5327 S INGLEWOOD BLVD 90230

Certificate Information: 5327 S INGLEWOOD BLVD 90230

Application / Permit
20010-20000-02932
Plan Check / Job No.
B20VN11289
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW(25'-10 1/2"x 17'-0") 2-STORY DETACHED ACCESSORY DWELLING UNIT WITH ATT 1-CAR GARAGE BELOW PER LAMC 12.22A.33 (c) and (d). WORK PER ENGINEER.
Permit Issued
Issued on 11/10/2021
Issuing Office
Current Status
CofO Issued on 7/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 TROY DEGUZMAN
Corrections Issued 10/1/2020 TROY DEGUZMAN
Quality Review Completed 10/1/2020 CHON CHIO KUO
Building Plans Picked Up 10/2/2020 APPLICANT
Applicant returned to address corrections 1/22/2021 TROY DEGUZMAN
Plan Check Approved 6/11/2021 TROY DEGUZMAN
Plan Check Approved 6/16/2021 TROY DEGUZMAN
Issued 11/10/2021 APPLICANT
CofO in Progress 7/7/2023 JESUS RODRIGUEZ
Permit Finaled 7/19/2023 DANIEL ORRANTE
CofO Issued 7/19/2023 DANIEL ORRANTE
Permit Finaled 7/19/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/6/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 10/6/2020 DINAH GARIN
ZI Cleared 10/6/2020 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 10/8/2020 DINAH GARIN
Sewer availability Cleared 10/8/2020 DINAH GARIN
Hydrant and Access approval Cleared 3/19/2021 KURT CORRAL

Contact Information

Contractor Dreamcatcher Remodeling; Lic. No.: 1036088-B 14823 1/4 OXNARD ST      VAN NUYS, CA 91411
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

RUBEN RIVAS, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/17/2021 Partial Approval BOBBY KEY
Pre-Inspection 12/17/2021 Partial Approval RICHARD STEINBACH
PLUMBING-Rough 1/14/2022 Partial Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 1/21/2022 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 1/28/2022 Approved DAVID FEILER
Footing/Foundation/Slab 1/28/2022 Approved DAVID FEILER
Sewer 1/28/2022 Approved DAVID FEILER
Special/Order Compliance 2/14/2022 Approved BOBBY KEY
Deputy Reinf. Concrete 2/17/2022 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Conditional Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Partial Approval JESUS RODRIGUEZ
Green Building Rough 3/10/2022 Not Ready for Inspection JESUS RODRIGUEZ
MERV13>=Rough 3/10/2022 Not Ready for Inspection JESUS RODRIGUEZ
Verify Sprinkler Sign Off 3/10/2022 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/24/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/4/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 5/4/2022 Not Ready for Inspection JESUS RODRIGUEZ
MERV13>=Rough 5/4/2022 Not Ready for Inspection JESUS RODRIGUEZ
Verify Sprinkler Sign Off 5/4/2022 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 5/20/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 6/21/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 6/21/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 6/21/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 7/5/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/5/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/12/2022 Approved JESUS RODRIGUEZ
Green Building Rough 7/12/2022 Approved JESUS RODRIGUEZ
Insulation 7/12/2022 Approved JESUS RODRIGUEZ
MERV13>=Rough 7/12/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 7/22/2022 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 8/18/2022 Approved HERBERT GIRON
ELECTRICAL-Final 12/22/2022 Corrections Issued HERBERT GIRON
Final 12/22/2022 Corrections Issued HERBERT GIRON
Green Building Final 12/22/2022 Not Ready for Inspection HERBERT GIRON
HVAC-Final 12/22/2022 Not Ready for Inspection HERBERT GIRON
MERV13>=Final 12/22/2022 Approved HERBERT GIRON
PLUMBING-Final 12/22/2022 Not Ready for Inspection HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Not Ready HERBERT GIRON
Service/Power Release 12/22/2022 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 12/22/2022 Approved HERBERT GIRON
Light Gage Steel Frame 2/3/2023 Approved HERBERT GIRON
Drywall Nailing 2/10/2023 Approved HERBERT GIRON
ELECTRICAL-Final 6/13/2023 Corrections Issued HERBERT GIRON
HVAC-Final 6/13/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 6/13/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 6/20/2023 Approved JESUS RODRIGUEZ
Final 6/20/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 6/20/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 6/20/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/20/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 6/20/2023 Corrections Issued JESUS RODRIGUEZ
Final 7/6/2023 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 7/6/2023 Approved JESUS RODRIGUEZ
Service/Power Release 7/6/2023 Approved JESUS RODRIGUEZ