3134-3136 N GRIFFIN AVE 90031
Certificate Information: 3134-3136 N GRIFFIN AVE 90031
- Application / Permit
- 18014-20000-03258
- Plan Check / Job No.
- B18VN09915
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add 2-story 29' x 15'3" to the rear of dwelling (at ascending slope) for bathroom and crawl space on ground floor and accessory dwelling unit with roof deck on 2nd floor per AB494 & SB229. All works per design. See comment./
- Permit Issued
- Issued on 10/10/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 6/11/2018 | APPLICANT |
Green Plans Picked Up | 6/20/2018 | APPLICANT |
Assigned to Plan Check Engineer | 7/5/2018 | ALDOUS CHIC |
Corrections Issued | 7/9/2018 | ALDOUS CHIC |
Quality Review Completed | 7/9/2018 | CHON CHIO KUO |
Building Plans Picked Up | 7/9/2018 | APPLICANT |
Applicant returned to address corrections | 9/10/2018 | ALDOUS CHIC |
Plan Check Approved | 10/9/2018 | ALDOUS CHIC |
Issued | 10/10/2018 | LADBS |
CofO in Progress | 12/27/2021 | COREY HUPP |
CofO in Progress | 12/27/2021 | COREY HUPP |
Permit Finaled | 5/7/2022 | DEROLD HAUFF |
CofO Issued | 5/7/2022 | DEROLD HAUFF |
Permit Finaled | 5/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
Grading Pre-Inspection | Cleared | 6/15/2018 | ALDOUS CHIC |
"D" conditions | Cleared | 7/13/2018 | NICOLE SANCHEZ |
"Q" conditions | Cleared | 7/13/2018 | NICOLE SANCHEZ |
Miscellaneous | Cleared | 7/13/2018 | NICOLE SANCHEZ |
ZI | Cleared | 7/13/2018 | NICOLE SANCHEZ |
Address approval | Cleared | 7/23/2018 | JOHN LIN |
Eng Process Fee Ord 176,300 | Cleared | 7/23/2018 | JOHN LIN |
Green Code | Cleared | 7/23/2018 | COLIN LOREDO |
Roof/Waste drainage to street | Cleared | 7/23/2018 | JOHN LIN |
Sewer availability | Cleared | 7/23/2018 | JOHN LIN |
GPI Written Notices | Cleared | 9/10/2018 | ALDOUS CHIC |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Barr, Joseph Daniel Iii; Lic. No.: C70708 | 1910 20TH AVE DRIVE NE #109 HICKORY, NC 28601 |
Engineer | El-Mustapha, Ahmad Mahmoud; Lic. No.: C49021 | 1608 CALLE CRISTINA SAN DIMAS, CA 91773 |
Engineer | Vidal, Juan Alonso; Lic. No.: GE861 | 15331 DOGWOOD ST WESTMINSTER, CA 92683 |
Geologist | Miller, Jonathan Steven; Lic. No.: EG2391 | 2800 NEILSON WAY #210 SANTA MONICA, CA 90405 |
Inspector Information
LILIANA PORTILLO, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
DEVON JACKSON, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
KELVIN MARTINEZ, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
IVAN SARABIA, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
CHRISTOPHER MORFIN, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
ROBERT MAGCALAS, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
GEM DE OCAMPO, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 11/16/2018 | Partial Approval | ENRIQUE MIRELES |
Excavation/Setback/Form/Re-Bar | 11/27/2018 | Partial Approval | RUBEN SALAS |
Deputy Reinf. Concrete | 11/28/2018 | Approved | ENRIQUE MIRELES |
Excavation/Setback/Form/Re-Bar | 12/7/2018 | Partial Approval | ENRIQUE MIRELES |
Underground Mechanical | 12/18/2018 | Partial Inspection | ENRIQUE MIRELES |
Excavation/Setback/Form/Re-Bar | 1/24/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
Excavation/Setback/Form/Re-Bar | 1/28/2019 | Approved | ENRIQUE MIRELES |
Deputy Reinf. Concrete | 1/29/2019 | Approved | ENRIQUE MIRELES |
Excavation/Setback/Form/Re-Bar | 2/8/2019 | Partial Approval | ENRIQUE MIRELES |
Deputy Reinf. Concrete | 2/11/2019 | Approved | ENRIQUE MIRELES |
Excavation/Setback/Form/Re-Bar | 2/11/2019 | No Access for Inspection | ENRIQUE MIRELES |
PLUMBING-Rough | 2/26/2019 | Partial Approval | RUBEN SALAS |
Excavation/Setback/Form/Re-Bar | 3/27/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
Footing/Foundation/Slab | 5/7/2019 | Approved | ENRIQUE MIRELES |
Underground Mechanical | 6/26/2019 | Approved | ENRIQUE MIRELES |
Underground Mechanical | 6/28/2019 | No Access for Inspection | ENRIQUE MIRELES |
Floor/Roof Diaphrgm/Shear Wall | 8/5/2019 | Corrections Issued | ENRIQUE MIRELES |
Floor/Roof Diaphrgm/Shear Wall | 8/30/2019 | Approved | ENRIQUE MIRELES |
Gas Test | 8/30/2019 | Approved | ENRIQUE MIRELES |
Green Building Rough | 2/7/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
Interior/Exterior Lathing | 2/7/2020 | Partial Approval | ENRIQUE MIRELES |
Interior/Exterior Lathing | 10/26/2020 | Partial Approval | COREY HUPP |
Rough-Elec/Plmb/HVAC | 10/26/2020 | Approved | COREY HUPP |
Shower Pan | 10/26/2020 | Approved | COREY HUPP |
BUILDING-Rough-Frame | 10/29/2020 | Approved | COREY HUPP |
Green Building Rough | 10/29/2020 | Approved | COREY HUPP |
Insulation | 11/5/2020 | Approved | COREY HUPP |
Drywall Nailing | 12/29/2020 | Approved | HAMIK HARTOUNIAN |
Interior/Exterior Lathing | 12/29/2020 | Partial Approval | HAMIK HARTOUNIAN |
Final | 11/30/2021 | Corrections Issued | COREY HUPP |
Green Building Final | 11/30/2021 | Not Ready for Inspection | COREY HUPP |
SGSOV-Seismic Gas S/O Valve | 11/30/2021 | SGSOV Approved | COREY HUPP |
Smoke Detectors | 11/30/2021 | Approved | COREY HUPP |
Final | 12/22/2021 | OK to Issue CofO | COREY HUPP |
Green Building Final | 12/22/2021 | Approved | COREY HUPP |
Reinforced Concrete Frame | 12/22/2021 | Approved | COREY HUPP |