3430-3440 W SUNSET BLVD 90026
Certificate Information: 3430-3440 W SUNSET BLVD 90026
- Application / Permit
- 17014-30000-02810
- Plan Check / Job No.
- B17WL03215
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- 59'-8" x 22'-6" irreg. shaped addition(491 S.F.) to and change of use of an (e) 1-story office into 5 spaces(4 retail & 1 restaurant). Remove 41'-2" x 12'-8"(474 S.F.) portion at NE corner & 21'-22" x 4'(33 S.F.) irreg. shaped portion at NW corner of building. Restripe parking. SEE COMMMENTS.
- Permit Issued
- Issued on 11/15/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/26/2018
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 6/13/2017 | APPLICANT |
Assigned to Plan Check Engineer | 6/22/2017 | STEVEN KIM |
Corrections Issued | 6/26/2017 | STEVEN KIM |
Quality Review Completed | 6/29/2017 | FELIX FIGUEROA |
Building Plans Picked Up | 6/30/2017 | APPLICANT |
Disabled Access Plans Picked Up | 6/30/2017 | APPLICANT |
Green Plans Picked Up | 6/30/2017 | APPLICANT |
Applicant returned to address corrections | 8/2/2017 | STEVEN KIM |
Plan Check Approved | 11/13/2017 | STEVEN KIM |
Issued | 11/15/2017 | LADBS |
CofO in Progress | 10/19/2018 | EDWIN GREGORYONA |
Permit Finaled | 11/26/2018 | HAMID PISHEHVAR |
CofO Issued | 11/26/2018 | HAMID PISHEHVAR |
Permit Finaled | 11/26/2018 | HAMID PISHEHVAR |
Permit Application Clearance Information
Highway dedication | Cleared | 7/13/2017 | CARLA VALLADARES |
DAS Clearance | Cleared | 7/27/2017 | WAI LAU |
"Q" conditions | Cleared | 8/23/2017 | HERMAN VAN BUREN |
Address approval | Cleared | 8/23/2017 | ADRIAN SANCHEZ |
Bicycle Parking | Cleared | 8/23/2017 | JACOB BIGLER |
Encroachment in public way | Cleared | 8/23/2017 | JACOB BIGLER |
Eng Process Fee Ord 176,300 | Cleared | 8/23/2017 | RAVIL MANAPOV |
Sewer availability | Cleared | 8/23/2017 | ADRIAN SANCHEZ |
Comm Cor/Mini-Mall | Cleared | 9/5/2017 | JOHN DACEY |
Prkng lot landscape/Water mgmt | Cleared | 9/5/2017 | JOHN DACEY |
Low Impact Development | Cleared | 10/11/2017 | MARTIN FRAGOSO |
Green Code | Cleared | 10/19/2017 | RICHARD GARCIA |
Comm Cor/Mini-Mall | Cleared | 10/23/2017 | SARAH GOLDMAN |
Roof/Waste drainage to street | Cleared | 10/23/2017 | MAHELET GEBEYHU |
Contact Information
Contractor | Uhles Construction Inc; Lic. No.: 473748-B | P O BOX 80237 BAKERSFIELD, CA 93380 |
Engineer | Lee, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
JONATHAN QUACH, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
JOHN YAKUBYAN, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
RONALD JIMENEZ, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 2/23/2018 | Approved | EDWIN GREGORYONA |
Deputy Drilled-In Anchors | 2/28/2018 | Partial Approval | EDWIN GREGORYONA |
Excavation/Setback/Form/Re-Bar | 2/28/2018 | Partial Approval | EDWIN GREGORYONA |
Footing/Foundation/Slab | 2/28/2018 | Partial Approval | EDWIN GREGORYONA |
Green Building Rough | 3/5/2018 | Not Ready for Inspection | EDWIN GREGORYONA |
Reinforced Masonry Frame | 3/5/2018 | Not Ready for Inspection | EDWIN GREGORYONA |
Green Building Rough | 3/7/2018 | Not Ready for Inspection | EDWIN GREGORYONA |
Reinforced Masonry Frame | 3/7/2018 | Partial Approval | EDWIN GREGORYONA |
Footing/Foundation/Slab | 3/16/2018 | Partial Approval | EDWIN GREGORYONA |
Excavation/Setback/Form/Re-Bar | 4/2/2018 | Partial Approval | EDWIN GREGORYONA |
Footing/Foundation/Slab | 4/2/2018 | Partial Approval | EDWIN GREGORYONA |
