2635 N ADELBERT AVE 90039
Certificate Information: 2635 N ADELBERT AVE 90039
- Application / Permit
- 17010-20000-04600
- Plan Check / Job No.
- B17VN17950
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (28'1" x 42'8") 3 STORY DWELLING AND BASEMENT GARAGE
- Permit Issued
- Issued on 10/12/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 11/21/2017 | APPLICANT |
Assigned to Plan Check Engineer | 12/14/2017 | JEFFREY TANGONAN |
Green Plans Picked Up | 12/18/2017 | APPLICANT |
Corrections Issued | 12/19/2017 | JEFFREY TANGONAN |
Quality Review Completed | 12/21/2017 | DOUGLAS NAKATANI |
Building Plans Picked Up | 12/27/2017 | APPLICANT |
Applicant returned to address corrections | 5/3/2018 | JEFFREY TANGONAN |
Applicant returned to address corrections | 7/24/2018 | JEFFREY TANGONAN |
Plan Check Approved | 7/26/2018 | JEFFREY TANGONAN |
Issued | 10/12/2018 | LADBS |
CofO in Progress | 6/15/2023 | THOMAS LOGRASSO |
Permit Finaled | 6/29/2023 | DEROLD HAUFF |
CofO Issued | 6/29/2023 | DEROLD HAUFF |
Permit Finaled | 6/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
Address approval | Cleared | 3/14/2018 | LEE GUILBEAUX |
Certificate of Compliance | Cleared | 3/14/2018 | DAISY BENICIA |
Eng Process Fee Ord 176,300 | Cleared | 3/14/2018 | LEE GUILBEAUX |
Miscellaneous | Cleared | 3/14/2018 | LEE GUILBEAUX |
Permit | Cleared | 3/14/2018 | LEE GUILBEAUX |
Sewer availability | Cleared | 3/14/2018 | LEE GUILBEAUX |
Hydrant and Access approval | Cleared | 3/22/2018 | GILBERT URREA |
GPI Written Notices | Cleared | 5/3/2018 | JEFFREY TANGONAN |
Grading Pre-Inspection | Cleared | 5/3/2018 | JEFFREY TANGONAN |
Green Code | Cleared | 6/19/2018 | SARKIS HARABEDIAN |
Low Impact Development | Cleared | 7/19/2018 | ANDRES COVARRUBIAS |
Roof/Waste drainage to street | Cleared | 7/19/2018 | MARKOS PEREZ-BRAN |
Contact Information
Architect | Glen, Charles; Lic. No.: C33143 | , |
Contractor | Owner-Builder | , |
Engineer | Robinson, Rory Anthony; Lic. No.: GE2491 | 963 EAST SANTA CLARA ST VENTURA, CA 93001 |
Engineer | Soheil, Moeini; Lic. No.: C84000 | , |
Geologist | Robinson, Rory Anthony; Lic. No.: EG1902 | 963 EAST SANTA CLARA STREET VENTURA, CA 93001 |
Inspector Information
HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 4/17/2019 | Partial Approval | DAVID CHAN |
Footing/Foundation/Slab | 10/13/2020 | Not Ready for Inspection | COREY HUPP |
Footing/Foundation/Slab | 11/17/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
Deputy Reinf. Concrete | 11/18/2020 | No Access for Inspection | ELMER BLAND |
Piling/Pier/Caisson | 11/20/2020 | Partial Approval | KATHRYN BUTTERWORTH |
Deputy Reinf. Concrete | 11/23/2020 | No Access for Inspection | ELMER BLAND |
Excavation/Setback/Form/Re-Bar | 12/1/2020 | Conditional Approval | HAMIK HARTOUNIAN |
Footing/Foundation/Slab | 12/1/2020 | Conditional Approval | HAMIK HARTOUNIAN |
Deputy Reinf. Concrete | 12/3/2020 | No Access for Inspection | ELMER BLAND |
Footing/Foundation/Slab | 1/7/2021 | Corrections Issued | HAMIK HARTOUNIAN |
Footing/Foundation/Slab | 1/12/2021 | Partial Approval | KATHRYN BUTTERWORTH |
Deputy Reinf. Concrete | 1/13/2021 | Conditional Approval | THOMAS LOGRASSO |
Deputy Reinf. Concrete | 2/2/2021 | Partial Approval | RUBEN SALAS |
Excavation/Setback/Form/Re-Bar | 3/1/2021 | Not Ready for Inspection | RUBEN SALAS |
Masonry Wall/Backfill | 3/1/2021 | Corrections Issued | RUBEN SALAS |
Excavation/Setback/Form/Re-Bar | 3/11/2021 | Not Ready for Inspection | RUBEN SALAS |
Masonry Wall/Backfill | 3/11/2021 | Corrections Issued | RUBEN SALAS |
Excavation/Setback/Form/Re-Bar | 3/19/2021 | Partial Approval | STUART CHAPMAN |
Masonry Wall/Backfill | 3/19/2021 | Corrections Issued | STUART CHAPMAN |
Deputy Reinf. Concrete | 3/26/2021 | Partial Approval | RUBEN SALAS |
Special/Order Compliance | 3/31/2021 | Corrections Issued | STUART CHAPMAN |
Special/Order Compliance | 4/12/2021 | Partial Approval | KATHRYN BUTTERWORTH |
Excavation/Setback/Form/Re-Bar | 7/9/2021 | Partial Approval | JUSTIN CURTIS |
Footing/Foundation/Slab | 7/9/2021 | Partial Approval | JUSTIN CURTIS |
Structural Steel Frame | 7/9/2021 | Conditional Approval | JUSTIN CURTIS |
Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Corrections Issued | THOMAS LOGRASSO |
BUILDING-Rough-Frame | 11/1/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
Floor/Roof Diaphrgm/Shear Wall | 11/1/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
Green Building Rough | 11/1/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
MERV13>=Rough | 11/1/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
Verify Sprinkler Sign Off | 11/1/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
Wood Frame | 11/1/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
BUILDING-Rough-Frame | 11/16/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
Floor/Roof Diaphrgm/Shear Wall | 11/16/2021 | Corrections Issued | THOMAS LOGRASSO |
Green Building Rough | 11/16/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
MERV13>=Rough | 11/16/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
PLUMBING-Rough | 11/16/2021 | Corrections Issued | THOMAS LOGRASSO |
Verify Sprinkler Sign Off | 11/16/2021 | Corrections Issued | THOMAS LOGRASSO |
Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Partial Approval | THOMAS LOGRASSO |
BUILDING-Rough-Frame | 2/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
ELECTRICAL-Rough | 2/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
Green Building Rough | 2/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
HVAC-Rough | 2/4/2022 | Corrections Issued | THOMAS LOGRASSO |
MERV13>=Rough | 2/4/2022 | Approved | THOMAS LOGRASSO |
PLUMBING-Rough | 2/4/2022 | Approved | THOMAS LOGRASSO |
Verify Sprinkler Sign Off | 2/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
BUILDING-Rough-Frame | 2/10/2022 | Corrections Issued | THOMAS LOGRASSO |
ELECTRICAL-Rough | 2/10/2022 | Corrections Issued | THOMAS LOGRASSO |
Green Building Rough | 2/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
HVAC-Rough | 2/10/2022 | Partial Approval | THOMAS LOGRASSO |
Verify Sprinkler Sign Off | 2/10/2022 | Approved | THOMAS LOGRASSO |
BUILDING-Rough-Frame | 3/10/2022 | Conditional Approval | THOMAS LOGRASSO |
ELECTRICAL-Rough | 3/10/2022 | Partial Approval | THOMAS LOGRASSO |
Green Building Rough | 3/10/2022 | Approved | THOMAS LOGRASSO |
HVAC-Rough | 3/29/2022 | Approved | THOMAS LOGRASSO |
Insulation | 3/29/2022 | Conditional Approval | THOMAS LOGRASSO |
Interior/Exterior Lathing | 3/29/2022 | Partial Approval | THOMAS LOGRASSO |
Drywall Nailing | 4/18/2022 | Conditional Approval | THOMAS LOGRASSO |
Shower Pan | 5/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
Shower Pan | 6/7/2022 | Approved | THOMAS LOGRASSO |
BUILDING-Rough-Frame | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
Drywall Nailing | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
Final | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
Footing/Foundation/Slab | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
Green Building Final | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
MERV13>=Final | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
Service/Power Release | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
Smoke Detectors | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
BUILDING-Rough-Frame | 4/13/2023 | Approved | THOMAS LOGRASSO |
Drywall Nailing | 4/13/2023 | Approved | THOMAS LOGRASSO |
Final | 4/13/2023 | Corrections Issued | THOMAS LOGRASSO |
Footing/Foundation/Slab | 4/13/2023 | Approved | THOMAS LOGRASSO |
Green Building Final | 4/13/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
MERV13>=Final | 4/13/2023 | Approved | THOMAS LOGRASSO |
SGSOV-Seismic Gas S/O Valve | 4/13/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
Service/Power Release | 4/13/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
Smoke Detectors | 4/13/2023 | Approved | THOMAS LOGRASSO |
Final | 6/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
Green Building Final | 6/14/2023 | Approved | THOMAS LOGRASSO |
SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Approved | THOMAS LOGRASSO |
Service/Power Release | 6/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
Final | 6/15/2023 | OK to Issue CofO | THOMAS LOGRASSO |
Service/Power Release | 6/15/2023 | Approved | THOMAS LOGRASSO |