412 S EUCLID AVE 90063

Certificate Information: 412 S EUCLID AVE 90063

Application / Permit
19014-10000-04401
Plan Check / Job No.
B19LA16940
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION TO 2ND FLOOR, REMODEL (E) SFD, NEW DECK
Permit Issued
Issued on 10/28/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 ADAM HEGAZI
Corrections Issued 9/4/2019 ADAM HEGAZI
Quality Review Completed 9/22/2019 YOUNG KIM
Building Plans Picked Up 9/24/2019 APPLICANT
Green Plans Picked Up 9/24/2019 APPLICANT
Plan Check Approved 10/11/2019 ADAM HEGAZI
Issued 10/28/2019 LADBS
CofO in Progress 9/14/2021 ROBERT VORHIS
Permit Finaled 10/2/2021 DEROLD HAUFF
CofO Issued 10/2/2021 DEROLD HAUFF
Permit Finaled 10/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Clean Up Green Up Cleared 10/3/2019 RICHARD REASER
Eng Process Fee Ord 176,300 Cleared 10/8/2019 ERIK BEASLEY
Project located in CRA area Cleared 10/8/2019 JIM URQUHART
Roof/Waste drainage to street Cleared 10/8/2019 ERIK BEASLEY
Green Code Cleared 10/9/2019 KHEDER ALRAZAA

Contact Information

Contractor Padilla Construction; Lic. No.: 884874-B 9725 ORIZABA AVENUE      DOWNEY, CA 90240
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/27/2020 Corrections Issued ROBERT CORNELL
METHANE-Barrier 1/27/2020 Approved ROBERT CORNELL
METHANE-Subgrade 1/27/2020 Approved ROBERT CORNELL
Footing/Foundation/Slab 1/31/2020 Approved ROBERT CORNELL
ELECTRICAL-Rough 5/21/2020 Partial Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 5/21/2020 Partial Inspection ROBERT VORHIS
PLUMBING-Rough 5/21/2020 Partial Inspection ROBERT VORHIS
Wood Frame 5/21/2020 Corrections Issued ROBERT VORHIS
Pre-Inspection 5/27/2020 Partial Inspection ROBERT VORHIS
BUILDING-Rough-Frame 7/15/2020 Corrections Issued RUBEN SALAS
ELECTRICAL-Rough 7/15/2020 Not Ready for Inspection RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 7/15/2020 Corrections Issued RUBEN SALAS
Gas Test 7/15/2020 Corrections Issued RUBEN SALAS
Green Building Rough 7/15/2020 Not Ready for Inspection RUBEN SALAS
METHANE-Rough 7/15/2020 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 7/15/2020 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Rough 8/3/2020 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 8/3/2020 Approved ROBERT VORHIS
PLUMBING-Rough 8/3/2020 Approved ROBERT VORHIS
BUILDING-Rough-Frame 8/20/2020 Approved ROBERT VORHIS
Green Building Rough 8/20/2020 Approved ROBERT VORHIS
Interior/Exterior Lathing 8/20/2020 Partial Approval ROBERT VORHIS
METHANE-Rough 8/20/2020 Approved ROBERT VORHIS
Insulation 8/25/2020 Approved DAVID MATSON
Drywall Nailing 9/4/2020 Approved DONALD CRICHLOW
Interior/Exterior Lathing 9/4/2020 Approved DONALD CRICHLOW
ELECTRICAL-Final 7/27/2021 Approved ROBERT VORHIS
Final 7/27/2021 Corrections Issued ROBERT VORHIS
Gas Test 7/27/2021 Approved ROBERT VORHIS
HVAC-Final 7/27/2021 Approved ROBERT VORHIS
PLUMBING-Final 7/27/2021 Approved ROBERT VORHIS
Smoke Detectors 7/27/2021 Approved ROBERT VORHIS
Final 8/3/2021 Partial Inspection OSVALDO PARAMO
Green Building Final 8/3/2021 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/3/2021 SGSOV Approved OSVALDO PARAMO
Final 8/30/2021 Corrections Issued JOAQUIN GREENOUGH
Final 9/13/2021 Conditional Approval ROBERT VORHIS