351-353 W 80TH ST 90003
Certificate Information: 351-353 W 80TH ST 90003
- Application / Permit
- 16010-10000-03399
- Plan Check / Job No.
- B16LA11741
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE IN FRONT AND ATTACHED 2-CAR GARAGE IN REAR. SEE COMMENTS.
- Permit Issued
- Issued on 10/31/2016
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/24/2017
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 8/3/2016 | APPLICANT |
Assigned to Plan Check Engineer | 8/25/2016 | CAROLYNN NEPOMUCENO |
Green Plans Picked Up | 8/29/2016 | APPLICANT |
Corrections Issued | 9/9/2016 | CAROLYNN NEPOMUCENO |
Quality Review Completed | 9/14/2016 | ALLEN MANALANSAN |
Building Plans Picked Up | 9/14/2016 | APPLICANT |
Applicant returned to address corrections | 9/29/2016 | CAROLYNN NEPOMUCENO |
Plan Check Approved | 10/4/2016 | CAROLYNN NAPOMUCENO |
Issued | 10/31/2016 | LADBS |
CofO in Progress | 6/15/2017 | JAVIER ALIPIO |
CofO Issued | 6/24/2017 | MARK CASEY |
Permit Finaled | 6/24/2017 | MARK CASEY |
Permit Application Clearance Information
Address approval | Cleared | 9/26/2016 | ARNULFO NUNO |
Eng Process Fee Ord 176,300 | Cleared | 9/26/2016 | ARNULFO NUNO |
Hydrant and Access approval | Cleared | 9/26/2016 | JOHN CONNEALLY |
Permit | Cleared | 9/26/2016 | ARNULFO NUNO |
Sewer availability | Cleared | 9/26/2016 | ARNULFO NUNO |
Green Code | Cleared | 9/28/2016 | MICKEY YAMASHITA |
Highway dedication | Cleared | 9/28/2016 | ROCHELLE DUNGCA |
Low Impact Development | Cleared | 9/28/2016 | RYAN HUDSON |
Roof/Waste drainage to street | Cleared | 9/28/2016 | ROCHELLE DUNGCA |
Demolition Pre-Inspection | Cleared | 9/29/2016 | CAROLYNN NAPOMUCENO |
Contact Information
Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
Engineer | Fidencio, Madero Jr; Lic. No.: C81695 | PO BOX 2222 DOWNEY, CA 90242 |
Inspector Information
JOHN QUINTANILLA, (213) 482-0325 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 11/22/2016 | Approved | ENRIQUE MIRELES |
PLUMBING-Rough | 12/8/2016 | Partial Approval | ENRIQUE MIRELES |
Wood Frame | 12/8/2016 | Partial Approval | ENRIQUE MIRELES |
Floor/Roof Diaphrgm/Shear Wall | 12/9/2016 | Partial Approval | ENRIQUE MIRELES |
Insulation | 12/9/2016 | Partial Approval | ENRIQUE MIRELES |
Sewer | 12/9/2016 | Not Ready for Inspection | ENRIQUE MIRELES |
Sewer | 12/14/2016 | Approved | ENRIQUE MIRELES |
Floor/Roof Diaphrgm/Shear Wall | 12/29/2016 | Approved | JAVIER ALIPIO |
Deputy Wood Construction | 1/17/2017 | No Access for Inspection | FRANCISCO MORADO |
Floor/Roof Diaphrgm/Shear Wall | 1/18/2017 | Partial Approval | ENRIQUE MIRELES |
Wood Frame | 1/18/2017 | Partial Approval | ENRIQUE MIRELES |
BUILDING-Rough-Frame | 2/1/2017 | Approved | FRANCISCO MORADO |
Green Building Rough | 2/1/2017 | Approved | FRANCISCO MORADO |
