15014 W HAYNES ST 91411

Certificate Information: 15014 W HAYNES ST 91411

Application / Permit
20014-20000-00032
Plan Check / Job No.
B20VN00131
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
KITCHEN/BEDROOM/BATHROOM REMODEL, 12'-0" X 17'-8" ADDITION OF BATHROOM / CLOSET TO THE (E) SFD. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 5/11/2021
Issuing Office
Current Status
CofO Issued on 4/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2020 APPLICANT
Assigned to Plan Check Engineer 1/6/2020 ARTIN ZARUKIAN
Corrections Issued 1/6/2020 ARTIN ZARUKIAN
Plan Check Approved 2/3/2020 JENNIFER LEE
Issued 5/11/2021 APPLICANT
CofO in Progress 12/1/2021 JOHN HAYES
Permit Finaled 4/17/2023 DANIEL ORRANTE
CofO Issued 4/17/2023 DANIEL ORRANTE
Permit Finaled 4/17/2023 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 1/22/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 1/28/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/28/2020 ADRIAN CASTRO
Sewer availability Cleared 1/28/2020 ADRIAN CASTRO

Contact Information

Contractor Liebobuilders; Lic. No.: 1054050-B 12149 BURBANK BLVD SUITE 4      VALLEY VILLAGE, CA 91607

Inspector Information

RYAN SALAZAR, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/19/2021 Approved STEVEN BACK
Footing/Foundation/Slab 5/19/2021 Approved STEVEN BACK
PLUMBING-Rough 6/4/2021 Partial Approval MATTHEW NELSON
Wood Frame 6/4/2021 Partial Approval MATTHEW NELSON
Wood Frame 6/9/2021 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 7/21/2021 Partial Approval ARTHUR SARGSYAN
Drywall Nailing 7/29/2021 Partial Approval JENNIFER RABUCHIN
Green Building Rough 7/29/2021 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 8/17/2021 Approved RICHARD DOCKUS
Green Building Rough 8/17/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 9/1/2021 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Final 9/15/2021 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 9/15/2021 Corrections Issued RICHARD DOCKUS
Sewer 9/15/2021 Not Ready for Inspection RICHARD DOCKUS
Wood Frame 9/22/2021 Corrections Issued RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 9/24/2021 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 9/28/2021 Partial Approval AMY COLIN
PLUMBING-Rough 9/29/2021 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 10/1/2021 Partial Approval AMY COLIN
HVAC-Rough 10/1/2021 Approved AMY COLIN
PLUMBING-Rough 10/1/2021 Approved AMY COLIN
Insulation 10/4/2021 Approved RICHARD DOCKUS
Drywall Nailing 10/13/2021 Approved ALAN MORELOS
BUILDING-Rough-Frame 12/1/2021 Approved JOHN HAYES
Final 12/1/2021 OK to Issue CofO JOHN HAYES
Green Building Final 12/1/2021 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 12/1/2021 SGSOV Approved JOHN HAYES
Smoke Detectors 12/1/2021 Approved JOHN HAYES