448 W 5TH ST 90731

Certificate Information: 448 W 5TH ST 90731

Application / Permit
19010-10000-00742
Plan Check / Job No.
B19LA03668
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
Construct new mixed-use for-rent multi-family building using TOC Tier 1 density bonus to achieve 99 residential units (including 8 extremely low income affordable units) and a 2,000 sf of ground floor commercial space. Construction is to include 5 levels of residential units with Type III-A construction over 3 levels Type IA.
Permit Issued
Issued on 7/29/2021
Issuing Office
Metro
Current Status
Issued on 7/29/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/27/2019 APPLICANT
Assigned to Plan Check Engineer 4/18/2019 ARSALAN SHABESTARI
Corrections Issued 6/7/2019 JOSE RODRIGUEZ
Quality Review Completed 6/27/2019 TIEN JEN WANG
Building Plans Picked Up 6/28/2019 APPLICANT
Applicant returned to address corrections 10/16/2019 JOSE RODRIGUEZ
Applicant returned to address corrections 5/28/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 6/2/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 6/4/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 6/5/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 8/13/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 8/20/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 6/30/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 7/2/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 7/8/2021 ARSALAN SHABESTARI
Plan Check Approved 7/15/2021 ARSALAN SHABESTARI
Issued 7/29/2021 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/11/2019 JEREMY CARTER
Address approval Cleared 1/21/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 1/21/2020 THOMAS LANG
Community Plan Implem. Overlay Cleared 5/13/2020 ERIK BEASLEY
Community Plan Implem. Overlay Cleared 5/18/2020 WALTER RAMIREZ
GPI Written Notices Cleared 5/28/2020 JOSE RODRIGUEZ
Grading Pre-Inspection Cleared 5/28/2020 JOSE RODRIGUEZ
Building over 3-story or 36-ft Cleared 6/2/2020 CALOSHA APPROVED
Highway dedication Cleared 6/15/2020 ERIK BEASLEY
Density Bonus 12.22.A.31 Cleared 7/30/2020 DORIS KWOK
Bicycle Parking Cleared 8/6/2020 ERIK BEASLEY
Community Plan Implem. Overlay Cleared 8/6/2020 FREDDY GARCIA
Community Plan Implem. Overlay Cleared 9/14/2020 JOHN KIM
Trees in Parkway Cleared 9/14/2020 JOHN KIM
Permit Cleared 9/22/2020 ERIK BEASLEY
Encroachment in public way Cleared 9/23/2020 CHINH DINH
DAS Clearance Cleared 9/24/2020 JOSE RODRIGUEZ
Fire Marshall Fire Life Safety Cleared 9/29/2020 MENOA AGHAJANI
"D" conditions Cleared 10/30/2020 JOE LUCKEY
Community Plan Implem. Overlay Cleared 10/30/2020 JOE LUCKEY
Frnt yard landscape/Water mgmt Cleared 10/30/2020 JOE LUCKEY
Miscellaneous Cleared 10/30/2020 JOE LUCKEY
Opn space landscape/Water mgmt Cleared 10/30/2020 JOE LUCKEY
Prkng lot landscape/Water mgmt Cleared 10/30/2020 JOE LUCKEY
Site Plan review Cleared 10/30/2020 JOE LUCKEY
ZI Cleared 10/30/2020 JOE LUCKEY
Low Impact Development Cleared 11/14/2020 ROBIN YAMADA
Project located in CRA area Cleared 11/16/2020 DAVID URITA
Roof/Waste drainage to street Cleared 11/16/2020 YEGANEH SADEGHI
Green Code Cleared 12/28/2020 JOSE RODRIGUEZ
Sewer availability Cleared 4/13/2021 ERIK BEASLEY

Contact Information

Architect Empakeris,, Donatas Eduard; Lic. No.: C13779 DE ARCHITECTS   1535 6TH ST STE 101    SANTA MONICA, CA 90401
Contractor Ark Construction & Development Inc; Lic. No.: 438036-B 15332 ANTIOCH ST #519      PACIFIC PALISADES, CA 90272
Engineer Berliner,, Neal David; Lic. No.: GE2576 4913 MONUMENT ST      SIMI VALLEY, CA 93063
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Larocca,, Francis Joseph; Lic. No.: C75121 1821 PACIFIC COAST HWY 38      HERMOSA BEACH, CA 90254
Engineer Zen,, Petrina; Lic. No.: C87489 944 LINCOLN AVE      POMONA, CA 91767
Landscape Architect Taft,, Robert Emory; Lic. No.: LA3669 36275 AVENIDA DE ACACIAS      TEMECULA, CA 92592

