361 S SPRING ST 90013
Certificate Information: 361 S SPRING ST 90013
- Application / Permit
- 18010-10004-02402
- Plan Check / Job No.
- B19LA11536
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (52) Foundation Only
- Work Description
- Supplemental to 18010-10003-02402 for fdn revisions to include the fire tank vault and crane fdn
- Permit Issued
- Issued on 6/11/2019
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 6/5/2019 | APPLICANT |
Assigned to Plan Check Engineer | 6/5/2019 | ALLEN MANALANSAN |
Corrections Issued | 6/5/2019 | ALLEN MANALANSAN |
Plan Check Approved | 6/10/2019 | ALLEN MANALANSAN |
Issued | 6/11/2019 | LADBS |
Permit Finaled | 6/14/2021 | JAMES POWERS |
Permit Application Clearance Information
Historical monument | Cleared | 6/6/2019 | JIM URQUHART |
Project located in CRA area | Cleared | 6/6/2019 | JIM URQUHART |
Fire Marshall Fire Life Safety | Cleared | 6/10/2019 | WILLIAM JOHNS |
Contact Information
Contractor | Mortenson M A Company; Lic. No.: 411701-A | ATTN LEGAL 700 MEADOW LANE NORTH MINNEAPOLIS, MN 55422 |
Contractor | Mortenson M A Company; Lic. No.: 411701-B | ATTN LEGAL 700 MEADOW LANE NORTH MINNEAPOLIS, MN 55422 |
Engineer | Bueno,, Jaime Luis; Lic. No.: C65389 | 1111 S GRAND AVE UNIT 510 LOS ANGELES, CA 90015 |
Engineer | Heeringa,, Roger L; Lic. No.: S4536 | 818 STEWART ST #1000 SEATTLE, WA 98101 |
Inspector Information
NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Deputy Reinf. Concrete | 7/1/2019 | Partial Approval | JAMES POWERS |
Excavation/Setback/Form/Re-Bar | 7/16/2019 | Partial Approval | JAMES POWERS |
Excavation/Setback/Form/Re-Bar | 7/17/2019 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 7/18/2019 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 8/8/2019 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 8/9/2019 | Conditional Approval | DANIEL COLLINS |
Deputy Reinf. Concrete | 8/14/2019 | Conditional Approval | DANIEL COLLINS |
Deputy Reinf. Concrete | 9/13/2019 | Conditional Approval | DANIEL COLLINS |
Deputy Reinf. Concrete | 9/16/2019 | Conditional Approval | DANIEL COLLINS |
Deputy Reinf. Concrete | 9/17/2019 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 10/16/2019 | Conditional Approval | DANIEL COLLINS |
Deputy Reinf. Concrete | 10/22/2019 | Conditional Approval | DANIEL COLLINS |
Deputy Reinf. Concrete | 10/24/2019 | Conditional Approval | DANIEL COLLINS |
Deputy Reinf. Concrete | 10/25/2019 | Approved | JOEY BUCHANAN |
Deputy Reinf. Concrete | 11/18/2019 | Conditional Approval | DANIEL COLLINS |
Deputy Reinf. Concrete | 1/3/2020 | Conditional Approval | DANIEL COLLINS |
Deputy Reinf. Concrete | 1/9/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 1/21/2020 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 1/27/2020 | Conditional Approval | DANIEL COLLINS |
Deputy Steel/Welding | 1/28/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 2/6/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 2/12/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 2/13/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 2/21/2020 | Partial Approval | JAMES POWERS |
Deputy Shotcrete | 2/21/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 2/24/2020 | Partial Approval | JAMES POWERS |
Deputy Shotcrete | 2/24/2020 | Partial Approval | JAMES POWERS |
Deputy Drilled-In Anchors | 2/26/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 2/26/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 3/6/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 9/11/2020 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 9/11/2020 | Partial Approval | JAMES POWERS |
Deputy Drilled-In Anchors | 10/16/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 12/23/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 12/29/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 12/30/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 1/5/2021 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 1/13/2021 | Partial Approval | JAMES POWERS |