Pre-Inspection
|
2/18/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Special/Order Compliance
|
3/9/2020
|
Corrections Issued
|
DANIEL MC AULIFFE
|
Footing/Foundation/Slab
|
3/10/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
Deputy Reinf. Masonry
|
3/16/2020
|
Conditional Approval
|
BRUCE CAMPBELL
|
Deputy Reinf. Masonry
|
3/31/2020
|
Approved
|
DANIEL MC AULIFFE
|
Excavation/Setback/Form/Re-Bar
|
4/1/2020
|
Partial Approval
|
LANNY MERRICK
|
Footing/Foundation/Slab
|
4/3/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Footing/Foundation/Slab
|
4/15/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Green Building Rough
|
4/15/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
Masonry Wall/Backfill
|
4/21/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Reinforced Concrete Frame
|
4/24/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
Reinforced Masonry Frame
|
4/24/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Green Building Rough
|
4/27/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
Masonry Wall/Backfill
|
4/27/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Excavation/Setback/Form/Re-Bar
|
4/29/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Green Building Rough
|
5/4/2020
|
Approved
|
DANIEL MC AULIFFE
|
Reinforced Masonry Frame
|
5/4/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Deputy Reinf. Concrete
|
5/7/2020
|
Approved
|
DANIEL MC AULIFFE
|
Deputy Reinf. Masonry
|
5/7/2020
|
Approved
|
DANIEL MC AULIFFE
|
Masonry Wall/Backfill
|
5/7/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Deputy Reinf. Concrete
|
5/8/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Deputy Reinf. Masonry
|
5/8/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
Masonry Wall/Backfill
|
5/8/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Excavation/Setback/Form/Re-Bar
|
5/21/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Deputy Reinf. Masonry
|
5/22/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
Deputy Reinf. Concrete
|
5/26/2020
|
Approved
|
DANIEL MC AULIFFE
|
Footing/Foundation/Slab
|
6/30/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Reinforced Concrete Frame
|
7/6/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Excavation/Setback/Form/Re-Bar
|
7/8/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Deputy Reinf. Concrete
|
7/10/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
Excavation/Setback/Form/Re-Bar
|
7/31/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
Footing/Foundation/Slab
|
7/31/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
Excavation/Setback/Form/Re-Bar
|
8/11/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
Excavation/Setback/Form/Re-Bar
|
8/12/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Deputy Reinf. Concrete
|
8/13/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
Excavation/Setback/Form/Re-Bar
|
8/28/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
9/4/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
9/14/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
9/17/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
9/25/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
9/29/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
10/14/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
10/22/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Deputy Drilled-In Anchors
|
10/26/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
10/30/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
11/4/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
11/12/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
Insulation
|
11/17/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
Drywall Nailing
|
11/23/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Insulation
|
11/23/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
Insulation
|
12/8/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
12/18/2020
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
Floor/Roof Diaphrgm/Shear Wall
|
12/21/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
12/23/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
Insulation
|
12/30/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
Floor/Roof Diaphrgm/Shear Wall
|
1/5/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
Insulation
|
1/20/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
Insulation
|
1/26/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
Drywall Nailing
|
2/2/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
Insulation
|
2/19/2021
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
Insulation
|
2/23/2021
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
Drywall Nailing
|
2/25/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
Interior/Exterior Lathing
|
3/9/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
Insulation
|
4/8/2021
|
Partial Inspection
|
DANIEL MC AULIFFE
|
Special/Order Compliance
|
4/21/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
Insulation
|
4/26/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
Drywall Nailing
|
5/3/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
Drywall Nailing
|
5/10/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
Interior/Exterior Lathing
|
5/25/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
Interior/Exterior Lathing
|
6/1/2021
|
Partial Inspection
|
DAVID BURKHEAD
|
Drywall Nailing
|
1/3/2022
|
Approved
|
DANIEL MC AULIFFE
|
Final
|
1/3/2022
|
Partial Inspection
|
DANIEL MC AULIFFE
|
Footing/Foundation/Slab
|
1/3/2022
|
Approved
|
DANIEL MC AULIFFE
|
Green Building Final
|
1/3/2022
|
Approved
|
DANIEL MC AULIFFE
|
Reinforced Concrete Frame
|
1/3/2022
|
Approved
|
DANIEL MC AULIFFE
|
Reinforced Masonry Frame
|
1/3/2022
|
Approved
|
DANIEL MC AULIFFE
|
Smoke Detectors
|
1/3/2022
|
Approved
|
DANIEL MC AULIFFE
|
Structural Steel Frame
|
1/3/2022
|
Approved
|
DANIEL MC AULIFFE
|
Wood Frame
|
1/3/2022
|
Approved
|
DANIEL MC AULIFFE
|
Final
|
3/1/2022
|
Partial Inspection
|
DANIEL MC AULIFFE
|
Final
|
3/4/2022
|
Partial Inspection
|
DANIEL MC AULIFFE
|
Final
|
3/18/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
Final
|
3/22/2022
|
Partial Inspection
|
DANIEL MC AULIFFE
|
Final
|
3/25/2022
|
Permit Finaled
|
DANIEL MC AULIFFE
|