Footing/Foundation/Slab
|
6/8/2020
|
Corrections Issued
|
DERRICK SPENCER
|
METHANE-Barrier
|
6/8/2020
|
Not Ready for Inspection
|
DERRICK SPENCER
|
METHANE-Subgrade
|
6/8/2020
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Piling/Pier/Caisson
|
6/24/2020
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Excavation/Setback/Form/Re-Bar
|
10/2/2020
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Excavation/Setback/Form/Re-Bar
|
10/20/2020
|
Approved
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
11/6/2020
|
Partial Approval
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
11/17/2020
|
Partial Approval
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
11/25/2020
|
Approved
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
12/8/2020
|
Partial Approval
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
12/28/2020
|
Partial Approval
|
DERRICK SPENCER
|
Excavation/Setback/Form/Re-Bar
|
1/5/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Excavation/Setback/Form/Re-Bar
|
1/6/2021
|
Partial Approval
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
1/15/2021
|
Partial Approval
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
1/20/2021
|
Partial Approval
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
1/22/2021
|
Partial Approval
|
DERRICK SPENCER
|
Green Building Rough
|
2/4/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
METHANE-Rough
|
2/4/2021
|
Partial Approval
|
DERRICK SPENCER
|
Reinforced Masonry Frame
|
2/4/2021
|
Partial Approval
|
DERRICK SPENCER
|
Verify Sprinkler Sign Off
|
2/4/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
2/19/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
2/23/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
3/2/2021
|
Partial Approval
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
3/2/2021
|
Partial Approval
|
DERRICK SPENCER
|
Green Building Rough
|
3/8/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
METHANE-Rough
|
3/8/2021
|
Approved
|
DERRICK SPENCER
|
Reinforced Masonry Frame
|
3/8/2021
|
Partial Approval
|
DERRICK SPENCER
|
Verify Sprinkler Sign Off
|
3/8/2021
|
Approved
|
DERRICK SPENCER
|
Structural Steel Frame
|
3/9/2021
|
Partial Approval
|
DERRICK SPENCER
|
Structural Steel Frame
|
3/24/2021
|
Partial Approval
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
3/26/2021
|
Partial Approval
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
4/9/2021
|
Partial Approval
|
PAUL DAVIDSON
|
Masonry Wall/Backfill
|
4/15/2021
|
Partial Approval
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
4/23/2021
|
Partial Approval
|
DERRICK SPENCER
|
Structural Steel Frame
|
4/28/2021
|
Partial Approval
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
5/4/2021
|
Partial Approval
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
5/7/2021
|
Corrections Issued
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
5/11/2021
|
Partial Approval
|
TED RIES
|
Masonry Wall/Backfill
|
5/12/2021
|
Conditional Approval
|
TED RIES
|
Reinforced Concrete Frame
|
5/12/2021
|
Conditional Approval
|
TED RIES
|
Green Building Rough
|
5/18/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Reinforced Masonry Frame
|
5/18/2021
|
Partial Inspection
|
DERRICK SPENCER
|
Green Building Rough
|
5/25/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
5/25/2021
|
Partial Approval
|
DERRICK SPENCER
|
Reinforced Masonry Frame
|
5/25/2021
|
Partial Approval
|
DERRICK SPENCER
|
Green Building Rough
|
6/1/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Reinforced Masonry Frame
|
6/1/2021
|
Partial Approval
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
6/2/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
6/3/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
6/3/2021
|
Partial Approval
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
6/7/2021
|
Partial Approval
|
DERRICK SPENCER
|
Reinforced Concrete Frame
|
6/7/2021
|
Partial Approval
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
6/10/2021
|
