Pre-Inspection
|
1/23/2020
|
Approved
|
JOHN KITCKO
|
Pre-Inspection
|
1/29/2020
|
Partial Inspection
|
JOHN KITCKO
|
Footing/Foundation/Slab
|
2/24/2020
|
Partial Inspection
|
JOHN KITCKO
|
Footing/Foundation/Slab
|
3/6/2020
|
Partial Approval
|
CAMERON CHABAN
|
SUSMP-Std. Urban Storm Water
|
1/7/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
1/14/2021
|
Partial Inspection
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
1/15/2021
|
Partial Approval
|
JOHN KITCKO
|
Footing/Foundation/Slab
|
2/9/2021
|
Corrections Issued
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
2/11/2021
|
Partial Approval
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
2/17/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
2/17/2021
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
2/17/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
2/18/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
2/18/2021
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
2/18/2021
|
Approved
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
2/18/2021
|
Partial Approval
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
2/19/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
2/19/2021
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
2/19/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
2/22/2021
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
2/22/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
2/23/2021
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
2/23/2021
|
Approved
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
2/23/2021
|
Partial Approval
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
2/24/2021
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
2/24/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
2/25/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
2/25/2021
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
2/25/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
2/26/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
2/26/2021
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
2/26/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
3/1/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
3/2/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
3/3/2021
|
Approved
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
3/3/2021
|
Partial Approval
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
3/4/2021
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
3/5/2021
|
Approved
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
3/30/2021
|
Partial Inspection
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
4/15/2021
|
Partial Approval
|
JOHN KITCKO
|
Deputy Reinf. Masonry
|
4/22/2021
|
Approved
|
HAMID PISHEHVAR
|
Deputy Reinf. Masonry
|
4/23/2021
|
Approved
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
4/23/2021
|
Partial Approval
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
5/3/2021
|
Partial Approval
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
5/27/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Green Building Rough
|
5/27/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Verify Sprinkler Sign Off
|
5/27/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
5/27/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
6/2/2021
|
Partial Approval
|
JOHN KITCKO
|
Green Building Rough
|
6/8/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Verify Sprinkler Sign Off
|
6/8/2021
|
Approved
|
JOHN KITCKO
|
Wood Frame
|
6/8/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Pre-Inspection
|
6/9/2021
|
Partial Approval
|
JOHN KITCKO
|
Deputy Steel/Welding
|
6/21/2021
|
Approved
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
6/24/2021
|
No Access for Inspection
|
JOHN KITCKO
|
Green Building Rough
|
6/24/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Masonry Wall/Backfill
|
6/24/2021
|
No Access for Inspection
|
JOHN KITCKO
|
Wood Frame
|
6/24/2021
|
No Access for Inspection
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
6/25/2021
|
Partial Approval
|
ROBERT DAVIS
|
Floor/Roof Diaphrgm/Shear Wall
|
6/25/2021
|
Conditional Approval
|
ROBERT DAVIS
|
Masonry Wall/Backfill
|
6/25/2021
|
Partial Approval
|
ROBERT DAVIS
|
Deputy Steel/Welding
|
6/30/2021
|
Approved
|
JOHN KITCKO
|
Deputy Steel/Welding
|
7/1/2021
|
Approved
|
JOHN KITCKO
|
Deputy Steel/Welding
|
7/2/2021
|
Approved
|
JOHN KITCKO
|
Deputy Steel/Welding
|
7/6/2021
|
Approved
|
JOHN KITCKO
|
Deputy Steel/Welding
|
7/20/2021
|
Conditional Approval
|
DANIEL VARNUM
|
Excavation/Setback/Form/Re-Bar
|
7/20/2021
|
Partial Approval
|
CAMERON CHABAN
|
Deputy Steel/Welding
|
7/23/2021
|
Approved
|
JOHN KITCKO
|
Green Building Rough
|
7/26/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
7/26/2021
|
Partial Approval
|
JOHN KITCKO
|
Green Building Rough
|
8/10/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
8/10/2021
|
Partial Approval
|
JOHN KITCKO
|
Deputy Wood Construction
|
8/12/2021
|
Conditional Approval
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
8/18/2021
|
Partial Approval
|
JOHN KITCKO
|
Green Building Rough
|
8/18/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
8/18/2021
|
Partial Inspection
|
JOHN KITCKO
|
Deputy Steel/Welding
|
9/10/2021
|
Approved
|
JOHN KITCKO
|
Green Building Rough
|
9/10/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
9/10/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Steel/Welding
|
9/13/2021
|
Approved
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
9/13/2021
|
Partial Approval
|
