412 S EUCLID AVE 90063
Certificate Information: 412 S EUCLID AVE 90063
- Application / Permit
- 19014-10000-04401
- Plan Check / Job No.
- B19LA16940
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION TO 2ND FLOOR, REMODEL (E) SFD, NEW DECK
- Permit Issued
- Issued on 10/28/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 8/13/2019 | APPLICANT |
Assigned to Plan Check Engineer | 8/29/2019 | ADAM HEGAZI |
Corrections Issued | 9/4/2019 | ADAM HEGAZI |
Quality Review Completed | 9/22/2019 | YOUNG KIM |
Building Plans Picked Up | 9/24/2019 | APPLICANT |
Green Plans Picked Up | 9/24/2019 | APPLICANT |
Plan Check Approved | 10/11/2019 | ADAM HEGAZI |
Issued | 10/28/2019 | LADBS |
CofO in Progress | 9/14/2021 | ROBERT VORHIS |
Permit Finaled | 10/2/2021 | DEROLD HAUFF |
CofO Issued | 10/2/2021 | DEROLD HAUFF |
Permit Finaled | 10/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
Clean Up Green Up | Cleared | 10/3/2019 | RICHARD REASER |
Eng Process Fee Ord 176,300 | Cleared | 10/8/2019 | ERIK BEASLEY |
Project located in CRA area | Cleared | 10/8/2019 | JIM URQUHART |
Roof/Waste drainage to street | Cleared | 10/8/2019 | ERIK BEASLEY |
Green Code | Cleared | 10/9/2019 | KHEDER ALRAZAA |
Contact Information
Contractor | Padilla Construction; Lic. No.: 884874-B | 9725 ORIZABA AVENUE DOWNEY, CA 90240 |
Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 1/27/2020 | Corrections Issued | ROBERT CORNELL |
METHANE-Barrier | 1/27/2020 | Approved | ROBERT CORNELL |
METHANE-Subgrade | 1/27/2020 | Approved | ROBERT CORNELL |
Footing/Foundation/Slab | 1/31/2020 | Approved | ROBERT CORNELL |
ELECTRICAL-Rough | 5/21/2020 | Partial Inspection | ROBERT VORHIS |
Floor/Roof Diaphrgm/Shear Wall | 5/21/2020 | Partial Inspection | ROBERT VORHIS |
PLUMBING-Rough | 5/21/2020 | Partial Inspection | ROBERT VORHIS |
Wood Frame | 5/21/2020 | Corrections Issued | ROBERT VORHIS |
Pre-Inspection | 5/27/2020 | Partial Inspection | ROBERT VORHIS |
BUILDING-Rough-Frame | 7/15/2020 | Corrections Issued | RUBEN SALAS |
ELECTRICAL-Rough | 7/15/2020 | Not Ready for Inspection | RUBEN SALAS |
Floor/Roof Diaphrgm/Shear Wall | 7/15/2020 | Corrections Issued | RUBEN SALAS |
Gas Test | 7/15/2020 | Corrections Issued | RUBEN SALAS |
Green Building Rough | 7/15/2020 | Not Ready for Inspection | RUBEN SALAS |
METHANE-Rough | 7/15/2020 | Not Ready for Inspection | RUBEN SALAS |
PLUMBING-Rough | 7/15/2020 | Not Ready for Inspection | RUBEN SALAS |
ELECTRICAL-Rough | 8/3/2020 | Approved | ROBERT VORHIS |
Floor/Roof Diaphrgm/Shear Wall | 8/3/2020 | Approved | ROBERT VORHIS |
PLUMBING-Rough | 8/3/2020 | Approved | ROBERT VORHIS |
BUILDING-Rough-Frame | 8/20/2020 | Approved | ROBERT VORHIS |
Green Building Rough | 8/20/2020 | Approved | ROBERT VORHIS |
Interior/Exterior Lathing | 8/20/2020 | Partial Approval | ROBERT VORHIS |
METHANE-Rough | 8/20/2020 | Approved | ROBERT VORHIS |
Insulation | 8/25/2020 | Approved | DAVID MATSON |
Drywall Nailing | 9/4/2020 | Approved | DONALD CRICHLOW |
Interior/Exterior Lathing | 9/4/2020 | Approved | DONALD CRICHLOW |
ELECTRICAL-Final | 7/27/2021 | Approved | ROBERT VORHIS |
Final | 7/27/2021 | Corrections Issued | ROBERT VORHIS |
Gas Test | 7/27/2021 | Approved | ROBERT VORHIS |
HVAC-Final | 7/27/2021 | Approved | ROBERT VORHIS |
PLUMBING-Final | 7/27/2021 | Approved | ROBERT VORHIS |
Smoke Detectors | 7/27/2021 | Approved | ROBERT VORHIS |
Final | 8/3/2021 | Partial Inspection | OSVALDO PARAMO |
Green Building Final | 8/3/2021 | Approved | OSVALDO PARAMO |
SGSOV-Seismic Gas S/O Valve | 8/3/2021 | SGSOV Approved | OSVALDO PARAMO |
Final | 8/30/2021 | Corrections Issued | JOAQUIN GREENOUGH |
Final | 9/13/2021 | Conditional Approval | ROBERT VORHIS |