3434 W 6TH ST 90020
Certificate Information: 3434 W 6TH ST 90020
- Application / Permit
- 19016-10000-40332
- Plan Check / Job No.
- B19LA26638
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- NEW PARKING GARAGE COMMERCIAL ADDITION & CHANGE OF USE TO HOTEL. NEW OFFSITE PARKING. CHANGE OF USE FROM 1ST FLOOR PARKING TO RESTAURANTS WITH COVERED OUTDOOR PATIO & HOTEL LOBBY. CHANGE OF USE FROM 2ND FLOOR OFFICE TO HOTEL/OUTDOOR BAR & ROOF DECK. CHANGE OF USE FROM 3RD/4TH FLOORS OFFICE TO HOTEL. CORE & SHELL PERMIT ONLY FOR RESTAURANT - TENANT IMPROVEMENT FOR RESTAURANT UNDER SEPARATE PERMIT.
- Permit Issued
- Issued on 12/5/2022
- Issuing Office
- Metro
- Current Status
- Issued on 12/5/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
Submitted | 12/18/2019 | APPLICANT |
Assigned to Plan Check Engineer | 12/24/2019 | PRANITA SHAH |
Disabled Access Plans Picked Up | 1/10/2020 | APPLICANT |
Corrections Issued | 1/16/2020 | PRANITA SHAH |
Quality Review Completed | 1/28/2020 | TU HUA |
Building Plans Picked Up | 2/18/2020 | APPLICANT |
Applicant returned to address corrections | 7/16/2020 | PRANITA SHAH |
Applicant returned to address corrections | 7/23/2020 | PRANITA SHAH |
Green Plans Picked Up | 3/26/2021 | APPLICANT |
Applicant returned to address corrections | 9/8/2022 | PRANITA SHAH |
Plan Check Approved | 9/9/2022 | PRANITA SHAH |
Issued | 12/5/2022 | APPLICANT |
Permit Application Clearance Information
Address approval | Cleared | 6/10/2021 | WALLIE JONG |
Permit | Cleared | 6/10/2021 | WALLIE JONG |
Bicycle Parking | Cleared | 6/18/2021 | JEREMY CHOK |
Driveway location | Cleared | 7/16/2021 | EDUARDO HERMOSO |
Internal circulation | Cleared | 7/16/2021 | EDUARDO HERMOSO |
Eng Process Fee Ord 176,300 | Cleared | 7/19/2021 | WALLIE JONG |
Fire Marshall Fire Life Safety | Cleared | 9/2/2021 | WILLIAM JOHNS |
Sewer availability | Cleared | 9/27/2021 | WALLIE JONG |
Green Code | Cleared | 10/6/2021 | VIVIAN LAO |
Trees in Parkway | Cleared | 10/9/2021 | ADALBERTO VERA |
Flood clearance | Cleared | 10/12/2021 | BRYAN GATHUKA |
Highway dedication | Cleared | 3/21/2022 | WALLIE JONG |
Food Service Establishment | Cleared | 4/20/2022 | PAWAN VERMA |
Low Impact Development | Cleared | 5/31/2022 | JORGE MEJIA LEMUS |
Roof/Waste drainage to street | Cleared | 6/2/2022 | TREVOR QUAN |
DAS Clearance | Cleared | 6/6/2022 | SOMKIAT SUPANYACHOTSKUL |
Comm Cor/Mini-Mall | Cleared | 7/20/2022 | DALIA MOKAYED |
Comm Cor/Mini-Mall | Cleared | 7/20/2022 | DALIA MOKAYED |
Comm Cor/Mini-Mall | Cleared | 7/20/2022 | DALIA MOKAYED |
Miscellaneous | Cleared | 7/20/2022 | DALIA MOKAYED |
ZA Case | Cleared | 7/20/2022 | DALIA MOKAYED |
ZA Case | Cleared | 7/20/2022 | DALIA MOKAYED |
Redevelopment Project Area | Cleared | 7/26/2022 | DAVID URITA |
Contact Information
Architect | Lee,, Myung-Jong; Lic. No.: C34188 | 1808 BORREGO DR WEST COVINA, CA 91791 |
Contractor | Duk J Corporation; Lic. No.: 862299-B | 3470 WILSHIRE BLVD STE 9301N LOS ANGELES, CA 90010 |
Engineer | Ha,, Seungil; Lic. No.: S4164 | 3454 W 1ST ST LOS ANGELES, CA 90004 |
Inspector Information
TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
JONATHAN QUACH, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
JOHN YAKUBYAN, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
RONALD JIMENEZ, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 12/13/2022 | Approved | JONATHAN QUACH |
Deputy Drilled-In Anchors | 7/10/2023 | Conditional Approval | RONALD JIMENEZ |