Inspector Information

JOEY BUCHANAN, (310) 732-4553 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 9/8/2021 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 10/22/2021 Not Ready for Inspection JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 11/4/2021 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 11/4/2021 Order to Comply Issued JOEY BUCHANAN
Footing/Foundation/Slab 11/10/2021 Conditional Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 11/23/2021 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 11/23/2021 Partial Approval JOEY BUCHANAN
Structural Steel Frame 12/1/2021 Partial Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 12/2/2021 Not Ready for Inspection JOEY BUCHANAN
Green Building Rough 12/2/2021 Approved JOEY BUCHANAN
Reinforced Concrete Frame 12/2/2021 Not Ready for Inspection JOEY BUCHANAN
Verify Sprinkler Sign Off 12/2/2021 Not Ready for Inspection JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 12/7/2021 Not Ready for Inspection JOEY BUCHANAN
Piling/Pier/Caisson 12/8/2021 Partial Approval JOEY BUCHANAN
Masonry Wall/Backfill 12/13/2021 Partial Approval JOEY BUCHANAN
Reinforced Concrete Frame 12/13/2021 Partial Approval JOEY BUCHANAN
Verify Sprinkler Sign Off 12/13/2021 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 12/20/2021 Partial Approval JOEY BUCHANAN
Piling/Pier/Caisson 12/22/2021 Partial Approval JOEY BUCHANAN
Reinforced Concrete Frame 12/22/2021 Partial Approval JOEY BUCHANAN
Verify Sprinkler Sign Off 12/22/2021 Not Ready for Inspection JOEY BUCHANAN
Masonry Wall/Backfill 1/7/2022 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 1/18/2022 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 1/27/2022 Partial Approval JOEY BUCHANAN
Masonry Wall/Backfill 2/4/2022 Partial Approval JOEY BUCHANAN
Masonry Wall/Backfill 2/7/2022 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 2/8/2022 Not Ready for Inspection DAVID TSAU
Footing/Foundation/Slab 2/8/2022 Partial Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 2/10/2022 Not Ready for Inspection JOEY BUCHANAN
Masonry Wall/Backfill 2/16/2022 Not Ready for Inspection JOEY BUCHANAN
Masonry Wall/Backfill 2/17/2022 Not Ready for Inspection JOEY BUCHANAN
Masonry Wall/Backfill 2/22/2022 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 3/4/2022 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Partial Approval JOEY BUCHANAN
Reinforced Concrete Frame 3/22/2022 Partial Approval JOEY BUCHANAN
Verify Sprinkler Sign Off 3/22/2022 Not Ready for Inspection JOEY BUCHANAN
Reinforced Concrete Frame 3/30/2022 Partial Approval JOEY BUCHANAN
Verify Sprinkler Sign Off 3/30/2022 Approved JOEY BUCHANAN
Masonry Wall/Backfill 4/6/2022 Partial Approval JOEY BUCHANAN
Masonry Wall/Backfill 4/7/2022 Not Ready for Inspection JOEY BUCHANAN
Masonry Wall/Backfill 4/13/2022 Partial Approval JOEY BUCHANAN
Special/Order Compliance 5/9/2022 Approved JOEY BUCHANAN
Reinforced Concrete Frame 5/10/2022 Not Ready for Inspection JOEY BUCHANAN
Reinforced Concrete Frame 5/17/2022 Partial Approval JOEY BUCHANAN
Structural Steel Frame 5/19/2022 Partial Approval JOEY BUCHANAN
Reinforced Concrete Frame 5/23/2022 Partial Inspection DAVID TSAU
Reinforced Masonry Frame 6/1/2022 Partial Approval JOEY BUCHANAN
Deputy Reinf. Masonry 6/3/2022 Approved JOEY BUCHANAN
Reinforced Concrete Frame 7/11/2022 Not Ready for Inspection JOEY BUCHANAN
Structural Steel Frame 7/15/2022 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 7/21/2022 Not Ready for Inspection JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 7/22/2022 Partial Approval JOEY BUCHANAN
Reinforced Concrete Frame 8/5/2022 Partial Inspection DAVID TSAU
Drywall Nailing 8/8/2022 No Access for Inspection DAVID TSAU
Drywall Nailing 8/8/2022 Partial Approval DAVID TSAU
Structural Steel Frame 8/8/2022 Not Ready for Inspection DAVID TSAU
Drywall Nailing 8/10/2022 Partial Approval DAVID TSAU
