832 N CHEROKEE AVE 90038
Certificate Information: 832 N CHEROKEE AVE 90038
- Application / Permit
- 15010-20000-01299
- Plan Check / Job No.
- B15VN04236
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 75'6"x40'0" Type V-B SFD and attached two car garage.Buidling To have Nfpa 13D fire sprinkler system.See Comments
- Permit Issued
- Issued on 6/5/2015
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/18/2016
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 4/8/2015 | APPLICANT |
Green Plans Picked Up | 4/13/2015 | APPLICANT |
Assigned to Plan Check Engineer | 4/30/2015 | FARUK SEZER |
Corrections Issued | 5/4/2015 | FARUK SEZER |
Quality Review Completed | 5/11/2015 | TIEN JEN WANG |
Building Plans Picked Up | 5/18/2015 | APPLICANT |
Applicant returned to address corrections | 5/29/2015 | FARUK SEZER |
Plan Check Approved | 6/5/2015 | FARUK SEZER |
Issued | 6/5/2015 | LADBS |
CofO in Progress | 10/27/2016 | BRIAN SULLIVAN |
Permit Finaled | 11/18/2016 | MARK CASEY |
CofO Issued | 11/18/2016 | MARK CASEY |
Permit Finaled | 11/18/2016 | MARK CASEY |
Permit Application Clearance Information
Green Code | Cleared | 5/26/2015 | MICKEY YAMASHITA |
Eng Process Fee Ord 176,300 | Cleared | 5/28/2015 | SANDRA FIGUEROA |
Hydrant and Access approval | Cleared | 5/28/2015 | JOHN CONNEALLY |
Low Impact Development | Cleared | 5/28/2015 | KOSTA KAPORIS |
Permit | Cleared | 5/28/2015 | SANDRA FIGUEROA |
Roof/Waste drainage to street | Cleared | 5/28/2015 | SANDRA FIGUEROA |
Sewer availability | Cleared | 5/28/2015 | SANDRA FIGUEROA |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Nazari, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 7/24/2015 | Corrections Issued | RUBEN SALAS |
METHANE-Barrier | 7/24/2015 | Not Ready for Inspection | RUBEN SALAS |
METHANE-Subgrade | 7/24/2015 | Not Ready for Inspection | RUBEN SALAS |
Excavation/Setback/Form/Re-Bar | 7/27/2015 | Partial Approval | RUBEN SALAS |
Deputy Reinf. Concrete | 7/28/2015 | Partial Approval | RUBEN SALAS |
PLUMBING-Rough | 8/5/2015 | Partial Approval | RUBEN SALAS |
Floor/Roof Diaphrgm/Shear Wall | 8/6/2015 | Partial Inspection | RUBEN SALAS |
Insulation | 8/6/2015 | Partial Approval | RUBEN SALAS |
BUILDING-Rough-Frame | 8/18/2015 | Not Ready for Inspection | RUBEN SALAS |
Green Building Rough | 8/18/2015 | Not Ready for Inspection | RUBEN SALAS |
METHANE-Rough | 8/18/2015 | Not Ready for Inspection | RUBEN SALAS |
Verify Sprinkler Sign Off | 8/18/2015 | Not Ready for Inspection | RUBEN SALAS |
Floor/Roof Diaphrgm/Shear Wall | 9/1/2015 | Partial Approval | RUBEN SALAS |
ELECTRICAL-Rough | 10/7/2015 | Approved | RUBEN SALAS |
HVAC-Rough | 10/7/2015 | Not Ready for Inspection | RUBEN SALAS |
PLUMBING-Rough | 10/7/2015 | Approved | RUBEN SALAS |
HVAC-Rough | 10/9/2015 | Approved | RUBEN SALAS |
PLUMBING-Rough | 10/9/2015 | Not Ready for Inspection | RUBEN SALAS |
Green Building Rough | 10/19/2015 | Partial Inspection | RUBEN SALAS |
Wood Frame | 10/19/2015 | Corrections Issued | RUBEN SALAS |
BUILDING-Rough-Frame | 10/21/2015 | Corrections Issued | RUBEN SALAS |
METHANE-Rough | 10/21/2015 | Not Ready for Inspection | RUBEN SALAS |
Verify Sprinkler Sign Off | 10/21/2015 | Approved | RUBEN SALAS |
Interior/Exterior Lathing | 10/22/2015 | Not Ready for Inspection | RUBEN SALAS |
Wood Frame | 10/22/2015 | Not Ready for Inspection | RUBEN SALAS |
BUILDING-Rough-Frame | 10/28/2015 | Corrections Issued | RUBEN SALAS |
Insulation | 10/28/2015 | Approved | RUBEN SALAS |
Interior/Exterior Lathing | 10/28/2015 | Partial Approval | RUBEN SALAS |
Wood Frame | 10/28/2015 | Partial Approval | RUBEN SALAS |
Drywall Nailing | 11/12/2015 | Not Ready for Inspection | RUBEN SALAS |
Drywall Nailing | 11/13/2015 | Approved | RUBEN SALAS |
Interior/Exterior Lathing | 12/8/2015 | Approved | RUBEN SALAS |
Sewer | 1/27/2016 | Approved | RUBEN SALAS |
Insulation | 5/20/2016 | Approved | RUBEN SALAS |
Drywall Nailing | 5/26/2016 | Approved | RUBEN SALAS |
ELECTRICAL-Final | 9/8/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
HVAC-Final | 9/8/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
PLUMBING-Final | 9/8/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
ELECTRICAL-Final | 9/19/2016 | Approved | BRIAN SULLIVAN |
Gas Test | 9/19/2016 | Approved | BRIAN SULLIVAN |
HVAC-Final | 9/19/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
PLUMBING-Final | 9/19/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
HVAC-Final | 9/21/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
PLUMBING-Final | 9/21/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
BUILDING-Rough-Frame | 9/26/2016 | Approved | BRIAN SULLIVAN |
Final | 9/26/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
Footing/Foundation/Slab | 9/26/2016 | Approved | BRIAN SULLIVAN |
Green Building Final | 9/26/2016 | Approved | BRIAN SULLIVAN |
Green Building Rough | 9/26/2016 | Approved | BRIAN SULLIVAN |
HVAC-Final | 9/26/2016 | Approved | BRIAN SULLIVAN |
METHANE-Barrier | 9/26/2016 | Approved | BRIAN SULLIVAN |
METHANE-Final | 9/26/2016 | Approved | BRIAN SULLIVAN |
METHANE-Rough | 9/26/2016 | Approved | BRIAN SULLIVAN |
METHANE-Subgrade | 9/26/2016 | Approved | BRIAN SULLIVAN |
PLUMBING-Final | 9/26/2016 | Approved | BRIAN SULLIVAN |
SGSOV-Seismic Gas S/O Valve | 9/26/2016 | SGSOV Approved | BRIAN SULLIVAN |
Smoke Detectors | 9/26/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
ELECTRICAL-Final | 9/30/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
Final | 9/30/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
Smoke Detectors | 9/30/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
Final | 10/5/2016 | Conditional Approval | BRIAN SULLIVAN |
Service/Power Release | 10/5/2016 | Approved | BRIAN SULLIVAN |
Smoke Detectors | 10/5/2016 | Approved | BRIAN SULLIVAN |