928 1/2 E 57TH ST 90011
Certificate Information: 928 1/2 E 57TH ST 90011
- Application / Permit
- 20010-10000-02166
- Plan Check / Job No.
- B20LA11310
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETACHED 1-STORY ADU PER CA GOVT. CODE 65852.2(e )(1)(c)
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 5/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 6/29/2020 | APPLICANT |
Assigned to Plan Check Engineer | 7/24/2020 | MAHNAZ NOURHASHEMI |
Corrections Issued | 7/30/2020 | MAHNAZ NOURHASHEMI |
Quality Review Completed | 8/6/2020 | TIEN JEN WANG |
Building Plans Picked Up | 8/11/2020 | APPLICANT |
Applicant returned to address corrections | 7/1/2021 | MAHNAZ NOURHASHEMI |
Applicant returned to address corrections | 12/27/2021 | MAHNAZ NOURHASHEMI |
Plan Check Approved | 2/3/2022 | MAHNAZ NOURHASHEMI |
Plan Check Approved | 2/3/2022 | MAHNAZ NOURHASHEMI |
Issued | 2/3/2022 | APPLICANT |
CofO in Progress | 5/17/2023 | BRENDAN MORELLI |
CofO Issued | 5/22/2023 | DEROLD HAUFF |
Permit Finaled | 5/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
Address approval | Cleared | 1/5/2021 | JEANIE LAM |
Redevelopment Project Area | Cleared | 1/7/2021 | GRACIELA ACOSTA |
Redevelopment Project Area | Cleared | 1/7/2021 | GRACIELA ACOSTA |
Eng Process Fee Ord 176,300 | Cleared | 1/19/2021 | JEANIE LAM |
Sewer availability | Cleared | 1/19/2021 | JEANIE LAM |
Hydrant and Access approval | Cleared | 2/2/2021 | MATTHEW CRAIG |
Construction near power lines | Cleared | 3/3/2021 | WALTER RAMIREZ |
Low Impact Development | Cleared | 6/15/2021 | MARTIN FRAGOSO |
Roof/Waste drainage to street | Cleared | 6/25/2021 | JEANIE LAM |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Pinzon,, Eduardo A; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Underground Mechanical | 3/18/2022 | Partial Approval | JOAQUIN GREENOUGH |
Excavation/Setback/Form/Re-Bar | 3/26/2022 | Off-Hour Fees Due | |
Excavation/Setback/Form/Re-Bar | 3/29/2022 | Approved | JOAQUIN GREENOUGH |
Floor/Roof Diaphrgm/Shear Wall | 4/8/2022 | Corrections Issued | JOAQUIN GREENOUGH |
Floor/Roof Diaphrgm/Shear Wall | 4/20/2022 | Partial Approval | JOAQUIN GREENOUGH |
Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Approved | JOAQUIN GREENOUGH |
BUILDING-Rough-Frame | 5/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
ELECTRICAL-Rough | 5/23/2022 | Corrections Issued | JOAQUIN GREENOUGH |
Green Building Rough | 5/23/2022 | Approved | JOAQUIN GREENOUGH |
HVAC-Rough | 5/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
METHANE-Rough | 5/23/2022 | Approved | JOAQUIN GREENOUGH |
PLUMBING-Rough | 5/23/2022 | Corrections Issued | JOAQUIN GREENOUGH |
Verify Sprinkler Sign Off | 5/23/2022 | Approved | JOAQUIN GREENOUGH |
BUILDING-Rough-Frame | 5/31/2022 | Corrections Issued | SHAVONNE ESPINOZA |
ELECTRICAL-Rough | 5/31/2022 | No Access for Inspection | SHAVONNE ESPINOZA |
HVAC-Rough | 5/31/2022 | No Access for Inspection | SHAVONNE ESPINOZA |
PLUMBING-Rough | 5/31/2022 | No Access for Inspection | SHAVONNE ESPINOZA |
ELECTRICAL-Rough | 6/3/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
HVAC-Rough | 6/3/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
PLUMBING-Rough | 6/3/2022 | Corrections Issued | JOAQUIN GREENOUGH |
Wood Frame | 6/3/2022 | Corrections Issued | JOAQUIN GREENOUGH |
BUILDING-Rough-Frame | 6/17/2022 | Approved | HORACE FULTZ |
ELECTRICAL-Rough | 6/17/2022 | Approved | HORACE FULTZ |
PLUMBING-Rough | 6/17/2022 | Approved | HORACE FULTZ |
ELECTRICAL-Rough | 6/21/2022 | Approved | JOAQUIN GREENOUGH |
Interior/Exterior Lathing | 6/21/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
PLUMBING-Rough | 6/21/2022 | Approved | JOAQUIN GREENOUGH |
Insulation | 6/24/2022 | Partial Approval | JOAQUIN GREENOUGH |
Interior/Exterior Lathing | 6/24/2022 | Partial Approval | JOAQUIN GREENOUGH |
Shower Pan | 6/24/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
Drywall Nailing | 7/1/2022 | Partial Approval | JOAQUIN GREENOUGH |
Interior/Exterior Lathing | 7/1/2022 | Partial Approval | JOAQUIN GREENOUGH |
Sewer | 9/26/2022 | Approved | RYAN SALAZAR |
Underground Mechanical | 9/26/2022 | Approved | RYAN SALAZAR |
ELECTRICAL-Final | 11/16/2022 | Corrections Issued | SCOTT FINNILA |
HVAC-Final | 11/16/2022 | Corrections Issued | SCOTT FINNILA |
PLUMBING-Final | 11/16/2022 | Corrections Issued | SCOTT FINNILA |
Gas Test | 12/5/2022 | Approved | ALIZAH MAYAGOITIA |
PLUMBING-Final | 12/5/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
ELECTRICAL-Final | 12/8/2022 | Corrections Issued | CALEB MEISTER |
ELECTRICAL-Final | 2/15/2023 | Corrections Issued | BRENDAN MORELLI |
HVAC-Final | 2/15/2023 | Corrections Issued | BRENDAN MORELLI |
ELECTRICAL-Final | 2/22/2023 | Approved | BRENDAN MORELLI |
Gas Test | 2/22/2023 | Corrections Issued | BRENDAN MORELLI |
HVAC-Final | 2/22/2023 | Conditional Approval | BRENDAN MORELLI |
Drywall Nailing | 4/19/2023 | Approved | BRENDAN MORELLI |
Final | 4/19/2023 | Corrections Issued | BRENDAN MORELLI |
Footing/Foundation/Slab | 4/19/2023 | Approved | BRENDAN MORELLI |
Gas Test | 4/19/2023 | Approved | BRENDAN MORELLI |
Green Building Final | 4/19/2023 | Conditional Approval | BRENDAN MORELLI |
METHANE-Barrier | 4/19/2023 | Approved | BRENDAN MORELLI |
METHANE-Subgrade | 4/19/2023 | Approved | BRENDAN MORELLI |
SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Approved | BRENDAN MORELLI |
Service/Power Release | 4/19/2023 | Corrections Issued | BRENDAN MORELLI |
Smoke Detectors | 4/19/2023 | Approved | BRENDAN MORELLI |
Final | 4/25/2023 | Conditional Approval | BRENDAN MORELLI |
Green Building Final | 4/25/2023 | Approved | BRENDAN MORELLI |
Service/Power Release | 4/25/2023 | Approved | BRENDAN MORELLI |
Final | 4/27/2023 | Corrections Issued | BRENDAN MORELLI |
Final | 5/17/2023 | OK to Issue CofO | BRENDAN MORELLI |