Wall Anchors 8/10/2022 Not Ready for Inspection DAVID TSAU
Excavation/Setback/Form/Re-Bar 8/18/2022 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 8/18/2022 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Conditional Approval JOEY BUCHANAN
Pre-Inspection 8/25/2022 Partial Approval JOEY BUCHANAN
Deputy Fireproofing 8/31/2022 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Partial Approval JOEY BUCHANAN
Pre-Inspection 8/31/2022 Partial Approval JOEY BUCHANAN
Drywall Nailing 9/9/2022 Partial Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Partial Approval TED RIES
Light Gage Steel Frame 9/9/2022 Partial Approval TED RIES
Pre-Inspection 9/9/2022 Approved TED RIES
Structural Steel Frame 9/9/2022 Partial Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Partial Approval JOEY BUCHANAN
Insulation 9/21/2022 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 9/21/2022 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 9/26/2022 Partial Approval JOEY BUCHANAN
Pre-Inspection 9/26/2022 Approved JOEY BUCHANAN
Pre-Inspection 9/29/2022 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Partial Approval JOEY BUCHANAN
Pre-Inspection 10/14/2022 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Partial Approval JOEY BUCHANAN
Drywall Nailing 10/28/2022 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 10/28/2022 Corrections Issued JOEY BUCHANAN
Deputy Fireproofing 10/31/2022 Approved JOEY BUCHANAN
Light Gage Steel Frame 11/10/2022 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 11/10/2022 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Partial Approval JOEY BUCHANAN
Pre-Inspection 12/8/2022 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Partial Approval JOEY BUCHANAN
Pre-Inspection 12/12/2022 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Corrections Issued JOEY BUCHANAN
Pre-Inspection 12/14/2022 Approved JOEY BUCHANAN
Drywall Nailing 12/16/2022 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Partial Approval JOEY BUCHANAN
Pre-Inspection 12/16/2022 Approved AMANUEL BERHE
Pre-Inspection 12/16/2022 Approved JOEY BUCHANAN
Drywall Nailing 12/19/2022 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Partial Approval JOEY BUCHANAN
Pre-Inspection 12/19/2022 Approved JOEY BUCHANAN
Drywall Nailing 12/28/2022 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 12/28/2022 Partial Approval JOEY BUCHANAN
Pre-Inspection 1/10/2023 Approved JOEY BUCHANAN
Wood Frame 1/10/2023 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 1/13/2023 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 1/13/2023 Approved JOEY BUCHANAN
Pre-Inspection 1/18/2023 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 1/20/2023 Approved JOEY BUCHANAN
Pre-Inspection 1/24/2023 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 1/31/2023 Approved JOEY BUCHANAN
Pre-Inspection 2/2/2023 Approved JOEY BUCHANAN
Insulation 2/3/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 2/3/2023 Approved JOEY BUCHANAN
Insulation 2/7/2023 Corrections Issued JOEY BUCHANAN
Pre-Inspection 2/7/2023 Approved JOEY BUCHANAN
Deputy Wood Construction 2/13/2023 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 2/16/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 2/21/2023 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 2/23/2023 Approved JOEY BUCHANAN
Pre-Inspection 2/23/2023 Corrections Issued JOEY BUCHANAN
Pre-Inspection 2/24/2023 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 2/27/2023 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 2/28/2023 Partial Approval JOEY BUCHANAN
Insulation 3/2/2023 Approved JOEY BUCHANAN
Pre-Inspection 3/2/2023 Partial Approval JOEY BUCHANAN
Wall Anchors 3/2/2023 Approved JOEY BUCHANAN
Pre-Inspection 3/6/2023 Corrections Issued JOEY BUCHANAN
Pre-Inspection 3/7/2023 Partial Approval JOEY BUCHANAN
