3451 S MOTOR AVE #1-30 90034
Certificate Information: 3451 S MOTOR AVE #1-30 90034
- Application / Permit
- 18010-10000-04349
- Plan Check / Job No.
- B18LA19105
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 30 UNIT TOC 139' X 32' (6 STORY) APARTMENT BUILDING WITH ONE LEVEL OF SUBTERRANEAN PARKING AND ROOFTOP DECK. TWO LEVELS OF TYPE 1A CONSTRUCTION UNDER 5 LEVELS OF TYPE IIIA CONSTRUCTION. NFPA 13 SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/8/2023
- Issuing Office
- Metro
- Current Status
- Issued on 8/8/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
Submitted | 9/7/2018 | APPLICANT |
Disabled Access Plans Picked Up | 10/10/2018 | APPLICANT |
Assigned to Plan Check Engineer | 10/11/2018 | MICHAEL PEREZ |
Corrections Issued | 10/25/2018 | MICHAEL PEREZ |
Quality Review Completed | 10/29/2018 | SIAVOSH POURSABAHIAN |
Building Plans Picked Up | 10/31/2018 | APPLICANT |
Green Plans Picked Up | 2/25/2019 | APPLICANT |
Applicant returned to address corrections | 4/23/2019 | MICHAEL PEREZ |
Plan Check Approved | 8/8/2023 | MICHAEL PEREZ |
Issued | 8/8/2023 | APPLICANT |
Permit Application Clearance Information
Address approval | Cleared | 2/26/2019 | ELENA LOPEZ |
Eng Process Fee Ord 176,300 | Cleared | 2/26/2019 | ELENA LOPEZ |
Permit | Cleared | 2/26/2019 | ELENA LOPEZ |
Encroachment in public way | Cleared | 4/23/2019 | ADRIAN SANCHEZ |
Hydrant and Access approval | Cleared | 5/9/2019 | ROBERT DUFF |
CPC | Cleared | 7/18/2019 | RICHARD REASER |
CPC | Cleared | 7/18/2019 | RICHARD REASER |
Prkng lot landscape/Water mgmt | Cleared | 7/18/2019 | DIANA JIMENEZ |
Green Code | Cleared | 8/21/2019 | MICHAEL PEREZ |
Bicycle Parking | Cleared | 11/5/2019 | ELAINE LEI |
Highway dedication | Cleared | 11/7/2019 | OSCAR GUTIERREZ |
Sewer availability | Cleared | 11/21/2019 | THOMAS LANG |
DAS Clearance | Cleared | 1/13/2020 | SHINE LIN |
Trees in Parkway | Cleared | 10/14/2020 | JOHN KIM |
Low Impact Development | Cleared | 1/21/2021 | ORVAL HERNANDEZ-MARCI |
Roof/Waste drainage to street | Cleared | 2/19/2021 | SAUL GARCIA |
Opn space landscape/Water mgmt | Cleared | 7/7/2021 | LAUREN PADICK |
Density Bonus 12.22.A.31 | Cleared | 7/27/2021 | NICHOLAS KAWAZOE |
Miscellaneous | Cleared | 4/26/2023 | NIKTA MOUSAVI |
GPI Written Notices | Cleared | 5/3/2023 | MICHAEL PEREZ |
Grading Pre-Inspection | Cleared | 5/3/2023 | MICHAEL PEREZ |
Miscellaneous | Cleared | 5/12/2023 | SPENCER WEJROWSKI |
Building over 3-story or 36-ft | Cleared | 7/11/2023 | CALOSHA APPROVED |
Excavation more than 5-ft deep | Cleared | 7/11/2023 | CALOSHA APPROVED |
Fire Marshal Fire Life Safety | Cleared | 7/18/2023 | DOMINIQUE MEDINA |
Work Adjacent to Public Way | Cleared | 8/1/2023 | LARRY LEE |
Contact Information
Architect | Uriu,, Giovanni; Lic. No.: C7487 | 830 SO GLENDALE AVENUE GLENDALE, CA 91205 |
Contractor | Owner-Builder | , |
Landscape Architect | Sparks,, Shelley E.; Lic. No.: LA2896 | 12224 ADDISON ST. VALLEY VILLAGE, CA 91607 |
Inspector Information
PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
Masonry Wall/Backfill | 12/20/2024 |
Inspection Request History
Pre-Inspection | 1/10/2024 | Approved | DERRICK SPENCER |
