Footing/Foundation/Slab
|
2/8/2018
|
Partial Approval
|
SCOTT FINNILA
|
Deputy Steel/Welding
|
3/7/2018
|
Partial Approval
|
SCOTT FINNILA
|
Deputy Steel/Welding
|
3/8/2018
|
Partial Approval
|
SCOTT FINNILA
|
Deputy Steel/Welding
|
3/9/2018
|
Partial Approval
|
SCOTT FINNILA
|
ELECTRICAL-Rough
|
3/29/2018
|
Partial Approval
|
SCOTT FINNILA
|
Footing/Foundation/Slab
|
3/29/2018
|
Corrections Issued
|
SCOTT FINNILA
|
Underground Mechanical
|
3/29/2018
|
Partial Approval
|
SCOTT FINNILA
|
Footing/Foundation/Slab
|
4/2/2018
|
Partial Approval
|
SCOTT FINNILA
|
Footing/Foundation/Slab
|
4/11/2018
|
Partial Approval
|
SCOTT FINNILA
|
Excavation/Setback/Form/Re-Bar
|
4/12/2018
|
Approved
|
SCOTT FINNILA
|
Deputy Wood Construction
|
4/30/2018
|
Approved
|
DOMINIC DANERI
|
Floor/Roof Diaphrgm/Shear Wall
|
5/1/2018
|
Partial Approval
|
SCOTT FINNILA
|
Deputy Wood Construction
|
5/2/2018
|
Conditional Approval
|
DOMINIC DANERI
|
Drywall Nailing
|
5/3/2018
|
Partial Approval
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
5/15/2018
|
Partial Approval
|
SCOTT FINNILA
|
Drywall Nailing
|
5/17/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
Green Building Rough
|
5/17/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
HVAC-Rough
|
5/17/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
Verify Sprinkler Sign Off
|
5/17/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
5/18/2018
|
Partial Approval
|
SCOTT FINNILA
|
Deputy Wood Construction
|
5/21/2018
|
Partial Approval
|
SCOTT FINNILA
|
Deputy Wood Construction
|
6/4/2018
|
Partial Approval
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
6/4/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
6/5/2018
|
Partial Approval
|
SCOTT FINNILA
|
Deputy Wood Construction
|
6/6/2018
|
Partial Approval
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
6/7/2018
|
Partial Approval
|
SCOTT FINNILA
|
Interior/Exterior Lathing
|
6/11/2018
|
Partial Approval
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
6/15/2018
|
Partial Approval
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
6/18/2018
|
Corrections Issued
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
6/22/2018
|
Partial Approval
|
SCOTT FINNILA
|
Drywall Nailing
|
6/25/2018
|
Partial Approval
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
6/26/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
Interior/Exterior Lathing
|
6/26/2018
|
Partial Approval
|
SCOTT FINNILA
|
Deputy Wood Construction
|
7/3/2018
|
Partial Approval
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
7/3/2018
|
Partial Approval
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
7/24/2018
|
No Access for Inspection
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
8/2/2018
|
Partial Approval
|
SCOTT FINNILA
|
Deputy Wood Construction
|
8/3/2018
|
Partial Approval
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
8/8/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
Deputy Wood Construction
|
8/9/2018
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
8/9/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
Drywall Nailing
|
8/10/2018
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
8/14/2018
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
9/5/2018
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Deputy Wood Construction
|
9/12/2018
|
Partial Approval
|
SCOTT FINNILA
|
Floor/Roof Diaphrgm/Shear Wall
|
10/1/2018
|
Approved
|
ALEJANDRO DE ARTOLA
|
HVAC-Rough
|
10/1/2018
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
10/15/2018
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
10/22/2018
|
Partial Inspection
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
10/23/2018
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Drywall Nailing
|
10/29/2018
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
Green Building Rough
|
10/29/2018
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
HVAC-Rough
|
10/29/2018
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
ELECTRICAL-Rough
|
12/4/2018
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
HVAC-Rough
|
12/4/2018
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
PLUMBING-Rough
|
12/4/2018
|
Approved
|
ALEJANDRO DE ARTOLA
|
ELECTRICAL-Rough
|
12/5/2018
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
HVAC-Rough
|
12/5/2018
|
Approved
|
ALEJANDRO DE ARTOLA
|
ELECTRICAL-Rough
|
12/7/2018
|
Approved
|
ALEJANDRO DE ARTOLA
|
BUILDING-Rough-Frame
|
12/12/2018
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Green Building Rough
|
12/12/2018
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
Verify Sprinkler Sign Off
|
12/12/2018
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
BUILDING-Rough-Frame
|
1/3/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
Green Building Rough
|
1/3/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
Verify Sprinkler Sign Off
|
1/3/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
Interior/Exterior Lathing
|
1/8/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Insulation
|
1/23/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
Drywall Nailing
|
1/30/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
Shower Pan
|
3/12/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
Shower Pan
|
3/13/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
Interior/Exterior Lathing
|
3/19/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
Gas Test
|
3/20/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
Shower Pan
|
4/17/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
PLUMBING-Rough
|
2/19/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Underground Mechanical
|
2/25/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Underground Mechanical
|
3/3/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
ELECTRICAL-Final
|
6/9/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
HVAC-Final
|
6/11/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
PLUMBING-Final
|
6/19/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Gas Test
|
6/26/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
PLUMBING-Final
|
6/26/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
HVAC-Final
|
7/10/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
PLUMBING-Final
|
7/10/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
HVAC-Final
|
7/14/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
PLUMBING-Final
|
7/14/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
Final
|
7/15/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
ELECTRICAL-Final
|
7/22/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
ELECTRICAL-Final
|
8/5/2020
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
Final
|
7/14/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Footing/Foundation/Slab
|
7/14/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
Green Building Final
|
7/14/2021
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
SGSOV-Seismic Gas S/O Valve
|
7/14/2021
|
SGSOV Approved
|
ALEJANDRO DE ARTOLA
|
Service/Power Release
|
7/14/2021
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
Smoke Detectors
|
7/14/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
Structural Steel Frame
|
7/14/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
Final
|
12/28/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Green Building Final
|
12/28/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Service/Power Release
|
12/28/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
ELECTRICAL-Final
|
12/30/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
Final
|
1/6/2022
|
OK to Issue CofO
|
ALEJANDRO DE ARTOLA
|
Green Building Final
|
1/6/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|