Wood Frame 3/8/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 3/10/2023 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 3/13/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 3/15/2023 Corrections Issued JOEY BUCHANAN
Pre-Inspection 3/17/2023 Partial Approval JOEY BUCHANAN
Wall Anchors 3/17/2023 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 3/21/2023 Approved JOEY BUCHANAN
Pre-Inspection 3/22/2023 Partial Approval JOEY BUCHANAN
Wall Anchors 3/22/2023 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 3/23/2023 Partial Approval JOEY BUCHANAN
Wall Anchors 3/23/2023 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 3/24/2023 Approved JOEY BUCHANAN
Deputy Wood Construction 3/28/2023 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 3/30/2023 Partial Approval JOEY BUCHANAN
Insulation 4/3/2023 Corrections Issued JOEY BUCHANAN
Pre-Inspection 4/3/2023 Approved JOEY BUCHANAN
Insulation 4/4/2023 Not Ready for Inspection JOEY BUCHANAN
Insulation 4/7/2023 Corrections Issued JOEY BUCHANAN
Pre-Inspection 4/7/2023 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 4/11/2023 Approved JOEY BUCHANAN
Drywall Nailing 4/13/2023 Corrections Issued JOEY BUCHANAN
Pre-Inspection 4/13/2023 Approved JOEY BUCHANAN
Insulation 4/17/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 4/17/2023 Approved JOEY BUCHANAN
Insulation 4/18/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 4/18/2023 Approved JOEY BUCHANAN
Pre-Inspection 4/20/2023 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 4/24/2023 Partial Approval JOEY BUCHANAN
Insulation 4/25/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 4/28/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 5/1/2023 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 5/3/2023 Approved JOEY BUCHANAN
Pre-Inspection 5/4/2023 Partial Approval JOEY BUCHANAN
Insulation 5/12/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 5/12/2023 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 5/17/2023 Approved JOEY BUCHANAN
Pre-Inspection 5/17/2023 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 5/19/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 5/22/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 5/25/2023 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 5/26/2023 Approved JOEY BUCHANAN
Insulation 5/30/2023 Not Ready for Inspection JOEY BUCHANAN
Insulation 5/31/2023 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 6/6/2023 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Partial Approval JOEY BUCHANAN
Insulation 6/7/2023 Not Ready for Inspection JOEY BUCHANAN
Insulation 6/12/2023 Order to Comply Issued JOEY BUCHANAN
Insulation 6/16/2023 Not Ready for Inspection JOEY BUCHANAN
Insulation 6/21/2023 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 6/26/2023 Partial Inspection AMANUEL BERHE
Pre-Inspection 6/29/2023 Conditional Approval JOEY BUCHANAN
Drywall Nailing 6/30/2023 Not Ready for Inspection AMANUEL BERHE
Drywall Nailing 7/3/2023 Partial Inspection AMANUEL BERHE
Drywall Nailing 7/5/2023 Partial Inspection AMANUEL BERHE
Drywall Nailing 7/6/2023 Partial Inspection AMANUEL BERHE
Insulation 7/6/2023 Not Ready for Inspection AMANUEL BERHE
Drywall Nailing 7/7/2023 Partial Inspection AMANUEL BERHE
Drywall Nailing 7/10/2023 Partial Approval DAVID TSAU
Insulation 7/14/2023 Partial Approval DAVID TSAU
Drywall Nailing 7/18/2023 Partial Approval JOEY BUCHANAN
Drywall Nailing 7/21/2023 Partial Approval JOEY BUCHANAN
Insulation 7/21/2023 Partial Approval JOEY BUCHANAN
Drywall Nailing 7/25/2023 Partial Approval JOEY BUCHANAN
Insulation 7/28/2023 Order to Comply Issued JOEY BUCHANAN
Light Gage Steel Frame 8/4/2023 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 8/11/2023 Partial Approval JOEY BUCHANAN
Insulation 8/18/2023 Corrections Issued JOEY BUCHANAN
Deputy Steel/Welding 8/23/2023 Approved JOEY BUCHANAN
Special/Order Compliance 8/23/2023 Approved AMANUEL BERHE
Deputy Steel/Welding 8/25/2023 Conditional Approval AMANUEL BERHE
