dedication Cleared 3/25/2016 ARNULFO NUNO
Internal circulation Cleared 3/25/2016 TAIMOUR TANAVOLI
Sewer availability Cleared 3/25/2016 ARNULFO NUNO
Hydrant and Access approval Cleared 4/11/2016 ROBERT DUFF
Low Impact Development Cleared 6/21/2016 MICHAEL SCADUTO
Stormwater Pollution Mitigatn Cleared 6/21/2016 MICHAEL SCADUTO
DAS Clearance Cleared 7/15/2016 ALLEN MANALANSAN
Excavation more than 5-ft deep Cleared 7/22/2016 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 7/25/2016 ADRIAN SANCHEZ
Construction near power lines Cleared 7/26/2016 LUCIO FERRER
Construction within easement Cleared 7/26/2016 LUCIO FERRER
Building over 3-story or 36-ft Cleared 8/2/2016 CALOSHA APPROVED
Miscellaneous Cleared 8/8/2016 TERRY PHAN
Work Adjacent to Public Way Cleared 8/8/2016 TERRY PHAN
Green Code Cleared 8/12/2016 ALLEN MANALANSAN
Methane Ordinance Cleared 8/12/2016 DAVE MYERS

Contact Information

Architect O'Herlihy, Lorcan Patrick; Lic. No.: C24245 1537 LA CIENEGA BLVD      LOS ANGELES, CA 90035
Contractor Owner-Builder       ,
Engineer Broad, Michael Charles; Lic. No.: C37457 2417 SHADY FOREST LANE      ORANGE, CA 92667
Engineer Knur, Reinard Thomas; Lic. No.: GE2755 1435 MONCADO DR      GLENDALE, CA 91207
Engineer Ortiz, David Arturo; Lic. No.: C56818 7248 BECKFORD AVE      RESEDA, CA 91335
Engineer Tofani, Glenn David; Lic. No.: C44229 77 BUNSEN      IRVINE, CA 92618

Inspector Information

ALFREDO LOPEZ, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 10/21/2016 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 10/24/2016 Conditional Approval GREGORY POMISH
Deputy Drilled-In Anchors 10/26/2016 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 2/15/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 4/19/2017 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 5/4/2017 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 5/5/2017 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 5/9/2017 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 5/10/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 5/10/2017 Partial Inspection GREGORY POMISH
METHANE-Barrier 5/10/2017 Partial Approval GREGORY POMISH
METHANE-Subgrade 5/10/2017 Partial Inspection GREGORY POMISH
Deputy Methane Barrier 5/11/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 5/11/2017 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 5/12/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 5/15/2017 Partial Approval GREGORY POMISH
METHANE-Barrier 5/15/2017 Partial Inspection GREGORY POMISH
METHANE-Subgrade 5/15/2017 Partial Inspection GREGORY POMISH
Deputy Shotcrete 5/16/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 5/17/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 5/19/2017 No Access for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 5/22/2017 Conditional Approval GREGORY POMISH
METHANE-Barrier 5/22/2017 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 5/23/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 5/24/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 5/25/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 5/26/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 5/30/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 5/31/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 5/31/2017 Partial Approval GREGORY POMISH
METHANE-Barrier 5/31/2017 Partial Inspection GREGORY POMISH
METHANE-Subgrade 5/31/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 6/1/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/2/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/5/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/6/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/7/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/8/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 6/8/2017 Partial Approval GREGORY POMISH
METHANE-Barrier 6/8/2017 Partial Inspection GREGORY POMISH
METHANE-Subgrade 6/8/2017 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 6/9/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/19/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/20/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/21/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/22/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/23/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/26/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 6/27/2017 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 6/28/2017 Conditional Approval GREGORY POMISH
Green Building Rough 6/28/2017 Not Ready for Inspection WILLIAM ROSE
METHANE-Rough 6/28/2017 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 6/28/2017 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 6/28/2017 Not Ready for Inspection GREGORY POMISH
Deputy Methane Barrier 6/29/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/29/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 6/29/2017 Corrections Issued GREGORY POMISH
METHANE-Barrier 6/29/2017 Partial Inspection GREGORY POMISH
METHANE-Subgrade 6/29/2017 Partial Inspection GREGORY POMISH
Deputy Methane Barrier 6/30/2017 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 7/3/2017 No Access for Inspection ERNESTO CORRAL
Deputy Methane Barrier 7/5/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 7/5/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 7/5/2017 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 7/6/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/6/2017 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 7/6/2017 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 7/7/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 7/7/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 7/7/2017 Conditional Approval GREGORY POMISH
METHANE-Rough 7/7/2017 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 7/7/2017 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 7/7/2017 Partial Inspection GREGORY POMISH
Deputy Shotcrete 7/10/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 7/10/2017 Not Ready for Inspection GREGORY POMISH
METHANE-Barrier 7/10/2017 Partial Inspection GREGORY POMISH
METHANE-Subgrade 7/10/2017 Not Ready for Inspection GREGORY POMISH
Deputy Shotcrete 7/11/2017 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 7/12/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 7/12/2017 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 7/13/2017 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 7/14/2017 Conditional Approval GREGORY POMISH