Deputy Grading | 5/7/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Grading | 5/8/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Grading | 5/9/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Grading | 5/10/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Grading | 5/13/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Grading | 5/15/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Grading | 5/16/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Grading | 5/17/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Grading | 5/24/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Grading | 5/28/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Grading | 5/29/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Grading | 5/30/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Reinf. Concrete | 6/28/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Reinf. Concrete | 7/1/2024 | Conditional Approval | PAUL DAVIDSON |
Excavation/Setback/Form/Re-Bar | 7/1/2024 | Partial Approval | PAUL DAVIDSON |
Footing/Foundation/Slab | 7/1/2024 | Partial Approval | PAUL DAVIDSON |
Deputy Reinf. Concrete | 7/8/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Reinf. Concrete | 7/15/2024 | Conditional Approval | PAUL DAVIDSON |
Excavation/Setback/Form/Re-Bar | 7/15/2024 | Partial Approval | PAUL DAVIDSON |
Green Building Rough | 7/15/2024 | Not Ready for Inspection | PAUL DAVIDSON |
Reinforced Concrete Frame | 7/15/2024 | Partial Approval | PAUL DAVIDSON |
Verify Sprinkler Sign Off | 7/15/2024 | Not Ready for Inspection | PAUL DAVIDSON |
Deputy Reinf. Concrete | 7/18/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Shotcrete | 7/18/2024 | Conditional Approval | PAUL DAVIDSON |
Excavation/Setback/Form/Re-Bar | 7/19/2024 | Partial Approval | PAUL DAVIDSON |
Green Building Rough | 7/19/2024 | Not Ready for Inspection | PAUL DAVIDSON |
Reinforced Concrete Frame | 7/19/2024 | Partial Approval | PAUL DAVIDSON |
Verify Sprinkler Sign Off | 7/19/2024 | Not Ready for Inspection | PAUL DAVIDSON |
Deputy Shotcrete | 7/22/2024 | Conditional Approval | PAUL DAVIDSON |
Deputy Shotcrete | 7/23/2024 | Conditional Approval | PAUL DAVIDSON |
Special/Order Compliance | 8/6/2024 | Partial Inspection | PAUL DAVIDSON |
Deputy Reinf. Masonry | 9/10/2024 | Conditional Approval | DANIEL VARNUM |
Deputy Reinf. Masonry | 9/18/2024 | Conditional Approval | DANIEL VARNUM |
Excavation/Setback/Form/Re-Bar | 9/18/2024 | Not Ready for Inspection | DANIEL VARNUM |
Green Building Rough | 9/18/2024 | Not Ready for Inspection | DANIEL VARNUM |
Masonry Wall/Backfill | 9/18/2024 | Partial Approval | DANIEL VARNUM |
Verify Sprinkler Sign Off | 9/18/2024 | Not Ready for Inspection | DANIEL VARNUM |
Deputy Reinf. Concrete | 10/4/2024 | Conditional Approval | DANIEL VARNUM |
Excavation/Setback/Form/Re-Bar | 10/4/2024 | Partial Approval | DANIEL VARNUM |
Footing/Foundation/Slab | 10/4/2024 | Partial Approval | DANIEL VARNUM |
Deputy Reinf. Concrete | 10/24/2024 | Conditional Approval | DANIEL VARNUM |
Footing/Foundation/Slab | 10/25/2024 | Not Ready for Inspection | DANIEL VARNUM |
Deputy Reinf. Concrete | 10/28/2024 | Conditional Approval | DANIEL VARNUM |
Excavation/Setback/Form/Re-Bar | 10/30/2024 | Partial Approval | DANIEL VARNUM |
Deputy Reinf. Concrete | 11/4/2024 | Conditional Approval | DANIEL VARNUM |
Deputy Reinf. Concrete | 11/5/2024 | Conditional Approval | PAUL DAVIDSON |
Excavation/Setback/Form/Re-Bar | 11/5/2024 | Not Ready for Inspection | PAUL DAVIDSON |
Deputy Reinf. Masonry | 11/7/2024 | Conditional Approval | FARHAD DADBIN |
Excavation/Setback/Form/Re-Bar | 11/7/2024 | Partial Approval | FARHAD DADBIN |
Deputy Reinf. Masonry | 11/12/2024 | Conditional Approval | PAUL DAVIDSON |
Masonry Wall/Backfill | 11/15/2024 | Partial Approval | PAUL DAVIDSON |
Masonry Wall/Backfill | 11/19/2024 | Partial Approval | PAUL DAVIDSON |
Deputy Reinf. Masonry | 11/27/2024 | Conditional Approval | DANIEL VARNUM |