Drywall Nailing 8/25/2023 Not Ready for Inspection AMANUEL BERHE
Insulation 8/25/2023 Conditional Approval AMANUEL BERHE
Deputy Steel/Welding 8/28/2023 Approved JOEY BUCHANAN
Drywall Nailing 8/29/2023 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 8/29/2023 Not Ready for Inspection JOEY BUCHANAN
Deputy Reinf. Concrete 9/5/2023 Conditional Approval AMANUEL BERHE
Insulation 9/7/2023 Partial Inspection AMANUEL BERHE
Insulation 9/8/2023 Not Ready for Inspection AMANUEL BERHE
Insulation 9/11/2023 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 9/13/2023 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 9/13/2023 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 9/13/2023 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 9/15/2023 Approved JOEY BUCHANAN
Drywall Nailing 9/18/2023 Partial Inspection AMANUEL BERHE
Insulation 9/18/2023 Not Ready for Inspection AMANUEL BERHE
Light Gage Steel Frame 9/18/2023 Not Ready for Inspection AMANUEL BERHE
Drywall Nailing 9/20/2023 Corrections Issued JOEY BUCHANAN
Drywall Nailing 9/25/2023 Not Ready for Inspection JOEY BUCHANAN
Interior/Exterior Lathing 9/25/2023 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 9/25/2023 Not Ready for Inspection JOEY BUCHANAN
Drywall Nailing 9/26/2023 Not Ready for Inspection JOEY BUCHANAN
Insulation 9/26/2023 Not Ready for Inspection JOEY BUCHANAN
Interior/Exterior Lathing 9/26/2023 Not Ready for Inspection JOEY BUCHANAN
Insulation 9/28/2023 Partial Approval AMANUEL BERHE
Insulation 10/2/2023 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 10/3/2023 Approved JOEY BUCHANAN
Drywall Nailing 10/5/2023 Not Ready for Inspection JOEY BUCHANAN
Insulation 10/5/2023 Partial Approval JOEY BUCHANAN
Insulation 10/12/2023 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 10/20/2023 Approved JOEY BUCHANAN
Drywall Nailing 10/20/2023 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 10/26/2023 Partial Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 10/31/2023 Partial Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 11/6/2023 Approved JOEY BUCHANAN
Reinforced Concrete Frame 11/6/2023 Approved JOEY BUCHANAN
Wood Frame 11/9/2023 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 11/14/2023 Not Ready for Inspection JOEY BUCHANAN
Deputy Reinf. Masonry 11/17/2023 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 11/29/2023 Corrections Issued JOEY BUCHANAN
Pre-Inspection 12/13/2023 Not Ready for Inspection JOEY BUCHANAN
Interior/Exterior Lathing 12/15/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 12/15/2023 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 12/22/2023 Partial Inspection AMANUEL BERHE
Insulation 1/3/2024 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 1/3/2024 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 1/5/2024 Partial Approval JOEY BUCHANAN
Drywall Nailing 1/18/2024 Partial Approval JOEY BUCHANAN
Special/Order Compliance 1/18/2024 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 2/1/2024 Partial Approval JOEY BUCHANAN
Special/Order Compliance 2/1/2024 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 2/27/2024 Partial Approval JOEY BUCHANAN
Special/Order Compliance 2/27/2024 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 3/5/2024 Partial Approval JOEY BUCHANAN
Special/Order Compliance 3/7/2024 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 3/14/2024 Approved JOEY BUCHANAN
Deputy Steel/Welding 3/18/2024 Approved JOEY BUCHANAN
Drywall Nailing 4/5/2024 Partial Approval AMANUEL BERHE
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Not Ready for Inspection JOEY BUCHANAN
Light Gage Steel Frame 4/26/2024 Partial Approval JOEY BUCHANAN
Drywall Nailing 5/20/2024 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 7/12/2024 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 11/19/2024 Approved JOEY BUCHANAN
Special/Order Compliance 2/3/2025 Corrections Issued JOEY BUCHANAN