Pre-Inspection | 7/11/2023 | Partial Inspection | MARTIN TAVITIAN |
Drywall Nailing | 7/20/2023 | Partial Approval | MARTIN TAVITIAN |
Light Gage Steel Frame | 8/1/2023 | Partial Approval | MARTIN TAVITIAN |
Deputy Methane Barrier | 9/5/2023 | Conditional Approval | RONALD JIMENEZ |
Deputy Methane Barrier | 9/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
Deputy Methane Barrier | 9/15/2023 | Conditional Approval | TIMOTHY POWELL |
Deputy Drilled-In Anchors | 9/21/2023 | Conditional Approval | TIMOTHY POWELL |
Footing/Foundation/Slab | 9/26/2023 | Partial Approval | TIMOTHY POWELL |
METHANE-Barrier | 9/26/2023 | Partial Inspection | TIMOTHY POWELL |
METHANE-Subgrade | 9/26/2023 | Partial Inspection | TIMOTHY POWELL |
Light Gage Steel Frame | 10/16/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
Light Gage Steel Frame | 10/17/2023 | Partial Approval | ALFREDO LOPEZ |
Footing/Foundation/Slab | 10/24/2023 | Not Ready for Inspection | DARRYL ARNOLD |
METHANE-Barrier | 10/24/2023 | Conditional Approval | DARRYL ARNOLD |
METHANE-Subgrade | 10/24/2023 | Conditional Approval | DARRYL ARNOLD |
Deputy Drilled-In Anchors | 11/2/2023 | Conditional Approval | MICHAEL ROSENBERG |
Footing/Foundation/Slab | 11/13/2023 | Partial Approval | MARTIN TAVITIAN |
Insulation | 11/13/2023 | Partial Approval | MARTIN TAVITIAN |
Light Gage Steel Frame | 11/13/2023 | Partial Approval | MARTIN TAVITIAN |
METHANE-Barrier | 11/13/2023 | Approved | MARTIN TAVITIAN |
METHANE-Subgrade | 11/13/2023 | Approved | MARTIN TAVITIAN |
Drywall Nailing | 11/27/2023 | Partial Approval | RONALD JIMENEZ |
Insulation | 11/27/2023 | Partial Approval | RONALD JIMENEZ |
Light Gage Steel Frame | 11/27/2023 | Partial Inspection | RONALD JIMENEZ |
Footing/Foundation/Slab | 11/28/2023 | Partial Approval | MARTIN TAVITIAN |
Footing/Foundation/Slab | 12/4/2023 | Partial Approval | RONALD JIMENEZ |
Light Gage Steel Frame | 12/4/2023 | Partial Approval | RONALD JIMENEZ |
Deputy Drilled-In Anchors | 12/7/2023 | Conditional Approval | RONALD JIMENEZ |
Deputy Steel/Welding | 12/12/2023 | Partial Approval | MARTIN TAVITIAN |
Footing/Foundation/Slab | 12/12/2023 | Partial Approval | MARTIN TAVITIAN |
Deputy Drilled-In Anchors | 12/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
Deputy Reinf. Masonry | 1/3/2024 | Conditional Approval | DARRYL ARNOLD |
Light Gage Steel Frame | 1/3/2024 | Approved | DARRYL ARNOLD |
Deputy Reinf. Masonry | 1/5/2024 | Conditional Approval | MICHAEL ROSENBERG |
Deputy Reinf. Masonry | 1/8/2024 | Conditional Approval | MICHAEL ROSENBERG |
Deputy Reinf. Masonry | 1/9/2024 | Conditional Approval | MICHAEL ROSENBERG |
Masonry Wall/Backfill | 1/10/2024 | Partial Approval | JEROME BLACKWOOD |
Green Building Rough | 1/18/2024 | Partial Approval | MARTIN TAVITIAN |
METHANE-Rough | 1/18/2024 | Partial Approval | MARTIN TAVITIAN |
Reinforced Concrete Frame | 1/18/2024 | Partial Approval | MARTIN TAVITIAN |
Reinforced Masonry Frame | 1/18/2024 | Partial Approval | MARTIN TAVITIAN |
Deputy Reinf. Masonry | 1/23/2024 | Conditional Approval | MICHAEL ROSENBERG |
Interior/Exterior Lathing | 2/7/2024 | Partial Approval | MARTIN TAVITIAN |
Deputy Fireproofing | 2/14/2024 | Conditional Approval | MICHAEL ROSENBERG |
Deputy Drilled-In Anchors | 2/16/2024 | Approved | TIMOTHY POWELL |
Deputy Methane Barrier | 2/16/2024 | Approved | TIMOTHY POWELL |
Footing/Foundation/Slab | 2/16/2024 | Partial Approval | TIMOTHY POWELL |