METHANE-Rough 7/14/2017 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 7/14/2017 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 7/14/2017 Not Ready for Inspection GREGORY POMISH
Deputy Methane Barrier 7/17/2017 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/17/2017 Approved SAKO AGHAZARIAN
Deputy Shotcrete 7/17/2017 Approved SAKO AGHAZARIAN
Deputy Methane Barrier 7/18/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 7/18/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 7/19/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 7/19/2017 Partial Approval GREGORY POMISH
METHANE-Barrier 7/19/2017 Approved GREGORY POMISH
METHANE-Subgrade 7/19/2017 Approved GREGORY POMISH
Deputy Methane Barrier 7/20/2017 Conditional Approval GREGORY POMISH
Deputy Methane Barrier 7/21/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 7/21/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 7/24/2017 Conditional Approval GREGORY POMISH
METHANE-Rough 7/24/2017 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 7/24/2017 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 7/24/2017 Not Ready for Inspection GREGORY POMISH
Deputy Shotcrete 7/25/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 7/25/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 7/31/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/1/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 8/1/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 8/2/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/3/2017 Conditional Approval GREGORY POMISH
METHANE-Rough 8/3/2017 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 8/3/2017 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 8/3/2017 Partial Inspection GREGORY POMISH
Deputy Shotcrete 8/4/2017 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 8/4/2017 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/8/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 8/8/2017 Conditional Approval GREGORY POMISH
Green Building Rough 8/8/2017 Not Ready for Inspection WILLIAM ROSE
METHANE-Rough 8/8/2017 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 8/8/2017 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 8/8/2017 Not Ready for Inspection GREGORY POMISH
Deputy Shotcrete 8/9/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 8/9/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 8/10/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/11/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 8/11/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/14/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/15/2017 Conditional Approval GREGORY POMISH
METHANE-Rough 8/15/2017 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 8/15/2017 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 8/15/2017 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 8/16/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/17/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 8/17/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/18/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 8/18/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/22/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/24/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/25/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/28/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 8/29/2017 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 8/30/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/5/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/5/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 9/6/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/7/2017 Conditional Approval GREGORY POMISH
METHANE-Rough 9/7/2017 Approved GREGORY POMISH
Reinforced Concrete Frame 9/7/2017 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 9/7/2017 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 9/8/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 9/11/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 9/12/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 9/13/2017 Approved SAKO AGHAZARIAN
Reinforced Concrete Frame 9/13/2017 Partial Approval SAKO AGHAZARIAN
Verify Sprinkler Sign Off 9/13/2017 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 9/14/2017 Partial Inspection SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/15/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 9/15/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/18/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 9/19/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 9/19/2017 Conditional Approval GREGORY POMISH
Green Building Rough 9/19/2017 Not Ready for Inspection WILLIAM ROSE
Reinforced Concrete Frame 9/19/2017 Not Ready for Inspection GREGORY POMISH
Deputy Shotcrete 9/20/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/20/2017 Not Ready for Inspection GREGORY POMISH
Deputy Shotcrete 9/21/2017 Conditional Approval GREGORY POMISH
Reinforced Concrete Frame 9/21/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 9/22/2017 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 9/26/2017 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 9/27/2017 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 9/28/2017 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 9/29/2017 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 10/2/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 10/2/2017 Partial Approval GREGORY POMISH
Deputy Pre-Stress Concrete 10/3/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/3/2017 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 10/4/2017 Conditional Approval GREGORY POMISH
Green Building Rough 10/5/2017 Not Ready for Inspection WILLIAM ROSE
Reinforced Concrete Frame 10/5/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 10/6/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 10/9/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 10/10/2017 Conditional Approval GREGORY POMISH
Green Building Rough 10/10/2017 Not Ready for Inspection WILLIAM ROSE
Reinforced Concrete Frame 10/10/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 10/11/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 10/11/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 10/11/2017 Partial Approval GREGORY POMISH
Deputy Shotcrete 10/12/2017 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 10/13/2017 Conditional Approval GREGORY POMISH