JOHN KITCKO
|
Green Building Rough
|
9/30/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
9/30/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
10/1/2021
|
Partial Approval
|
JOHN KITCKO
|
Deputy Wood Construction
|
10/7/2021
|
Conditional Approval
|
JOHN KITCKO
|
Floor/Roof Diaphrgm/Shear Wall
|
10/22/2021
|
Not Ready for Inspection
|
SORIN CIRSTOIU
|
Floor/Roof Diaphrgm/Shear Wall
|
10/28/2021
|
Partial Approval
|
JOHN KITCKO
|
Deputy Wood Construction
|
11/23/2021
|
Approved
|
JOHN KITCKO
|
Insulation
|
12/1/2021
|
Partial Inspection
|
JOHN KITCKO
|
Green Building Rough
|
12/2/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
12/2/2021
|
Partial Inspection
|
JOHN KITCKO
|
Pre-Inspection
|
12/3/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Wood Construction
|
12/15/2021
|
Conditional Approval
|
JOHN KITCKO
|
Deputy Wood Construction
|
1/4/2022
|
Approved
|
JOHN KITCKO
|
Green Building Rough
|
1/5/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
1/5/2022
|
Partial Inspection
|
JOHN KITCKO
|
Deputy Wood Construction
|
1/10/2022
|
Approved
|
JOHN KITCKO
|
Deputy Wood Construction
|
1/12/2022
|
Approved
|
JOHN KITCKO
|
Green Building Rough
|
1/13/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
1/13/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
1/14/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
2/1/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Wood Construction
|
2/9/2022
|
Approved
|
JOHN KITCKO
|
Deputy Wood Construction
|
2/16/2022
|
Conditional Approval
|
JOHN KITCKO
|
Green Building Rough
|
2/16/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Wood Construction
|
2/17/2022
|
Approved
|
JOHN KITCKO
|
Wood Frame
|
2/17/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Wood Construction
|
2/18/2022
|
Conditional Approval
|
JOHN KITCKO
|
Deputy Wood Construction
|
2/22/2022
|
Conditional Approval
|
ANDREW DORSO
|
Deputy Wood Construction
|
2/22/2022
|
Conditional Approval
|
CAMERON CHABAN
|
Deputy Wood Construction
|
2/23/2022
|
Conditional Approval
|
CAMERON CHABAN
|
Excavation/Setback/Form/Re-Bar
|
2/23/2022
|
Not Ready for Inspection
|
CAMERON CHABAN
|
Floor/Roof Diaphrgm/Shear Wall
|
2/23/2022
|
Partial Approval
|
CAMERON CHABAN
|
Green Building Rough
|
2/23/2022
|
Partial Inspection
|
CAMERON CHABAN
|
Masonry Wall/Backfill
|
2/23/2022
|
Not Ready for Inspection
|
CAMERON CHABAN
|
Deputy Wood Construction
|
2/24/2022
|
Conditional Approval
|
JOHN KITCKO
|
Wood Frame
|
2/25/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
3/1/2022
|
Partial Approval
|
JOHN KITCKO
|
Deputy Wood Construction
|
3/7/2022
|
Approved
|
JOHN KITCKO
|
Green Building Rough
|
3/8/2022
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
3/8/2022
|
Partial Approval
|
JOHN KITCKO
|
Green Building Rough
|
3/10/2022
|
Not Ready for Inspection
|
ANDREW DORSO
|
Wood Frame
|
3/10/2022
|
Partial Inspection
|
ANDREW DORSO
|
Green Building Rough
|
3/15/2022
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
3/15/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
3/16/2022
|
Partial Approval
|
JOHN KITCKO
|
Green Building Rough
|
3/18/2022
|
Partial Inspection
|
CAMERON CHABAN
|
Wood Frame
|
3/18/2022
|
Partial Approval
|
CAMERON CHABAN
|
Deputy Wood Construction
|
3/22/2022
|
Approved
|
JOHN KITCKO
|
Insulation
|
3/29/2022
|
Partial Approval
|
DANIEL VARNUM
|
Interior/Exterior Lathing
|
3/29/2022
|
Not Ready for Inspection
|
DANIEL VARNUM
|
Green Building Rough
|
3/30/2022
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
3/30/2022
|
Partial Approval
|
JOHN KITCKO
|
Deputy Wood Construction
|
3/31/2022
|
Approved
|
JOHN KITCKO
|
Insulation
|
3/31/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Interior/Exterior Lathing
|
3/31/2022
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
4/4/2022
|
Partial Approval
|
JOHN KITCKO
|
Green Building Rough
|
4/4/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
4/4/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
4/6/2022
|
Partial Inspection
|
JOHN KITCKO
|
Interior/Exterior Lathing
|
4/14/2022
|
Partial Approval
|
JOHN KITCKO
|
Masonry Wall/Backfill
|
4/15/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Green Building Rough
|
4/18/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
4/18/2022
|
Partial Approval
|
JOHN KITCKO
|
Masonry Wall/Backfill
|
4/19/2022
|
Partial Approval
|
JOHN KITCKO
|
Deputy Wood Construction
|
4/25/2022
|
Conditional Approval
|
JOHN KITCKO
|
Insulation
|
4/25/2022
|
Partial Approval
|
JOHN KITCKO
|
Green Building Rough
|
4/26/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
4/26/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
4/27/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
4/28/2022
|
Partial Approval
|
JOHN KITCKO
|
Masonry Wall/Backfill
|
4/29/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
5/3/2022
|
Partial Approval
|
JOHN KITCKO
|
Green Building Rough
|
5/4/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
5/4/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
5/5/2022
|
No Access for Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
5/6/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
5/6/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Wood Construction
|
5/10/2022
|
Approved
|
JOHN KITCKO
|
Green Building Rough
|
5/10/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
5/10/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Green Building Rough
|
5/13/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
5/13/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
5/16/2022
