361 S SPRING ST 90013

Certificate Information: 361 S SPRING ST 90013

Application / Permit
18010-10003-02402
Plan Check / Job No.
B19LA06267
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(52) Foundation Only
Work Description
Early Start Permit for New 12-story Hotel building for foundation only. No modular construction.
Permit Issued
Issued on 5/24/2019
Issuing Office
Metro
Current Status
Permit Finaled on 8/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 5/24/2019 ALLEN MANALANSAN
Issued 5/24/2019 LADBS
Permit Finaled 8/20/2020 JAMES POWERS

Permit Application Clearance Information

Address approval Cleared 3/28/2019 KARAN PATEL
DAS Clearance Cleared 3/28/2019 ALLEN MANALANSAN
Eng Process Fee Ord 176,300 Cleared 3/28/2019 KARAN PATEL
Highway dedication Cleared 3/28/2019 KARAN PATEL
Green Code Cleared 4/2/2019 ALLEN MANALANSAN
Permit Cleared 4/2/2019 ERIK BEASLEY
Sewer availability Cleared 4/2/2019 ERIK BEASLEY
Fire Marshall Fire Life Safety Cleared 4/10/2019 GEORGE SUCHAND
Food Service Establishment Cleared 4/22/2019 KENNETH BROWNE
Bicycle Parking Cleared 4/24/2019 KAREN LE
Hydrant and Access approval Cleared 4/24/2019 GEORGE SUCHAND
Low Impact Development Cleared 4/24/2019 ALLEN MANALANSAN
City Hist. Cultural Monument Cleared 5/6/2019 LAMBERT GIESSINGER
Historic monument Cleared 5/6/2019 LAMBERT GIESSINGER
Work Adjacent to Public Way Cleared 5/7/2019 CHIU TAM
"D" conditions Cleared 5/9/2019 SOPHIE GABEL-SCHEINBAU
"Q" conditions Cleared 5/9/2019 SOPHIE GABEL-SCHEINBAU
CPC Cleared 5/9/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 5/9/2019 SOPHIE GABEL-SCHEINBAU
Site Plan review Cleared 5/9/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 5/9/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 5/9/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 5/9/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 5/9/2019 SOPHIE GABEL-SCHEINBAU
Driveway location Cleared 5/14/2019 MOHAMMAD HASAN
Historical monument Cleared 5/16/2019 JIM URQUHART
Project located in CRA area Cleared 5/16/2019 JIM URQUHART
Roof/Waste drainage to street Cleared 5/23/2019 ELAINE LEI
Building over 3-story or 36-ft Cleared 5/24/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 5/24/2019 CALOSHA APPROVED
Food establishment approval Cleared 5/24/2019 LACDHS APPROVED

Contact Information

Contractor Mortenson M A Company; Lic. No.: 411701-A ATTN LEGAL   700 MEADOW LANE NORTH    MINNEAPOLIS, MN 55422
Engineer Bueno,, Jaime Luis; Lic. No.: C65389 1111 S GRAND AVE UNIT 510      LOS ANGELES, CA 90015
Engineer Heeringa,, Roger L; Lic. No.: S4536 818 STEWART ST #1000      SEATTLE, WA 98101

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/18/2019 Approved JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/2/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/16/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 7/17/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/18/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/19/2019 Partial Approval JAMES POWERS
Deputy Shotcrete 7/26/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/26/2019 Partial Approval JAMES POWERS
Deputy Shotcrete 7/29/2019 Partial Approval JAMES POWERS
Deputy Shotcrete 7/30/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/7/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/8/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/9/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/9/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/29/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/29/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/6/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 9/6/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 9/9/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/10/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/12/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/13/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/20/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/25/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/3/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/4/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/7/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/8/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/9/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/21/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/21/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/22/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/22/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/23/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/23/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/24/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/24/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 10/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/30/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/31/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/1/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/4/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/5/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/12/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/13/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/14/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/18/2020 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 2/19/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/20/2020 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 2/21/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/5/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/6/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/7/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/8/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/11/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/12/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/13/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/14/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/15/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/21/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/22/2020 Partial Approval JAMES POWERS