710 N VIRGIL AVE 90029

Certificate Information: 710 N VIRGIL AVE 90029

Application / Permit
19010-10000-05729
Plan Check / Job No.
B19LA26486
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
Proposed mixed-use building with 37 apartment units, over one story retail, over 2 subterranian parking levels.
Permit Issued
Issued on 5/17/2022
Issuing Office
Metro
Current Status
Issued on 5/17/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 JOE VO
Corrections Issued 1/13/2020 JOE VO
Quality Review Completed 1/16/2020 KEN GILL
Building Plans Picked Up 1/27/2020 APPLICANT
Disabled Access Plans Picked Up 1/27/2020 APPLICANT
Applicant returned to address corrections 6/15/2020 JOE VO
Applicant returned to address corrections 8/11/2020 JOE VO
Green Plans Picked Up 12/7/2020 APPLICANT
Applicant returned to address corrections 1/11/2021 JOE VO
Applicant returned to address corrections 1/19/2021 JOE VO
Plan Check Approved 4/20/2021 JOE VO
Plan Check Approved 6/22/2021 JOE VO
Issued 5/17/2022 APPLICANT

Permit Application Clearance Information

DAS Clearance Cleared 6/25/2020 WAI LAU
Driveway location Cleared 7/14/2020 PETE EYRE
Green Code Cleared 7/15/2020 NEGAR NEJAD
Eng Process Fee Ord 176,300 Cleared 7/16/2020 CECILIO NAVARRO
Building over 3-story or 36-ft Cleared 7/19/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 7/19/2020 CALOSHA APPROVED
ZA Case Cleared 7/22/2020 RUBEN VASQUEZ
ZA Case Cleared 7/22/2020 RUBEN VASQUEZ
Hydrant and Access approval Cleared 9/1/2020 MATTHEW CRAIG
Excavation more than 5-ft deep Cleared 9/18/2020 CALOSHA APPROVED
Fire Marshall Fire Life Safety Cleared 9/23/2020 DOMINIQUE MEDINA
Highway dedication Cleared 10/15/2020 CELINA MORENO
Low Impact Development Cleared 11/5/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/17/2020 ROSA SILVA
Permit Cleared 11/25/2020 CECILIO NAVARRO
Density Bonus 12.22.A.31 Cleared 12/2/2020 NICHOLAS KAWAZOE
Sewer availability Cleared 12/4/2020 CECILIO NAVARRO
"D" conditions Cleared 12/23/2020 KENTON TRINH
Opn space landscape/Water mgmt Cleared 12/23/2020 KENTON TRINH
Specific Plan Cleared 12/23/2020 KENTON TRINH
ZI Cleared 12/23/2020 KENTON TRINH
Miscellaneous Cleared 1/25/2021 JOE VO
Address approval Cleared 1/27/2021 CECILIO NAVARRO
Haul Route Cleared 2/9/2021 JOE VO
Work Adjacent to Public Way Cleared 3/3/2021 JOSE RODRIGUEZ

Contact Information

Architect Tsai,, Kuo-Huei; Lic. No.: C33710 834 S BROADWAY SUITE 1206      LOS ANGELES, CA 90014
Contractor Owner-Builder       ,
Engineer Berliner,, Neal David; Lic. No.: GE2576 4913 MONUMENT ST      SIMI VALLEY, CA 93063
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Zen,, Petrina; Lic. No.: C87489 944 LINCOLN AVE      POMONA, CA 91767

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/18/2022 Approved TED RIES
Deputy Grading 9/12/2022 Conditional Approval TED RIES
Special/Order Compliance 3/14/2023 Not Ready for Inspection TED RIES
Special/Order Compliance 4/4/2023 Approved TED RIES
Deputy Steel/Welding 5/1/2023 Conditional Approval MICHAEL ROSENBERG
Posting Pre-Inspection 8/18/2023 Partial Inspection TIMOTHY POWELL
Footing/Foundation/Slab 10/17/2023 Partial Inspection DAVID BURKHEAD
Pre-Inspection 11/7/2023 Approved DAVID BURKHEAD
Footing/Foundation/Slab 12/8/2023 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 12/9/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 12/9/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 1/8/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 1/8/2024 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 1/8/2024 Not Ready for Inspection LARRY ARNICK
Deputy Drilled-In Anchors 1/10/2024 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/10/2024 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/10/2024 Partial Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 1/17/2024 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/17/2024 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/17/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/18/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 1/30/2024 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/30/2024 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 2/9/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 2/13/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 2/13/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 2/16/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 2/29/2024 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 3/4/2024 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 3/5/2024 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 3/5/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 3/6/2024 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 3/6/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 3/11/2024 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 3/11/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 3/12/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 3/12/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/13/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/14/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 3/15/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 3/15/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/18/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 3/21/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 3/22/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 3/27/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 4/29/2024 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 5/1/2024 Corrections Issued JEFFREY FULTON
Deputy Reinf. Concrete 5/3/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 5/3/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 5/7/2024 Partial Approval MARTIN TAVITIAN
Green Building Rough 8/23/2024 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 8/23/2024 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 8/23/2024 Corrections Issued JEFFREY FULTON
Verify Sprinkler Sign Off 8/23/2024 Not Ready for Inspection JEFFREY FULTON
Masonry Wall/Backfill 8/26/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 8/29/2024 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 8/29/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/19/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 9/20/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/20/2024 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/20/2024 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 9/20/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 10/8/2024 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 10/8/2024 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/18/2024 Partial Inspection JEFFREY FULTON
Special/Order Compliance 10/21/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 10/22/2024 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 10/22/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 10/22/2024 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 11/7/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 11/18/2024 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 12/5/2024 Partial Approval JAMES POWERS