2353 S SELBY AVE 90064
Certificate Information: 2353 S SELBY AVE 90064
- Application / Permit
- 15014-10000-05438
- Plan Check / Job No.
- B15LA16591
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST & 2ND STORY ADDITION WITH ATTACHED 2-CAR GARAGE AND REMODEL TO EXISTING 1-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 3/3/2016
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/25/2017
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 11/24/2015 | APPLICANT |
Green Plans Picked Up | 12/9/2015 | APPLICANT |
Assigned to Plan Check Engineer | 12/17/2015 | PRANITA SHAH |
Corrections Issued | 1/7/2016 | PRANITA SHAH |
Quality Review Completed | 1/7/2016 | LAWRENCE QUIRANTE |
Building Plans Picked Up | 1/7/2016 | APPLICANT |
Applicant returned to address corrections | 2/26/2016 | PRANITA SHAH |
Plan Check Approved | 3/1/2016 | PRANITA SHAH |
Issued | 3/3/2016 | LADBS |
CofO in Progress | 3/11/2017 | MICHAEL PELHAM |
Permit Finaled | 4/25/2017 | JACK CONGER |
CofO Issued | 4/25/2017 | JACK CONGER |
Permit Finaled | 4/25/2017 | JACK CONGER |
Permit Application Clearance Information
Eng Process Fee Ord 176,300 | Cleared | 2/3/2016 | JAMES KHO |
Sewer availability | Cleared | 2/3/2016 | JAMES KHO |
Low Impact Development | Cleared | 2/9/2016 | AMMAR ELTAWIL |
Roof/Waste drainage to street | Cleared | 2/9/2016 | ARNULFO NUNO |
Hydrant and Access approval | Cleared | 2/10/2016 | ROBERT DUFF |
Green Code | Cleared | 2/19/2016 | MARCUS LEVIAS |
ZI | Cleared | 2/29/2016 | GRACIELA ACOSTA |
Contact Information
Architect | Hamilton, John Patrick; Lic. No.: C28865 | 12240 VENICE BLVD SUITE 25 LOS ANGELES, CA 90066 |
Contractor | Waconah Construction; Lic. No.: 908219-B | 25 EASTWIND STREET #3 MARINA DEL REY, CA 90292 |
Engineer | Le, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
WILBER ROSALES, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Excavation/Setback/Form/Re-Bar | 4/6/2016 | Corrections Issued | ROBERT VORHIS |
PLUMBING-Rough | 4/8/2016 | Corrections Issued | RICHARD STEINBACH |
Excavation/Setback/Form/Re-Bar | 4/14/2016 | Not Ready for Inspection | ROBERT VORHIS |
METHANE-Subgrade | 4/27/2016 | Approved | JOHN LUMB |
Footing/Foundation/Slab | 5/3/2016 | Approved | ROBERT VORHIS |
METHANE-Barrier | 5/3/2016 | Approved | ROBERT VORHIS |
PLUMBING-Rough | 5/17/2016 | Corrections Issued | VINCENT SCIPIONI |
PLUMBING-Rough | 5/23/2016 | Approved | MARVIN GODFREY |
Floor/Roof Diaphrgm/Shear Wall | 5/27/2016 | Partial Approval | JOHN LUMB |
Floor/Roof Diaphrgm/Shear Wall | 6/14/2016 | Approved | ROBERT VORHIS |
Floor/Roof Diaphrgm/Shear Wall | 6/16/2016 | Approved | ROBERT VORHIS |
HVAC-Rough | 7/22/2016 | Approved | GRANT WOODS |
PLUMBING-Rough | 7/22/2016 | Approved | GRANT WOODS |
ELECTRICAL-Rough | 7/25/2016 | Approved | GRANT WOODS |
Floor/Roof Diaphrgm/Shear Wall | 7/25/2016 | Approved | GRANT WOODS |
Wood Frame | 7/29/2016 | Approved | GRANT WOODS |
Shower Pan | 8/12/2016 | Approved | EDWIN GREGORYONA |
METHANE-Final | 8/18/2016 | Partial Approval | EDWIN GREGORYONA |
Interior/Exterior Lathing | 8/22/2016 | Approved | EDWIN GREGORYONA |
Shower Pan | 8/22/2016 | Approved | EDWIN GREGORYONA |
Insulation | 8/29/2016 | Approved | EDWIN GREGORYONA |
Interior/Exterior Lathing | 9/2/2016 | Approved | MICHAEL PELHAM |
Drywall Nailing | 9/26/2016 | Approved | MICHAEL PELHAM |
Green Building Rough | 9/26/2016 | Approved | MICHAEL PELHAM |
Gas Test | 12/21/2016 | Approved | MICHAEL PELHAM |
Service/Power Release | 1/5/2017 | Approved | MICHAEL PELHAM |
BUILDING-Rough-Frame | 3/1/2017 | Approved | MICHAEL PELHAM |
Final | 3/1/2017 | Not Ready for Inspection | MICHAEL PELHAM |
Green Building Final | 3/1/2017 | Approved | MICHAEL PELHAM |
METHANE-Final | 3/1/2017 | Approved | MICHAEL PELHAM |
METHANE-Rough | 3/1/2017 | Approved | MICHAEL PELHAM |
SGSOV-Seismic Gas S/O Valve | 3/1/2017 | SGSOV Approved | MICHAEL PELHAM |
Smoke Detectors | 3/1/2017 | Approved | MICHAEL PELHAM |
Final | 3/11/2017 | OK to Issue CofO | MICHAEL PELHAM |