Reinforced Concrete Frame 10/16/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 10/18/2017 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 10/23/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/23/2017 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 10/24/2017 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 10/25/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 10/25/2017 Partial Approval GREGORY POMISH
Deputy Pre-Stress Concrete 10/26/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 10/27/2017 Partial Approval GREGORY POMISH
Deputy Pre-Stress Concrete 10/30/2017 Conditional Approval GREGORY POMISH
Reinforced Concrete Frame 10/30/2017 Partial Approval GREGORY POMISH
Deputy Pre-Stress Concrete 10/31/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/1/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 11/1/2017 Conditional Approval GREGORY POMISH
Green Building Rough 11/1/2017 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 11/1/2017 Partial Approval GREGORY POMISH
Deputy Shotcrete 11/2/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 11/2/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 11/3/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 11/3/2017 Conditional Approval GREGORY POMISH
Green Building Rough 11/3/2017 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 11/3/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 11/6/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 11/6/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 11/6/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 11/7/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 11/7/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/8/2017 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 11/17/2017 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 11/20/2017 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 11/20/2017 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 11/21/2017 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 11/28/2017 Conditional Approval GREGORY POMISH
Green Building Rough 11/28/2017 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 11/28/2017 Partial Approval GREGORY POMISH
Deputy Pre-Stress Concrete 11/29/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/29/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 11/29/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 11/30/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 11/30/2017 Conditional Approval GREGORY POMISH
Green Building Rough 11/30/2017 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 11/30/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 12/1/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 12/1/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 12/1/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 12/5/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 12/5/2017 Conditional Approval GREGORY POMISH
Green Building Rough 12/5/2017 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 12/5/2017 Partial Approval GREGORY POMISH
Deputy Steel/Welding 12/6/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 12/11/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 12/12/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/14/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/15/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 12/15/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 12/18/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/19/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/20/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/21/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/22/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 12/22/2017 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 12/26/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 12/26/2017 Conditional Approval GREGORY POMISH
Green Building Rough 12/26/2017 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 12/26/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 12/27/2017 Conditional Approval GREGORY POMISH
Deputy Shotcrete 12/27/2017 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 12/27/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 12/28/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/29/2017 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 1/2/2018 Conditional Approval DAVID BURKHEAD
Green Building Rough 1/2/2018 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 1/2/2018 Partial Approval DAVID BURKHEAD
Deputy Shotcrete 1/3/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 1/4/2018 Conditional Approval GREGORY POMISH
Green Building Rough 1/4/2018 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 1/4/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/8/2018 Conditional Approval GREGORY POMISH
Reinforced Masonry Frame 1/10/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/11/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 1/12/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 1/16/2018 Partial Approval GREGORY POMISH
Deputy Pre-Stress Concrete 1/19/2018 Conditional Approval GREGORY POMISH
Green Building Rough 1/19/2018 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 1/19/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/22/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 1/22/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/23/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 1/24/2018 Conditional Approval GREGORY POMISH
Green Building Rough 1/24/2018 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 1/24/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/25/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 1/26/2018 Conditional Approval GREGORY POMISH
Deputy Shotcrete 1/26/2018 Conditional Approval GREGORY POMISH
Green Building Rough 1/30/2018 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 1/30/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/31/2018 Conditional Approval GREGORY POMISH
Deputy Shotcrete 1/31/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 2/1/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 2/8/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 2/9/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 2/12/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 2/12/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 2/13/2018 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 2/14/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 2/14/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 2/15/2018 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 2/16/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 2/16/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 2/16/2018 Conditional Approval GREGORY POMISH
