832 N CHEROKEE AVE 90038

Certificate Information: 832 N CHEROKEE AVE 90038

Application / Permit
15010-20000-01299
Plan Check / Job No.
B15VN04236
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 75'6"x40'0" Type V-B SFD and attached two car garage.Buidling To have Nfpa 13D fire sprinkler system.See Comments
Permit Issued
Issued on 6/5/2015
Issuing Office
Valley
Current Status
CofO Issued on 11/18/2016
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2015 APPLICANT
Green Plans Picked Up 4/13/2015 APPLICANT
Assigned to Plan Check Engineer 4/30/2015 FARUK SEZER
Corrections Issued 5/4/2015 FARUK SEZER
Quality Review Completed 5/11/2015 TIEN JEN WANG
Building Plans Picked Up 5/18/2015 APPLICANT
Applicant returned to address corrections 5/29/2015 FARUK SEZER
Plan Check Approved 6/5/2015 FARUK SEZER
Issued 6/5/2015 LADBS
CofO in Progress 10/27/2016 BRIAN SULLIVAN
Permit Finaled 11/18/2016 MARK CASEY
CofO Issued 11/18/2016 MARK CASEY
Permit Finaled 11/18/2016 MARK CASEY

Permit Application Clearance Information

Green Code Cleared 5/26/2015 MICKEY YAMASHITA
Eng Process Fee Ord 176,300 Cleared 5/28/2015 SANDRA FIGUEROA
Hydrant and Access approval Cleared 5/28/2015 JOHN CONNEALLY
Low Impact Development Cleared 5/28/2015 KOSTA KAPORIS
Permit Cleared 5/28/2015 SANDRA FIGUEROA
Roof/Waste drainage to street Cleared 5/28/2015 SANDRA FIGUEROA
Sewer availability Cleared 5/28/2015 SANDRA FIGUEROA

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/24/2015 Corrections Issued RUBEN SALAS
METHANE-Barrier 7/24/2015 Not Ready for Inspection RUBEN SALAS
METHANE-Subgrade 7/24/2015 Not Ready for Inspection RUBEN SALAS
Excavation/Setback/Form/Re-Bar 7/27/2015 Partial Approval RUBEN SALAS
Deputy Reinf. Concrete 7/28/2015 Partial Approval RUBEN SALAS
PLUMBING-Rough 8/5/2015 Partial Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 8/6/2015 Partial Inspection RUBEN SALAS
Insulation 8/6/2015 Partial Approval RUBEN SALAS
BUILDING-Rough-Frame 8/18/2015 Not Ready for Inspection RUBEN SALAS
Green Building Rough 8/18/2015 Not Ready for Inspection RUBEN SALAS
METHANE-Rough 8/18/2015 Not Ready for Inspection RUBEN SALAS
Verify Sprinkler Sign Off 8/18/2015 Not Ready for Inspection RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 9/1/2015 Partial Approval RUBEN SALAS
ELECTRICAL-Rough 10/7/2015 Approved RUBEN SALAS
HVAC-Rough 10/7/2015 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 10/7/2015 Approved RUBEN SALAS
HVAC-Rough 10/9/2015 Approved RUBEN SALAS
PLUMBING-Rough 10/9/2015 Not Ready for Inspection RUBEN SALAS
Green Building Rough 10/19/2015 Partial Inspection RUBEN SALAS
Wood Frame 10/19/2015 Corrections Issued RUBEN SALAS
BUILDING-Rough-Frame 10/21/2015 Corrections Issued RUBEN SALAS
METHANE-Rough 10/21/2015 Not Ready for Inspection RUBEN SALAS
Verify Sprinkler Sign Off 10/21/2015 Approved RUBEN SALAS
Interior/Exterior Lathing 10/22/2015 Not Ready for Inspection RUBEN SALAS
Wood Frame 10/22/2015 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 10/28/2015 Corrections Issued RUBEN SALAS
Insulation 10/28/2015 Approved RUBEN SALAS
Interior/Exterior Lathing 10/28/2015 Partial Approval RUBEN SALAS
Wood Frame 10/28/2015 Partial Approval RUBEN SALAS
Drywall Nailing 11/12/2015 Not Ready for Inspection RUBEN SALAS
Drywall Nailing 11/13/2015 Approved RUBEN SALAS
Interior/Exterior Lathing 12/8/2015 Approved RUBEN SALAS
Sewer 1/27/2016 Approved RUBEN SALAS
Insulation 5/20/2016 Approved RUBEN SALAS
Drywall Nailing 5/26/2016 Approved RUBEN SALAS
ELECTRICAL-Final 9/8/2016 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Final 9/8/2016 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 9/8/2016 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 9/19/2016 Approved BRIAN SULLIVAN
Gas Test 9/19/2016 Approved BRIAN SULLIVAN
HVAC-Final 9/19/2016 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 9/19/2016 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Final 9/21/2016 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 9/21/2016 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 9/26/2016 Approved BRIAN SULLIVAN
Final 9/26/2016 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 9/26/2016 Approved BRIAN SULLIVAN
Green Building Final 9/26/2016 Approved BRIAN SULLIVAN
Green Building Rough 9/26/2016 Approved BRIAN SULLIVAN
HVAC-Final 9/26/2016 Approved BRIAN SULLIVAN
METHANE-Barrier 9/26/2016 Approved BRIAN SULLIVAN
METHANE-Final 9/26/2016 Approved BRIAN SULLIVAN
METHANE-Rough 9/26/2016 Approved BRIAN SULLIVAN
METHANE-Subgrade 9/26/2016 Approved BRIAN SULLIVAN
PLUMBING-Final 9/26/2016 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/26/2016 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 9/26/2016 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 9/30/2016 Not Ready for Inspection BRIAN SULLIVAN
Final 9/30/2016 Not Ready for Inspection BRIAN SULLIVAN
Smoke Detectors 9/30/2016 Not Ready for Inspection BRIAN SULLIVAN
Final 10/5/2016 Conditional Approval BRIAN SULLIVAN
Service/Power Release 10/5/2016 Approved BRIAN SULLIVAN
Smoke Detectors 10/5/2016 Approved BRIAN SULLIVAN