330 N PATTON ST 1-32 90026

Certificate Information: 330 N PATTON ST 1-32 90026

Application / Permit
17010-10000-04956
Plan Check / Job No.
B17LA23079
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
7-STORY 32 UNIT APPARTMENTS BUILDING OVER 1 LEVEL SUBTERRANIEAN GARAGE
Permit Issued
Issued on 3/12/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2017 APPLICANT
Assigned to Plan Check Engineer 12/28/2017 LARRY LEE
Green Plans Picked Up 1/3/2018 APPLICANT
Corrections Issued 1/8/2018 LARRY LEE
Quality Review Completed 1/9/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 1/16/2018 APPLICANT
Applicant returned to address corrections 1/31/2018 LARRY LEE
Applicant returned to address corrections 2/13/2018 LARRY LEE
Applicant returned to address corrections 2/28/2018 LARRY LEE
Applicant returned to address corrections 4/10/2018 LARRY LEE
Applicant returned to address corrections 5/8/2018 LARRY LEE
Applicant returned to address corrections 5/29/2018 LARRY LEE
Applicant returned to address corrections 8/23/2019 LARRY LEE
Applicant returned to address corrections 9/4/2019 LARRY LEE
Applicant returned to address corrections 9/16/2019 LARRY LEE
Plan Check Approved 3/10/2020 LARRY LEE
Issued 3/12/2020 LADBS
TCO Issued (Expire Date: 06-28-2023) 12/30/2022 ERNESTO CORRAL
CofO in Progress 1/9/2023 ERNESTO CORRAL
CofO Issued 1/9/2023 ERNESTO CORRAL
Permit Finaled 1/9/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/29/2018 STEVE MELGAR
Permit Cleared 1/29/2018 NAZILA NOORIFAR
Specific Plan Cleared 2/8/2018 TAIMOUR TANAVOLI
Highway dedication Cleared 2/12/2018 STEVE MELGAR
Hydrant and Access approval Cleared 2/21/2018 JOHN CONNEALLY
Low Impact Development Cleared 4/9/2018 SAM NAVID
Eng Process Fee Ord 176,300 Cleared 4/17/2018 MICHAEL CASTILLO
Roof/Waste drainage to street Cleared 4/17/2018 MICHAEL CASTILLO
Density Bonus 12.22.A.25 Cleared 4/26/2018 NICHOLAS KAWAZOE
DAS Clearance Cleared 5/7/2018 SHINE LIN
Green Code Cleared 5/11/2018 DONALD CRICHLOW
Frnt yard landscape/Water mgmt Cleared 5/21/2018 BRIAN CARR
Miscellaneous Cleared 5/21/2018 BRIAN CARR
Miscellaneous Cleared 5/21/2018 BRIAN CARR
Opn space landscape/Water mgmt Cleared 5/21/2018 BRIAN CARR
Specific Plan Cleared 5/21/2018 BRIAN CARR
Building over 3-story or 36-ft Cleared 5/29/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 5/29/2018 CALOSHA APPROVED
Fire Marshall Fire Life Safety Cleared 6/6/2018 MENOA AGHAJANI
Sewer availability Cleared 7/23/2019 ELENA LOPEZ
Work Adjacent to Public Way Cleared 8/30/2019 ROSA SILVA
DAS Clearance Cleared 9/4/2019 LARRY LEE
Green Code Cleared 9/17/2019 DONALD CRICHLOW
Miscellaneous Cleared 3/10/2020 ANACANY HURTADO

