Pre-Inspection
|
12/9/2020
|
Approved
|
JAMES POWERS
|
Reinforced Concrete Frame
|
12/15/2020
|
Not Ready for Inspection
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
12/16/2020
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
12/17/2020
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
1/7/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
1/8/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
1/11/2021
|
Partial Approval
|
JAMES POWERS
|
Footing/Foundation/Slab
|
1/12/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
1/22/2021
|
Partial Approval
|
JAMES POWERS
|
Masonry Wall/Backfill
|
3/1/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
3/2/2021
|
Partial Approval
|
JAMES POWERS
|
Masonry Wall/Backfill
|
3/3/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
3/4/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
3/5/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
3/8/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
3/9/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
3/10/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
3/11/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
3/12/2021
|
Partial Approval
|
JAMES POWERS
|
Reinforced Concrete Frame
|
3/12/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
3/15/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
3/16/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Steel/Welding
|
3/18/2021
|
Conditional Approval
|
NICK DANERI
|
Deputy Steel/Welding
|
3/19/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Steel/Welding
|
3/23/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
3/24/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Steel/Welding
|
3/30/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Steel/Welding
|
4/6/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Steel/Welding
|
4/7/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Steel/Welding
|
4/8/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Steel/Welding
|
4/9/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Other (see comments)
|
4/12/2021
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
4/15/2021
|
Partial Approval
|
JAMES POWERS
|
Drywall Nailing
|
4/22/2021
|
Partial Approval
|
JONATHAN QUACH
|
Floor/Roof Diaphrgm/Shear Wall
|
4/22/2021
|
Partial Approval
|
JONATHAN QUACH
|
Deputy Reinf. Concrete
|
4/23/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
Insulation
|
5/14/2021
|
Partial Approval
|
JAMES POWERS
|
Interior/Exterior Lathing
|
5/14/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
5/20/2021
|
Partial Approval
|
JAMES POWERS
|
Footing/Foundation/Slab
|
5/20/2021
|
Partial Approval
|
JAMES POWERS
|
Light Gage Steel Frame
|
5/20/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
5/24/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Masonry
|
5/25/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Masonry
|
5/26/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Masonry
|
5/27/2021
|
Partial Approval
|
JAMES POWERS
|
Reinforced Masonry Frame
|
5/28/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
6/2/2021
|
Partial Approval
|
JAMES POWERS
|
Drywall Nailing
|
6/2/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
6/3/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
6/4/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
6/7/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
6/8/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Steel/Welding
|
6/9/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Steel/Welding
|
6/10/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/11/2021
|
Partial Approval
|
JAMES POWERS
|
Masonry Wall/Backfill
|
6/11/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/14/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/15/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/16/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/17/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/18/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/21/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/22/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/23/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/24/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/25/2021
|
Conditional Approval
|
LEOPOLDO MENDOZA
|
Deputy Fireproofing
|
6/28/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/29/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
6/30/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/1/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/6/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/7/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/8/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/9/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/12/2021
|
Conditional Approval
|
DAVID TSAU
|
Deputy Fireproofing
|
7/13/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/14/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/15/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/16/2021
|
Approved
|
JOEY BUCHANAN
|
Deputy Fireproofing
|
7/19/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/20/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/21/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/22/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/23/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/26/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/27/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/28/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/29/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Fireproofing
|
7/30/2021
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
8/4/2021
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
8/16/2021
|
Partial Approval
|
JAMES POWERS
|
Drywall Nailing
|
8/23/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Wood Construction
|
8/25/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
8/27/2021
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
8/27/2021
|
Partial Approval
|
JAMES POWERS
|
Green Building Rough
|
8/27/2021
|
Approved
|
JAMES POWERS
|
Verify Sprinkler Sign Off
|
8/27/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
Light Gage Steel Frame
|
8/31/2021
|
Partial Approval
|
JAMES POWERS
|
Wood Frame
|
8/31/2021
|
Partial Approval
|
JAMES POWERS
|
Drywall Nailing
|
9/8/2021
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
9/8/2021
|
Partial Approval
|
JAMES POWERS
|
Deputy Drilled-In Anchors
|
9/10/2021
|
Partial Approval
|
JAMES POWERS
|
Footing/Foundation/Slab
|
9/13/2021
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
9/13/2021
|
Partial Approval
|
JAMES POWERS
|
Interior/Exterior Lathing
|
9/13/2021
|
Partial Approval
|
JAMES POWERS
|
Drywall Nailing
|
9/28/2021
|
Not Ready for Inspection
|
JAMES POWERS
|
Insulation
|
9/28/2021
|
Partial Approval
|
JAMES POWERS
|
Special/Order Compliance
|
9/30/2021
|
Not Ready for Inspection
|
JONATHAN QUACH
|
Special/Order Compliance
|
10/1/2021
|
Partial Approval
|
JONATHAN QUACH
|
Drywall Nailing
|
10/4/2021
|
Partial Approval
|
JAMES POWERS
|
T-Bar Ceiling
|
1/11/2022
|
Approved
|
JAMES POWERS
|
Special/Order Compliance
|
1/24/2022
|
Partial Approval
|
JAMES POWERS
|
Pre-Inspection
|
1/30/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
Final
|
4/19/2023
|
Partial Inspection
|
GREGORY POMISH
|
Footing/Foundation/Slab
|
4/19/2023
|
Approved
|
GREGORY POMISH
|
Green Building Final
|
4/19/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
SGSOV-Seismic Gas S/O Valve
|
4/19/2023
|
SGSOV Approved
|
GREGORY POMISH
|
Smoke Detectors
|
4/19/2023
|
Approved
|
GREGORY POMISH
|
Verify Sprinkler Sign Off
|
4/19/2023
|
Approved
|
GREGORY POMISH
|
Wood Frame
|
4/19/2023
|
Approved
|
GREGORY POMISH
|
Final
|
6/5/2023
|
OK to Issue CofO
|
JAMES POWERS
|
Green Building Final
|
6/5/2023
|
Approved
|
JAMES POWERS
|