Deputy Drilled-In Anchors | 2/26/2024 | Approved | TIMOTHY POWELL |
Deputy Methane Barrier | 2/26/2024 | Approved | TIMOTHY POWELL |
METHANE-Rough | 2/27/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
Green Building Rough | 2/28/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
Reinforced Concrete Frame | 2/28/2024 | Partial Approval | JEROME BLACKWOOD |
Deputy Steel/Welding | 3/4/2024 | Approved | TIMOTHY POWELL |
Light Gage Steel Frame | 3/4/2024 | Partial Approval | TIMOTHY POWELL |
Footing/Foundation/Slab | 3/8/2024 | Approved | DARRYL ARNOLD |
Drywall Nailing | 3/18/2024 | Partial Approval | DAVID BURKHEAD |
Light Gage Steel Frame | 3/18/2024 | Partial Approval | DAVID BURKHEAD |
T-Bar Ceiling | 3/18/2024 | Partial Approval | DAVID BURKHEAD |
Drywall Nailing | 3/27/2024 | Not Ready for Inspection | RAFAEL CORTES |
Drywall Nailing | 3/28/2024 | Not Ready for Inspection | RAFAEL CORTES |
Deputy Steel/Welding | 4/2/2024 | Conditional Approval | DARRYL ARNOLD |
Drywall Nailing | 4/2/2024 | Approved | DARRYL ARNOLD |
METHANE-Final | 4/2/2024 | Approved | DARRYL ARNOLD |
METHANE-Rough | 4/2/2024 | Approved | DARRYL ARNOLD |
Deputy Steel/Welding | 4/9/2024 | Conditional Approval | DARRYL ARNOLD |
Pre-Inspection | 4/9/2024 | Conditional Approval | DARRYL ARNOLD |
Light Gage Steel Frame | 4/26/2024 | Partial Approval | TIMOTHY POWELL |
T-Bar Ceiling | 4/26/2024 | Partial Approval | TIMOTHY POWELL |
Drywall Nailing | 5/9/2024 | Partial Approval | RAFAEL CORTES |
Green Building Rough | 5/23/2024 | Not Ready for Inspection | RAFAEL CORTES |
Reinforced Concrete Frame | 5/23/2024 | Partial Approval | RAFAEL CORTES |
Structural Steel Frame | 5/23/2024 | Partial Approval | RAFAEL CORTES |
Structural Steel Frame | 7/2/2024 | Partial Approval | RAFAEL CORTES |
Masonry Wall/Backfill | 7/9/2024 | Partial Approval | TIMOTHY POWELL |
Insulation | 7/26/2024 | Partial Approval | TIMOTHY POWELL |
Light Gage Steel Frame | 7/26/2024 | Partial Approval | TIMOTHY POWELL |
Drywall Nailing | 8/2/2024 | Partial Approval | TIMOTHY POWELL |
Insulation | 8/27/2024 | Not Ready for Inspection | LUIS CCAMACHO |
Light Gage Steel Frame | 8/27/2024 | Not Ready for Inspection | LUIS CCAMACHO |
Masonry Wall/Backfill | 8/27/2024 | Partial Approval | LUIS CCAMACHO |
T-Bar Ceiling | 8/27/2024 | Not Ready for Inspection | LUIS CCAMACHO |
Light Gage Steel Frame | 8/29/2024 | Partial Approval | JEROME BLACKWOOD |
T-Bar Ceiling | 8/29/2024 | Partial Approval | JEROME BLACKWOOD |
Light Gage Steel Frame | 8/30/2024 | Not Ready for Inspection | TIMOTHY POWELL |
Drywall Nailing | 9/5/2024 | Approved | JEROME BLACKWOOD |
Green Building Rough | 9/12/2024 | Approved | RONALD JIMENEZ |
Reinforced Concrete Frame | 9/12/2024 | Approved | RONALD JIMENEZ |
Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Conditional Approval | DARRYL ARNOLD |
Masonry Wall/Backfill | 9/26/2024 | Conditional Approval | DARRYL ARNOLD |
Wood Frame | 9/26/2024 | Conditional Approval | DARRYL ARNOLD |
Wood Frame | 9/30/2024 | Partial Approval | TIMOTHY POWELL |
Structural Steel Frame | 12/6/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
Wood Frame | 12/6/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
Structural Steel Frame | 1/16/2025 | Partial Approval | LUIS CCAMACHO |
Wood Frame | 1/16/2025 | Partial Approval | LUIS CCAMACHO |
Pre-Inspection | 3/24/2025 | Partial Approval | ALFREDO LOPEZ |
Pre-Inspection | 4/18/2025 | Partial Approval | TIMOTHY POWELL |