Contact Information

Architect Empakeris, Donatas Eduard; Lic. No.: C13779 1535 6TH STREET SUITE 101   DE ARCHITECTS    SANTA MONICA, CA 90401
Contractor Ravanshenas David; Lic. No.: 966018-B 8322 BEVERLY BOULEVARD STE 301      LOS ANGELES, CA 90048
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/16/2020 Approved LESLIE TRUJILLO
Deputy Methane Barrier 6/24/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 6/25/2020 Conditional Approval NICK DANERI
Deputy Methane Barrier 6/26/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 6/29/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/29/2020 Partial Inspection RAFAEL ESPINOZA
METHANE-Barrier 6/29/2020 Partial Inspection RAFAEL ESPINOZA
METHANE-Subgrade 6/29/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Methane Barrier 6/30/2020 Conditional Approval NICK DANERI
Deputy Methane Barrier 7/7/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 7/10/2020 Partial Inspection RAFAEL ESPINOZA
METHANE-Barrier 7/10/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 7/10/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Methane Barrier 7/16/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 7/17/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 7/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 7/22/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/24/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 7/27/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 7/27/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 7/27/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/29/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 7/29/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 7/29/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Subgrade 7/29/2020 Not Ready for Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/30/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/31/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/11/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/12/2020 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 8/12/2020 Approved RAFAEL ESPINOZA
METHANE-Rough 8/12/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 8/12/2020 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 8/13/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 8/14/2020 Conditional Approval NICK DANERI
Deputy Shotcrete 8/17/2020 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/18/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/19/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 8/19/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 8/20/2020 Conditional Approval NICK DANERI
Deputy Shotcrete 8/21/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 8/21/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/24/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 8/24/2020 Conditional Approval NICK DANERI
Deputy Shotcrete 8/25/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 8/31/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/2/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 9/3/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/3/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/4/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/4/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 9/4/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 9/4/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Subgrade 9/4/2020 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 9/4/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/8/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/8/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 9/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 9/22/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/24/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 9/24/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 9/24/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Subgrade 9/24/2020 Partial Approval RAFAEL ESPINOZA
Deputy Methane Barrier 10/5/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 10/6/2020 Conditional Approval RAFAEL ESPINOZA
METHANE-Barrier 10/7/2020 Approved RAFAEL ESPINOZA
METHANE-Final 10/7/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 10/7/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Subgrade 10/7/2020 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 10/9/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/27/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/28/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 10/28/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/29/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 10/29/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/5/2020 Conditional Approval RAFAEL ESPINOZA
METHANE-Rough 11/9/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 11/9/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/9/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/10/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 11/10/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 11/12/2020 Conditional Approval RAFAEL ESPINOZA
METHANE-Rough 11/12/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 11/12/2020 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/12/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Shotcrete 11/13/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 11/13/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/16/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/16/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 11/17/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/19/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/19/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/20/2020 Conditional Approval NICK DANERI
Footing/Foundation/Slab 11/20/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/24/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/24/2020 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 12/1/2020 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 12/2/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/3/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 12/3/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/14/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/17/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/18/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 12/18/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/21/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 12/21/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/22/2020 Conditional Approval NICK DANERI
Deputy Shotcrete 12/24/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/30/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/31/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 12/31/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 12/31/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 12/31/2020 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 1/4/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 1/4/2021 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 1/6/2021 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 1/7/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 1/7/2021 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/7/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Shotcrete 1/8/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/4/2021 Conditional Approval RAFAEL ESPINOZA
Pre-Inspection 2/5/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/8/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/8/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 2/9/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/10/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/10/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 2/16/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/17/2021 Conditional Approval RAFAEL ESPINOZA
METHANE-Rough 3/8/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/8/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 3/8/2021 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/9/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/6/2021 Partial Approval RAFAEL ESPINOZA
METHANE-Rough 4/6/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 4/26/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 4/26/2021 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 4/27/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/27/2021 Conditional Approval RAFAEL ESPINOZA
METHANE-Rough 4/27/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 4/27/2021 Partial Approval RAFAEL ESPINOZA
METHANE-Rough 4/29/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 4/29/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 5/20/2021 Conditional Approval RAFAEL ESPINOZA
Wood Frame 5/21/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/25/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/25/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/26/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 6/3/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/3/2021 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 6/4/2021 Conditional Approval RAFAEL ESPINOZA
Wood Frame 6/17/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 6/22/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 6/24/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/24/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 6/29/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 7/2/2021 Partial Approval JAMES POWERS
Insulation 7/2/2021 Partial Approval JAMES POWERS
METHANE-Rough 7/2/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 7/2/2021 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 7/14/2021 Partial Approval JAMES POWERS
Insulation 7/15/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/20/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 7/20/2021 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 7/22/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/23/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 7/23/2021 Partial Approval JAMES POWERS
Insulation 7/29/2021 Partial Approval JAMES POWERS
Insulation 8/4/2021 Partial Approval JAMES POWERS
Wood Frame 8/5/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 8/10/2021 Partial Approval JAMES POWERS
Insulation 8/10/2021 Partial Approval JAMES POWERS
Drywall Nailing 8/13/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/17/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 8/17/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 8/20/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 8/20/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Partial Approval RAFAEL ESPINOZA
Insulation 9/13/2021 Partial Approval JAMES POWERS
Pre-Inspection 9/24/2021 Partial Approval JAMES POWERS
Drywall Nailing 10/13/2021 Partial Approval JAMES POWERS
Drywall Nailing 10/19/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 10/28/2021 Not Ready for Inspection JAMES POWERS
Drywall Nailing 11/3/2021 Partial Approval JAMES POWERS
Drywall Nailing 11/5/2021 Partial Approval JAMES POWERS
Drywall Nailing 11/8/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 11/12/2021 Partial Approval JAMES POWERS
Drywall Nailing 11/17/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 11/17/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 11/17/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 11/24/2021 Partial Approval RAFAEL ESPINOZA
Insulation 12/15/2021 Partial Approval JAMES POWERS
Pre-Inspection 4/6/2022 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 4/12/2022 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 4/14/2022 Partial Approval JAMES POWERS
Masonry Wall/Backfill 4/26/2022 Partial Approval JAMES POWERS
Pre-Inspection 6/29/2022 Partial Approval NICK DANERI
Footing/Foundation/Slab 7/21/2022 Partial Approval NICK DANERI
Drywall Nailing 8/5/2022 Partial Inspection GREGORY POMISH
Drywall Nailing 10/11/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/22/2022 Approved NICK DANERI
Final 11/22/2022 Corrections Issued NICK DANERI
Footing/Foundation/Slab 11/22/2022 Approved NICK DANERI
Green Building Final 11/22/2022 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 11/22/2022 Approved NICK DANERI
Reinforced Masonry Frame 11/22/2022 Approved NICK DANERI
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Not Ready NICK DANERI
Smoke Detectors 11/22/2022 Approved NICK DANERI
Verify Sprinkler Sign Off 11/22/2022 Approved NICK DANERI
Wood Frame 11/22/2022 Approved NICK DANERI
Final 12/22/2022 Not Ready for Inspection NICK DANERI
Green Building Final 12/22/2022 Approved NICK DANERI
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Approved NICK DANERI
Special/Order Compliance 12/23/2022 Conditional Approval NICK DANERI
Final 1/9/2023 OK to Issue CofO ERNESTO CORRAL