Deputy Reinf. Concrete | 4/3/2018 | Approved | ARTHUR SARGSYAN |
Deputy Drilled-In Anchors | 4/6/2018 | Approved | ARTHUR SARGSYAN |
Footing/Foundation/Slab | 4/6/2018 | Partial Approval | EDWIN GREGORYONA |
Deputy Steel/Welding | 4/13/2018 | Partial Approval | EDWIN GREGORYONA |
Footing/Foundation/Slab | 4/13/2018 | Partial Approval | EDWIN GREGORYONA |
Excavation/Setback/Form/Re-Bar | 4/17/2018 | Partial Inspection | EDWIN GREGORYONA |
Floor/Roof Diaphrgm/Shear Wall | 4/25/2018 | Partial Approval | EDWIN GREGORYONA |
Green Building Rough | 4/25/2018 | Partial Inspection | EDWIN GREGORYONA |
Wood Frame | 4/25/2018 | Partial Approval | EDWIN GREGORYONA |
Drywall Nailing | 4/30/2018 | Partial Inspection | EDWIN GREGORYONA |
Green Building Rough | 4/30/2018 | Partial Inspection | EDWIN GREGORYONA |
Deputy Reinf. Concrete | 5/2/2018 | Partial Approval | EDWIN GREGORYONA |
Deputy Reinf. Masonry | 5/4/2018 | Partial Approval | EDWIN GREGORYONA |
Drywall Nailing | 5/4/2018 | Partial Approval | EDWIN GREGORYONA |
Green Building Rough | 5/4/2018 | Partial Inspection | EDWIN GREGORYONA |
Floor/Roof Diaphrgm/Shear Wall | 5/7/2018 | Conditional Approval | EDWIN GREGORYONA |
Wood Frame | 5/7/2018 | Partial Approval | EDWIN GREGORYONA |
Drywall Nailing | 5/10/2018 | Partial Inspection | EDWIN GREGORYONA |
Green Building Rough | 5/10/2018 | Partial Inspection | EDWIN GREGORYONA |
Deputy Drilled-In Anchors | 5/11/2018 | Partial Approval | EDWIN GREGORYONA |
Excavation/Setback/Form/Re-Bar | 5/11/2018 | Partial Approval | EDWIN GREGORYONA |
Wood Frame | 5/11/2018 | Partial Approval | EDWIN GREGORYONA |
Footing/Foundation/Slab | 5/15/2018 | Partial Approval | EDWIN GREGORYONA |
Deputy Steel/Welding | 5/22/2018 | Partial Approval | EDWIN GREGORYONA |
Green Building Rough | 5/22/2018 | Partial Inspection | EDWIN GREGORYONA |
Wood Frame | 5/22/2018 | Partial Approval | EDWIN GREGORYONA |
Deputy Steel/Welding | 5/23/2018 | Approved | ARTHUR SARGSYAN |
Deputy Steel/Welding | 5/23/2018 | Partial Approval | EDWIN GREGORYONA |
Drywall Nailing | 5/26/2018 | Partial Approval | EDWIN GREGORYONA |
Green Building Rough | 5/26/2018 | Partial Inspection | EDWIN GREGORYONA |
Interior/Exterior Lathing | 5/26/2018 | Approved | EDWIN GREGORYONA |
Drywall Nailing | 5/31/2018 | Partial Approval | EDWIN GREGORYONA |
Green Building Rough | 5/31/2018 | Partial Inspection | EDWIN GREGORYONA |
Green Building Rough | 6/5/2018 | Approved | EDWIN GREGORYONA |
Wood Frame | 6/5/2018 | Approved | EDWIN GREGORYONA |
Drywall Nailing | 7/19/2018 | Partial Inspection | EDWIN GREGORYONA |
Final | 7/19/2018 | Partial Inspection | EDWIN GREGORYONA |
Footing/Foundation/Slab | 7/19/2018 | Approved | EDWIN GREGORYONA |
Green Building Final | 7/19/2018 | Partial Inspection | EDWIN GREGORYONA |
Reinforced Masonry Frame | 7/19/2018 | Approved | EDWIN GREGORYONA |
SGSOV-Seismic Gas S/O Valve | 7/19/2018 | SGSOV Not Ready | EDWIN GREGORYONA |
Smoke Detectors | 7/19/2018 | Approved | EDWIN GREGORYONA |
Structural Steel Frame | 7/19/2018 | Approved | EDWIN GREGORYONA |
Drywall Nailing | 7/24/2018 | Approved | EDWIN GREGORYONA |
Final | 7/24/2018 | Partial Inspection | EDWIN GREGORYONA |
Green Building Final | 7/24/2018 | Partial Inspection | EDWIN GREGORYONA |
SGSOV-Seismic Gas S/O Valve | 7/24/2018 | SGSOV Approved | EDWIN GREGORYONA |
Final | 9/28/2018 | Conditional Approval | EDWIN GREGORYONA |
Green Building Final | 9/28/2018 | Approved | EDWIN GREGORYONA |