731 S BROADWAY 90014

Certificate Information: 731 S BROADWAY 90014

Application / Permit
15016-10000-19156
Plan Check / Job No.
B15LA12553
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
(E) 4 STORY COMMERCIAL BLDG IMPROVEMENT W/ (2) NEW STAIRS, (1) NEW ELEVATOR, CORRIDORS AND PARTITION WALLS, (N) RESTROOMS, REPAIR (E) BLDG FACADE, (N) ALUMINUM WINDOWS, (N) DECK @ 2ND FLOOR LEVEL (N) ROOFING AND SELECTIVE DEMOLITION
Permit Issued
Issued on 8/3/2016
Issuing Office
Metro
Current Status
Permit Finaled on 1/16/2019

Permit Application Status History

Submitted 9/4/2015 APPLICANT
Disabled Access Plans Picked Up 9/22/2015 APPLICANT
Green Plans Picked Up 9/22/2015 APPLICANT
Assigned to Plan Check Engineer 10/1/2015 LARRY LEE
Corrections Issued 10/5/2015 LARRY LEE
Quality Review Completed 10/15/2015 BILL STUTSMAN
Building Plans Picked Up 10/20/2015 APPLICANT
Applicant returned to address corrections 11/3/2015 LARRY LEE
Applicant returned to address corrections 3/1/2016 LARRY LEE
Plan Check Approved 6/13/2016 LARRY LEE
Issued 8/3/2016 LADBS
Permit Finaled 1/15/2019 DANIEL COLLINS

Permit Application Clearance Information

"D" conditions Cleared 10/22/2015 ERIC CLAROS
"Q" conditions Cleared 10/22/2015 ERIC CLAROS
Green Code Cleared 2/26/2016 RUSSELL KELLY
DAS Clearance Cleared 2/29/2016 SHINE LIN
HPOZ Cleared 4/27/2016 LAMBERT GIESSINGER
Hist. Property Cntrct Mgr Appr Cleared 4/27/2016 LAMBERT GIESSINGER
Historic monument Cleared 4/27/2016 LAMBERT GIESSINGER
Historical monument Cleared 5/4/2016 JIM URQUHART
Project located in CRA area Cleared 5/4/2016 JIM URQUHART
Miscellaneous Cleared 6/13/2016 ULISES GONZALEZ
ZI Cleared 6/13/2016 ULISES GONZALEZ

Contact Information

Architect Bahng, Chae Joung; Lic. No.: C10055 11449 TAMPA AVE #142      NORTHRIDGE, CA 91326
Contractor Cal-City Construction Inc; Lic. No.: 539265-B 16605 NORWALK BLVD      CERRITOS, CA 90703
Engineer Park, Juntae; Lic. No.: C65104 1444 HI POINT ST      LOS ANGELES, CA 90035

Inspector Information

KATY RAMIREZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BAZERKANIAN, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/1/2016 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 11/4/2016 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 11/17/2016 No Access for Inspection JOSE GAXIOLA
Deputy Drilled-In Anchors 12/20/2016 No Access for Inspection JOSE GAXIOLA
Deputy Drilled-In Anchors 1/27/2017 Approved JOSE GAXIOLA
Deputy Drilled-In Anchors 1/30/2017 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 1/30/2017 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 2/7/2017 No Access for Inspection JOSE GAXIOLA
Deputy Steel/Welding 2/9/2017 No Access for Inspection JOSE GAXIOLA
Deputy Drilled-In Anchors 2/10/2017 Approved JOSE GAXIOLA
Deputy Drilled-In Anchors 3/9/2017 Conditional Approval JOSE GAXIOLA
Deputy Drilled-In Anchors 3/14/2017 Conditional Approval JOSE GAXIOLA
Excavation/Setback/Form/Re-Bar 3/17/2017 Partial Approval JOSE GAXIOLA
Deputy Drilled-In Anchors 4/3/2017 Conditional Approval JOSE GAXIOLA
Excavation/Setback/Form/Re-Bar 4/26/2017 Partial Approval JOSE GAXIOLA
Reinforced Concrete Frame 4/26/2017 Partial Approval JOSE GAXIOLA
Deputy Drilled-In Anchors 5/11/2017 Conditional Approval JOSE GAXIOLA
Reinforced Concrete Frame 5/15/2017 Partial Approval JOSE GAXIOLA
Deputy Reinf. Concrete 5/16/2017 Conditional Approval JOSE GAXIOLA
Deputy Steel/Welding 5/22/2017 Conditional Approval JOSE GAXIOLA
Deputy Steel/Welding 5/26/2017 Conditional Approval JOSE GAXIOLA
Deputy Drilled-In Anchors 6/2/2017 Conditional Approval JOSE GAXIOLA
Deputy Drilled-In Anchors 6/9/2017 Conditional Approval JOSE GAXIOLA
Deputy Drilled-In Anchors 6/16/2017 Conditional Approval JOSE GAXIOLA
Deputy Drilled-In Anchors 6/23/2017 No Access for Inspection AJA COLLAY
Deputy Drilled-In Anchors 6/30/2017 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 7/7/2017 Conditional Approval AJA COLLAY
Deputy Drilled-In Anchors 7/11/2017 Conditional Approval JOSE GAXIOLA
Deputy Drilled-In Anchors 8/1/2017 Conditional Approval JOSE GAXIOLA
Reinforced Concrete Frame 8/14/2017 Corrections Issued JOSE GAXIOLA
Reinforced Concrete Frame 8/31/2017 Partial Approval JOSE GAXIOLA
Deputy Drilled-In Anchors 9/5/2017 Conditional Approval JOSE GAXIOLA
Deputy Drilled-In Anchors 9/29/2017 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 10/2/2017 Partial Approval JOSE GAXIOLA
Deputy Steel/Welding 10/23/2017 Conditional Approval JOSE GAXIOLA
Reinforced Concrete Frame 11/14/2017 Partial Approval JOSE GAXIOLA
Structural Steel Frame 11/14/2017 Conditional Approval JOSE GAXIOLA
Light Gage Steel Frame 12/12/2017 Partial Approval JOSE GAXIOLA
Drywall Nailing 12/26/2017 Partial Approval WINSTON DUNNING
Drywall Nailing 1/8/2018 Partial Approval JOSE GAXIOLA
Drywall Nailing 1/17/2018 Partial Approval JOSE GAXIOLA
Green Building Final 9/6/2018 Not Ready for Inspection JOSE GAXIOLA
Pre-Inspection 9/6/2018 Partial Approval JOSE GAXIOLA
SGSOV-Seismic Gas S/O Valve 9/6/2018 SGSOV No Gas JOSE GAXIOLA
Smoke Detectors 9/6/2018 Approved JOSE GAXIOLA
Final 11/15/2018 Not Ready for Inspection JAMES POWERS
Green Building Final 11/15/2018 Approved JAMES POWERS
Final 1/15/2019 Permit Finaled DANIEL COLLINS