Partial Approval
|
DERRICK SPENCER
|
Deputy Fireproofing
|
6/30/2021
|
Approved
|
DERRICK SPENCER
|
Deputy Fireproofing
|
7/1/2021
|
Approved
|
DERRICK SPENCER
|
Deputy Fireproofing
|
7/2/2021
|
Approved
|
DERRICK SPENCER
|
Deputy Fireproofing
|
7/6/2021
|
Approved
|
DERRICK SPENCER
|
Deputy Fireproofing
|
7/7/2021
|
Approved
|
DERRICK SPENCER
|
Deputy Fireproofing
|
7/9/2021
|
Approved
|
DERRICK SPENCER
|
Deputy Fireproofing
|
7/12/2021
|
Approved
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
7/12/2021
|
Partial Approval
|
DERRICK SPENCER
|
Deputy Fireproofing
|
7/13/2021
|
Approved
|
DERRICK SPENCER
|
Structural Steel Frame
|
7/19/2021
|
Partial Approval
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
7/27/2021
|
Corrections Issued
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
7/30/2021
|
Partial Approval
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
8/3/2021
|
Partial Approval
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
8/10/2021
|
Partial Approval
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
8/13/2021
|
Partial Approval
|
TED RIES
|
Light Gage Steel Frame
|
8/25/2021
|
Partial Approval
|
JOHN DODGE
|
Light Gage Steel Frame
|
8/30/2021
|
Corrections Issued
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
8/31/2021
|
Partial Approval
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
9/3/2021
|
Partial Approval
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
9/3/2021
|
Approved
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
9/13/2021
|
Corrections Issued
|
DERRICK SPENCER
|
Drywall Nailing
|
9/24/2021
|
Partial Approval
|
DERRICK SPENCER
|
Interior/Exterior Lathing
|
9/24/2021
|
Approved
|
DERRICK SPENCER
|
Drywall Nailing
|
9/28/2021
|
Approved
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
9/28/2021
|
Approved
|
DERRICK SPENCER
|
Wall Anchors
|
9/28/2021
|
Partial Approval
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
10/4/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
10/15/2021
|
Partial Approval
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
10/22/2021
|
Partial Approval
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
10/25/2021
|
Partial Approval
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
11/5/2021
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Green Building Rough
|
11/16/2021
|
Approved
|
DERRICK SPENCER
|
Reinforced Masonry Frame
|
11/16/2021
|
Approved
|
DERRICK SPENCER
|
Insulation
|
11/19/2021
|
Approved
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
11/19/2021
|
Approved
|
DERRICK SPENCER
|
Masonry Wall/Backfill
|
11/24/2021
|
Partial Approval
|
DERRICK SPENCER
|
Light Gage Steel Frame
|
12/14/2021
|
Partial Approval
|
DERRICK SPENCER
|
T-Bar Ceiling
|
1/11/2022
|
No Access for Inspection
|
DERRICK SPENCER
|
T-Bar Ceiling
|
1/19/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Special/Order Compliance
|
1/21/2022
|
Approved
|
DERRICK SPENCER
|
T-Bar Ceiling
|
1/27/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
T-Bar Ceiling
|
2/4/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
T-Bar Ceiling
|
2/11/2022
|
Corrections Issued
|
DERRICK SPENCER
|
T-Bar Ceiling
|
2/15/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
T-Bar Ceiling
|
2/17/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Insulation
|
2/23/2022
|
Approved
|
DERRICK SPENCER
|
T-Bar Ceiling
|
2/23/2022
|
Partial Approval
|
DERRICK SPENCER
|
Interior/Exterior Lathing
|
3/8/2022
|
Approved
|
DERRICK SPENCER
|
Final
|
7/1/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Footing/Foundation/Slab
|
7/1/2022
|
Approved
|
DERRICK SPENCER
|
Green Building Final
|
7/1/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
METHANE-Barrier
|
7/1/2022
|
Approved
|
DERRICK SPENCER
|
METHANE-Subgrade
|
7/1/2022
|
Approved
|
DERRICK SPENCER
|
Pre-Inspection
|
7/1/2022
|
Approved
|
DERRICK SPENCER
|
SGSOV-Seismic Gas S/O Valve
|
7/1/2022
|
SGSOV Approved
|
DERRICK SPENCER
|
Smoke Detectors
|
7/1/2022
|
Approved
|
DERRICK SPENCER
|