Reinforced Masonry Frame 2/16/2018 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 2/17/2018 Partial Approval GREGORY POMISH
Deputy Shotcrete 2/20/2018 Conditional Approval GREGORY POMISH
Green Building Rough 2/20/2018 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 2/20/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 2/21/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 2/21/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 2/22/2018 Conditional Approval GREGORY POMISH
Deputy Shotcrete 2/22/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 2/23/2018 Conditional Approval GREGORY POMISH
Green Building Rough 2/26/2018 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 2/26/2018 Partial Inspection ERNESTO CORRAL
Deputy Shotcrete 2/27/2018 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/27/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 2/28/2018 Conditional Approval GREGORY POMISH
Deputy Other (see comments) 3/9/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 3/9/2018 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 3/12/2018 Conditional Approval GREGORY POMISH
Deputy Drilled-In Anchors 3/13/2018 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 3/13/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 3/13/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 3/13/2018 Partial Approval GREGORY POMISH
Deputy Pre-Stress Concrete 3/14/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 3/14/2018 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 3/15/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 3/19/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 3/19/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 3/19/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 3/20/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 3/21/2018 Conditional Approval GREGORY POMISH
Deputy Shotcrete 3/21/2018 Conditional Approval GREGORY POMISH
Green Building Rough 3/21/2018 Approved GREGORY POMISH
Reinforced Concrete Frame 3/21/2018 Partial Approval GREGORY POMISH
Deputy Pre-Stress Concrete 3/23/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 3/27/2018 Conditional Approval GREGORY POMISH
Reinforced Concrete Frame 3/28/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 4/2/2018 Conditional Approval GREGORY POMISH
Deputy Drilled-In Anchors 4/4/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/4/2018 Conditional Approval GREGORY POMISH
Deputy Drilled-In Anchors 4/5/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 4/5/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 4/10/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 4/11/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 4/11/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 4/12/2018 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 4/16/2018 Conditional Approval GREGORY POMISH
Deputy Pre-Stress Concrete 4/17/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 4/17/2018 Partial Approval GREGORY POMISH
Deputy Pre-Stress Concrete 4/18/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 4/18/2018 Conditional Approval GREGORY POMISH
Deputy Shotcrete 4/20/2018 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 4/20/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/25/2018 Conditional Approval GREGORY POMISH
Deputy Shotcrete 4/25/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/26/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/27/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 5/2/2018 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 5/3/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 5/3/2018 Conditional Approval GREGORY POMISH
Reinforced Concrete Frame 5/3/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 5/4/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 5/7/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 5/8/2018 Conditional Approval GREGORY POMISH
Deputy Other (see comments) 5/10/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 5/10/2018 Conditional Approval GREGORY POMISH
Reinforced Masonry Frame 5/10/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 5/15/2018 Conditional Approval GREGORY POMISH
Reinforced Masonry Frame 5/18/2018 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 5/21/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 5/23/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 5/25/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 5/30/2018 Conditional Approval GREGORY POMISH
Light Gage Steel Frame 6/25/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 6/29/2018 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 7/2/2018 Conditional Approval GREGORY POMISH
Drywall Nailing 7/11/2018 Partial Approval GREGORY POMISH
Light Gage Steel Frame 7/11/2018 Partial Approval GREGORY POMISH
Drywall Nailing 7/16/2018 Partial Approval GREGORY POMISH
Light Gage Steel Frame 7/16/2018 Partial Inspection GREGORY POMISH
Light Gage Steel Frame 7/23/2018 Not Ready for Inspection GREGORY POMISH
Light Gage Steel Frame 10/23/2018 Partial Approval GREGORY POMISH
Deputy Drilled-In Anchors 1/8/2019 Approved GREGORY POMISH
Deputy Drilled-In Anchors 1/9/2019 Approved GREGORY POMISH
Deputy Reinf. Masonry 1/11/2019 Approved GREGORY POMISH
Deputy Reinf. Masonry 1/14/2019 Approved GREGORY POMISH
Final 1/29/2019 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 1/29/2019 Approved GREGORY POMISH
Green Building Final 1/29/2019 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 1/29/2019 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 1/29/2019 SGSOV Approved GREGORY POMISH
Smoke Detectors 1/29/2019 Not Ready for Inspection GREGORY POMISH
Final 2/26/2019 Partial Inspection GREGORY POMISH
Green Building Final 2/26/2019 Not Ready for Inspection GREGORY POMISH
Smoke Detectors 2/26/2019 Not Ready for Inspection GREGORY POMISH
Final 3/8/2019 Not Ready for Inspection GREGORY POMISH
Green Building Final 3/8/2019 Not Ready for Inspection GREGORY POMISH
Smoke Detectors 3/8/2019 Not Ready for Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 3/21/2019 Partial Inspection GREGORY POMISH
Final 5/1/2019 Not Ready for Inspection HAMID PISHEHVAR
Green Building Final 5/1/2019 Not Ready for Inspection HAMID PISHEHVAR
Smoke Detectors 5/1/2019 Not Ready for Inspection HAMID PISHEHVAR
Final 5/10/2019 Not Ready for Inspection JEFF BYTHEWAY
Green Building Final 5/10/2019 Approved JEFF BYTHEWAY
Smoke Detectors 5/10/2019 Approved JEFF BYTHEWAY
Final 5/21/2019 Not Ready for Inspection DAVID BURKHEAD
Final 5/22/2019 OK to Issue CofO JEFF BYTHEWAY