24515 S BROAD AVE 90744

Certificate Information: 24515 S BROAD AVE 90744

Application / Permit
19014-70000-03384
Plan Check / Job No.
B19SL00802
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ONE STORY ADDITION TO (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL
Permit Issued
Issued on 6/24/2020
Issuing Office
Current Status
Issued on 6/24/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/24/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 LUKE GONZALES
Corrections Issued 7/3/2019 LUKE GONZALES
Quality Review Completed 7/5/2019 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 7/10/2019 APPLICANT
Green Plans Picked Up 7/16/2019 APPLICANT
Plan Check Approved 10/23/2019 LUKE GONZALES
Issued 6/24/2020 APPLICANT

Permit Application Clearance Information

Green Code Cleared 8/23/2019 KHEDER ALRAZAA
Low Impact Development Cleared 8/26/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/26/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/27/2019 PHILLIP WILSON

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/1/2020 Approved JOHN KLARIN
Footing/Foundation/Slab 7/1/2020 Approved JOHN KLARIN
METHANE-Barrier 7/1/2020 Approved JOHN KLARIN
METHANE-Subgrade 7/1/2020 Approved JOHN KLARIN
Insulation 7/8/2020 Partial Inspection JOHN KLARIN
PLUMBING-Rough 7/8/2020 Partial Inspection JOHN KLARIN
ELECTRICAL-Rough 7/13/2020 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/13/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 7/13/2020 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 7/13/2020 Not Ready for Inspection EUGENE CASSIDY
Insulation 7/15/2020 Not Ready for Inspection JOHN KLARIN
Wood Frame 7/15/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 7/20/2020 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 7/20/2020 Approved JOHN KLARIN
Green Building Rough 7/20/2020 Approved JOHN KLARIN
Insulation 7/20/2020 Approved JOHN KLARIN
METHANE-Rough 7/20/2020 Approved JOHN KLARIN
Drywall Nailing 7/22/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 7/22/2020 Approved JOHN KLARIN
Shower Pan 7/22/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 7/24/2020 Approved JOHN KLARIN
Service/Power Release 8/17/2020 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 9/25/2020 Not Ready for Inspection JOHN KLARIN
Final 9/25/2020 Not Ready for Inspection JOHN KLARIN
Green Building Final 9/25/2020 Not Ready for Inspection JOHN KLARIN
HVAC-Final 9/25/2020 Not Ready for Inspection JOHN KLARIN
PLUMBING-Final 9/25/2020 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 9/25/2020 SGSOV Not Ready JOHN KLARIN
Smoke Detectors 9/25/2020 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 10/29/2020 Approved JOHN KLARIN
Final 10/29/2020 Corrections Issued JOHN KLARIN
Green Building Final 10/29/2020 Approved JOHN KLARIN
HVAC-Final 10/29/2020 Approved JOHN KLARIN
PLUMBING-Final 10/29/2020 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 10/29/2020 SGSOV Approved JOHN KLARIN
Smoke Detectors 10/29/2020 Approved JOHN KLARIN