|
Partial Approval
|
JOHN KITCKO
|
Green Building Rough
|
5/17/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
5/17/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
5/18/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
5/19/2022
|
Partial Approval
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
6/2/2022
|
Partial Inspection
|
CAMERON CHABAN
|
Green Building Rough
|
6/2/2022
|
Partial Inspection
|
CAMERON CHABAN
|
Wood Frame
|
6/2/2022
|
Partial Approval
|
CAMERON CHABAN
|
Masonry Wall/Backfill
|
6/3/2022
|
Partial Inspection
|
CAMERON CHABAN
|
Wood Frame
|
6/8/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
6/14/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
6/15/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
6/16/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
6/17/2022
|
Partial Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
6/22/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Green Building Rough
|
6/22/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
6/22/2022
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
6/22/2022
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
6/23/2022
|
Conditional Approval
|
JOHN KITCKO
|
Drywall Nailing
|
6/27/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Green Building Rough
|
6/27/2022
|
Approved
|
JOHN KITCKO
|
Wood Frame
|
6/27/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
6/28/2022
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
6/29/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
6/29/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
6/30/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
6/30/2022
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
7/1/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
7/1/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Interior/Exterior Lathing
|
7/6/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Interior/Exterior Lathing
|
7/14/2022
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
7/18/2022
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
7/18/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
7/20/2022
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
7/21/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
7/21/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
7/25/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Masonry Wall/Backfill
|
7/25/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
7/25/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
7/28/2022
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
7/28/2022
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
7/29/2022
|
Partial Approval
|
JOHN KITCKO
|
Interior/Exterior Lathing
|
8/2/2022
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
8/2/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
8/4/2022
|
Partial Approval
|
DANIEL VARNUM
|
Masonry Wall/Backfill
|
8/4/2022
|
Partial Approval
|
DANIEL VARNUM
|
Insulation
|
8/5/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
8/5/2022
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
8/10/2022
|
Partial Approval
|
ROBERT DAVIS
|
Insulation
|
8/10/2022
|
Partial Approval
|
ROBERT DAVIS
|
Insulation
|
8/12/2022
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
8/19/2022
|
No Access for Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
8/23/2022
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
8/30/2022
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
8/31/2022
|
Partial Approval
|
ROBERT DAVIS
|
Insulation
|
12/6/2022
|
Conditional Approval
|
CAMERON CHABAN
|
Drywall Nailing
|
12/22/2022
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
12/28/2022
|
Partial Approval
|
JOHN KITCKO
|
Final
|
3/13/2023
|
Partial Inspection
|
JOHN KITCKO
|
Footing/Foundation/Slab
|
3/13/2023
|
Approved
|
JOHN KITCKO
|
Green Building Final
|
3/13/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
Reinforced Concrete Frame
|
3/13/2023
|
Approved
|
JOHN KITCKO
|
SGSOV-Seismic Gas S/O Valve
|
3/13/2023
|
SGSOV Not Ready
|
JOHN KITCKO
|
SUSMP-Std. Urban Storm Water
|
3/13/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
Smoke Detectors
|
3/13/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
Structural Steel Frame
|
3/13/2023
|
Approved
|
JOHN KITCKO
|
Wood Frame
|
3/13/2023
|
Approved
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
4/26/2023
|
Partial Approval
|
JOHN KITCKO
|
Final
|
8/24/2023
|
Partial Inspection
|
JOHN KITCKO
|
Green Building Final
|
8/24/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
SGSOV-Seismic Gas S/O Valve
|
8/24/2023
|
SGSOV Approved
|
JOHN KITCKO
|
SUSMP-Std. Urban Storm Water
|
8/24/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
Smoke Detectors
|
8/24/2023
|
Approved
|
JOHN KITCKO
|
Final
|
8/29/2023
|
Partial Inspection
|
JOHN KITCKO
|
Green Building Final
|
8/29/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
SUSMP-Std. Urban Storm Water
|
8/29/2023
|
Approved
|
JOHN KITCKO
|
Final
|
9/13/2023
|
Partial Inspection
|
JOHN KITCKO
|
Green Building Final
|
9/13/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
Final
|
10/2/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
Green Building Final
|
10/2/2023
|
Approved
|
JOHN KITCKO
|
Final
|
10/12/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
Final
|
10/23/2023
|
OK for TCO
|
JOHN KITCKO
|
Final
|
3/6/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
Special/Order Compliance
|
3/27/2024
|
Partial Inspection
|
JOHN KITCKO
|
Final
|
6/11/2024
|
OK to Issue CofO
|
JOHN KITCKO
|