11162 W EXPOSITION BLVD 90064
Certificate Information: 11162 W EXPOSITION BLVD 90064
- Application / Permit
- 15010-30000-01303
- Plan Check / Job No.
- B15WL01860
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- new (3) units apartment
- Permit Issued
- Issued on 10/8/2015
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/15/2017
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 4/8/2015 | APPLICANT |
Assigned to Plan Check Engineer | 4/23/2015 | SHANGQIN XIE |
Green Plans Picked Up | 4/24/2015 | APPLICANT |
Corrections Issued | 4/29/2015 | SHANGQIN XIE |
Quality Review Completed | 5/7/2015 | KAMRAN GHOTBI RAVANDI |
Building Plans Picked Up | 5/11/2015 | APPLICANT |
Applicant returned to address corrections | 6/25/2015 | SHANGQIN XIE |
Applicant returned to address corrections | 9/2/2015 | SHANGQIN XIE |
Applicant returned to address corrections | 10/7/2015 | SHANGQIN XIE |
Plan Check Approved | 10/8/2015 | SHANGQIN XIE |
Issued | 10/8/2015 | LADBS |
CofO in Progress | 5/15/2017 | DAVID TSAU |
CofO in Progress | 5/15/2017 | DAVID TSAU |
CofO in Progress | 5/15/2017 | TONY HARTONO |
Permit Finaled | 5/15/2017 | DAVID TSAU |
CofO Issued | 5/15/2017 | DAVID TSAU |
Permit Finaled | 5/15/2017 | DAVID TSAU |
Permit Application Clearance Information
DAS Clearance | Cleared | 8/11/2015 | SHINE LIN |
Address approval | Cleared | 8/13/2015 | ADRIAN HERNANDEZ |
Eng Process Fee Ord 176,300 | Cleared | 8/13/2015 | ADRIAN HERNANDEZ |
Hydrant and Access approval | Cleared | 8/13/2015 | ROBERT DUFF |
Metro Rail approval | Cleared | 8/18/2015 | THAN WIN |
Low Impact Development | Cleared | 8/27/2015 | IDA MEISAMI-FARD |
Roof/Waste drainage to street | Cleared | 8/27/2015 | AVALYN KAMACHI |
Green Code | Cleared | 9/1/2015 | RICHARD GARCIA |
Sewer availability | Cleared | 9/2/2015 | HUGO RICO |
Miscellaneous | Cleared | 9/23/2015 | ANDREW KO |
Grading Pre-Inspection | Cleared | 10/7/2015 | KAMRAN GHOTBI RAVANDI |
Contact Information
Contractor | Eurocon Group Inc; Lic. No.: 708010-B | 923 HILTS AVE LOS ANGELES, CA 90024 |
Engineer | Basseri, Siavash; Lic. No.: C45487 | 1205 MAPLE ST SANTA MONICA, CA 90405 |
Engineer | Foroughi, Mohammad Hossein; Lic. No.: C66179 | PO BOX 643079 LOS ANGELES, CA 90064 |
Inspector Information
DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 2/11/2016 | Partial Approval | DERRICK SPENCER |
Excavation/Setback/Form/Re-Bar | 2/12/2016 | Partial Approval | DERRICK SPENCER |
Footing/Foundation/Slab | 4/4/2016 | Partial Approval | DERRICK SPENCER |
Excavation/Setback/Form/Re-Bar | 4/5/2016 | Partial Approval | DERRICK SPENCER |
Footing/Foundation/Slab | 4/18/2016 | Partial Approval | DERRICK SPENCER |
Green Building Rough | 5/26/2016 | Not Ready for Inspection | BRYAN MEYER |
Verify Sprinkler Sign Off | 5/26/2016 | Approved | DERRICK SPENCER |
Wood Frame | 5/26/2016 | Partial Approval | DERRICK SPENCER |
Green Building Rough | 6/27/2016 | Not Ready for Inspection | BRYAN MEYER |
Wood Frame | 6/27/2016 | Partial Approval | DERRICK SPENCER |
Floor/Roof Diaphrgm/Shear Wall | 8/3/2016 | Partial Approval | TONY HARTONO |
Interior/Exterior Lathing | 8/3/2016 | Not Ready for Inspection | TONY HARTONO |
Interior/Exterior Lathing | 8/15/2016 | Partial Approval | TONY HARTONO |
Green Building Rough | 10/6/2016 | Partial Approval | BRYAN MEYER |
Green Building Rough | 10/11/2016 | Partial Approval | BRYAN MEYER |
Wood Frame | 10/11/2016 | Not Ready for Inspection | TONY HARTONO |
Drywall Nailing | 10/13/2016 | Partial Approval | TONY HARTONO |
Insulation | 10/13/2016 | Partial Approval | TONY HARTONO |
Green Building Rough | 10/17/2016 | Not Ready for Inspection | BRYAN MEYER |
Green Building Rough | 10/19/2016 | Approved | BRYAN MEYER |
Wood Frame | 10/19/2016 | Partial Inspection | TONY HARTONO |
Wood Frame | 10/24/2016 | Partial Approval | TONY HARTONO |
Insulation | 10/26/2016 | Partial Approval | TONY HARTONO |
Insulation | 11/8/2016 | Approved | JONATHAN ALLEN |
Drywall Nailing | 11/17/2016 | Approved | SORIN CIRSTOIU |
Interior/Exterior Lathing | 11/17/2016 | Approved | TONY HARTONO |
Green Building Final | 3/30/2017 | Approved | JOHN KLARIN |
Final | 4/12/2017 | Not Ready for Inspection | TONY HARTONO |
Footing/Foundation/Slab | 4/12/2017 | Approved | TONY HARTONO |
SGSOV-Seismic Gas S/O Valve | 4/12/2017 | SGSOV Approved | TONY HARTONO |
Smoke Detectors | 4/12/2017 | Approved | TONY HARTONO |
Structural Steel Frame | 4/12/2017 | Approved | TONY HARTONO |
Wood Frame | 4/12/2017 | Approved | TONY HARTONO |
Final | 5/9/2017 | OK to Issue CofO | TONY HARTONO |