6220 N TOPANGA CANYON BLVD STE 9010 91367

Certificate Information: 6220 N TOPANGA CANYON BLVD STE 9010 91367

Application / Permit
15020-20000-00667
Plan Check / Job No.
B15VN03139
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
NEW (9010) KIOSK BUILDING (300SF)
Permit Issued
Issued on 5/5/2015
Issuing Office
Valley
Current Status
CofO Issued on 1/22/2018
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2015 APPLICANT
Disabled Access Plans Picked Up 3/24/2015 APPLICANT
Assigned to Plan Check Engineer 3/26/2015 DAWN MC NULTY
Corrections Issued 4/1/2015 DAWN MC NULTY
Quality Review Completed 4/7/2015 BINH PHAN
Building Plans Picked Up 4/10/2015 APPLICANT
Applicant returned to address corrections 4/15/2015 DAWN MC NULTY
Plan Check Approved 4/30/2015 DAWN MC NULTY
Issued 5/5/2015 LADBS
TCO Issued (Expire Date: 03-13-2016) 9/15/2015 HENRY BAGHDASSARIAN
CofO in Progress 1/17/2018 ROBERT COLE
Permit Finaled 1/22/2018 ANDREW CROMER
CofO Issued 1/22/2018 ANDREW CROMER
Permit Finaled 1/22/2018 ANDREW CROMER

Permit Application Clearance Information

DAS Clearance Cleared 4/15/2015 NORLITO MEDRANO
Green Code Cleared 4/15/2015 MICHAEL AYERS
CPC Cleared 4/27/2015 ANNA VIDAL
CPC Cleared 4/27/2015 ANNA VIDAL
Fire Marshall Fire Life Safety Cleared 4/27/2015 DAVE MYERS
Hydrant and Access approval Cleared 4/27/2015 JOHN DALLAS
Specific Plan Cleared 4/27/2015 ANNA VIDAL
Tract Map conditions Cleared 4/27/2015 ANNA VIDAL
Tract Map conditions Cleared 4/27/2015 ANNA VIDAL
Tract Map conditions Cleared 4/27/2015 ANNA VIDAL
Address approval Cleared 4/30/2015 SANDRA FIGUEROA
Eng Process Fee Ord 176,300 Cleared 4/30/2015 SANDRA FIGUEROA
Roof/Waste drainage to street Cleared 4/30/2015 SANDRA FIGUEROA
Sewer availability Cleared 4/30/2015 SANDRA FIGUEROA

Contact Information

Architect Budetti, Robert Peter Jr; Lic. No.: C23757 11 ASHWOOD      IRVINE, CA 92604
Contractor Westfield Development Inc; Lic. No.: 892271-B 11601 WILSHIRE BLVD 11TH FLOOR   ATTN ERIC WILSON    LOS ANGELES, CA 90025
Engineer Sarkis, Peter; Lic. No.: S5038 26111 CONNEMARA CT      LAKE FOREST, CA 92630
Engineer Soltis, Paul Christopher; Lic. No.: GE2606 5732 LEMON AVE      CYPRESS, CA 90630

Inspector Information

ROBERT DAVIS, (818) 374-1128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/10/2015 Approved ROBERT COLE
Excavation/Setback/Form/Re-Bar 6/12/2015 Partial Approval ROBERT COLE
Structural Steel Frame 6/23/2015 Approved ROBERT COLE
Light Gage Steel Frame 6/24/2015 Approved ROBERT COLE
Structural Steel Frame 6/24/2015 Approved ROBERT COLE
Drywall Nailing 6/26/2015 Partial Approval CAMERON CHABAN
Drywall Nailing 7/7/2015 Not Ready for Inspection ROBERT COLE
Interior/Exterior Lathing 7/7/2015 Approved ROBERT COLE
Light Gage Steel Frame 7/7/2015 Partial Approval ROBERT COLE
Green Building Final 9/9/2015 Partial Approval BRYAN MEYER
Green Building Rough 9/9/2015 Approved BRYAN MEYER
Final 12/2/2015 Corrections Issued ROBERT COLE
Reinforced Masonry Frame 12/2/2015 Partial Approval ROBERT COLE
SGSOV-Seismic Gas S/O Valve 12/2/2015 SGSOV No Gas ROBERT COLE
Smoke Detectors 12/2/2015 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 12/2/2015 Not Ready for Inspection ROBERT COLE
Special/Order Compliance 2/19/2016 Partial Inspection ROBERT COLE
Final 2/24/2016 Not Ready for Inspection ROBERT COLE
Green Building Final 2/24/2016 No Access for Inspection RICHARD DOCKUS
Reinforced Masonry Frame 2/24/2016 Partial Approval ROBERT COLE
Smoke Detectors 2/24/2016 Approved ROBERT COLE
Verify Sprinkler Sign Off 2/24/2016 Not Ready for Inspection ROBERT COLE
Final 3/30/2016 Not Ready for Inspection ROBERT COLE
Green Building Final 3/30/2016 Approved RICHARD DOCKUS
Reinforced Masonry Frame 3/30/2016 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 3/30/2016 Not Ready for Inspection ROBERT COLE
Final 4/19/2016 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 4/19/2016 Partial Inspection ROBERT COLE
Final 5/17/2016 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 5/17/2016 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 5/17/2016 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 5/24/2016 Not Ready for Inspection ROBERT COLE
Final 1/13/2017 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 1/13/2017 Approved ROBERT COLE
Special/Order Compliance 1/13/2017 Conditional Approval ROBERT COLE
Special/Order Compliance 1/13/2017 Partial Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 1/13/2017 Approved ROBERT COLE