Rough-Elec/Plmb/HVAC | 2/1/2017 | Approved | FRANCISCO MORADO |
Verify Sprinkler Sign Off | 2/1/2017 | Approved | FRANCISCO MORADO |
Drywall Nailing | 2/6/2017 | Not Ready for Inspection | FRANCISCO MORADO |
Interior/Exterior Lathing | 2/6/2017 | Not Ready for Inspection | FRANCISCO MORADO |
Drywall Nailing | 2/16/2017 | No Access for Inspection | ENRIQUE MIRELES |
Interior/Exterior Lathing | 2/16/2017 | No Access for Inspection | ENRIQUE MIRELES |
Drywall Nailing | 2/17/2017 | Approved | FRANCISCO MORADO |
Interior/Exterior Lathing | 2/17/2017 | Approved | FRANCISCO MORADO |
ELECTRICAL-Final | 5/11/2017 | No Access for Inspection | ANDEY CHAPARRO |
Final | 5/11/2017 | No Access for Inspection | ANDEY CHAPARRO |
Green Building Final | 5/11/2017 | No Access for Inspection | ANDEY CHAPARRO |
HVAC-Final | 5/11/2017 | No Access for Inspection | ANDEY CHAPARRO |
PLUMBING-Final | 5/11/2017 | No Access for Inspection | ANDEY CHAPARRO |
SGSOV-Seismic Gas S/O Valve | 5/11/2017 | SGSOV Not Ready | ANDEY CHAPARRO |
Service/Power Release | 5/11/2017 | No Access for Inspection | ANDEY CHAPARRO |
Smoke Detectors | 5/11/2017 | No Access for Inspection | ANDEY CHAPARRO |
ELECTRICAL-Final | 5/15/2017 | Corrections Issued | ANDEY CHAPARRO |
Final | 5/15/2017 | Corrections Issued | ANDEY CHAPARRO |
Green Building Final | 5/15/2017 | Not Ready for Inspection | ANDEY CHAPARRO |
HVAC-Final | 5/15/2017 | Corrections Issued | ANDEY CHAPARRO |
PLUMBING-Final | 5/15/2017 | Corrections Issued | ANDEY CHAPARRO |
SGSOV-Seismic Gas S/O Valve | 5/15/2017 | SGSOV Approved | ANDEY CHAPARRO |
Service/Power Release | 5/15/2017 | Conditional Approval | ANDEY CHAPARRO |
Smoke Detectors | 5/15/2017 | Approved | ANDEY CHAPARRO |
PLUMBING-Final | 5/19/2017 | Partial Approval | JAVIER ALIPIO |
Final | 5/23/2017 | Corrections Issued | ANDEY CHAPARRO |
Green Building Final | 5/23/2017 | No Access for Inspection | ANDEY CHAPARRO |
HVAC-Final | 5/23/2017 | No Access for Inspection | ANDEY CHAPARRO |
Service/Power Release | 5/23/2017 | No Access for Inspection | ANDEY CHAPARRO |
Final | 5/25/2017 | Not Ready for Inspection | ANDEY CHAPARRO |
Green Building Final | 5/25/2017 | Conditional Approval | ANDEY CHAPARRO |
HVAC-Final | 5/25/2017 | Not Ready for Inspection | ANDEY CHAPARRO |
Service/Power Release | 5/25/2017 | Conditional Approval | ANDEY CHAPARRO |
ELECTRICAL-Final | 5/26/2017 | Approved | ANDEY CHAPARRO |
ELECTRICAL-Final | 6/7/2017 | Approved | JAVIER ALIPIO |
Service/Power Release | 6/7/2017 | Approved | JAVIER ALIPIO |
Final | 6/9/2017 | OK to Issue CofO | JAVIER ALIPIO |
Green Building Final | 6/9/2017 | Approved | JAVIER ALIPIO |
HVAC-Final | 6/9/2017 | Approved | JAVIER ALIPIO |
PLUMBING-Final | 6/9/2017 | Approved | JAVIER ALIPIO |