1155 S WINDSOR BLVD 90019
Certificate Information: 1155 S WINDSOR BLVD 90019
- Application / Permit
- 20014-20000-04251
- Plan Check / Job No.
- B20VN12760
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 14' X 10' TRELLIS ADDITION, 12' X 43'-7" IRREG SHAPED ADDITION TO ENLARGE 2ND FLOOR, AND REMODEL TO (E) TWO STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 4/6/2021
- Issuing Office
- Current Status
- CofO Issued on 6/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Building Plans Picked Up | 4/7/2020 | APPLICANT |
Submitted | 9/29/2020 | APPLICANT |
Assigned to Plan Check Engineer | 10/1/2020 | JEROME MAGAT PALMA |
Corrections Issued | 10/5/2020 | JEROME MAGAT PALMA |
Quality Review Completed | 10/6/2020 | OMID HEDAYAT |
Applicant returned to address corrections | 1/15/2021 | JEROME MAGAT PALMA |
No Progress | 3/16/2021 | JEROME MAGAT PALMA |
Plan Check Approved | 4/6/2021 | JEROME MAGAT PALMA |
Issued | 4/6/2021 | APPLICANT |
CofO in Progress | 6/5/2023 | CALEB MEISTER |
Permit Finaled | 6/11/2023 | DEROLD HAUFF |
Permit Finaled | 6/11/2023 | DEROLD HAUFF |
CofO Issued | 6/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
Eng Process Fee Ord 176,300 | Cleared | 10/15/2020 | JEANIE LAM |
Low Impact Development | Cleared | 1/29/2021 | MARTIN FRAGOSO |
Roof/Waste drainage to street | Cleared | 2/3/2021 | JEANIE LAM |
HPOZ | Cleared | 2/10/2021 | AMANDA KAINER |
Flood clearance | Cleared | 2/18/2021 | BRYAN GATHUKA |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Excavation/Setback/Form/Re-Bar | 6/15/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
Excavation/Setback/Form/Re-Bar | 6/21/2021 | Corrections Issued | STUART CHAPMAN |
Special/Order Compliance | 11/8/2021 | Not Ready for Inspection | STUART CHAPMAN |
Special/Order Compliance | 11/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
Special/Order Compliance | 11/10/2021 | Corrections Issued | STUART CHAPMAN |
Wood Frame | 12/16/2021 | Partial Approval | STUART CHAPMAN |
ELECTRICAL-Rough | 1/24/2022 | Approved | STUART CHAPMAN |
HVAC-Rough | 1/24/2022 | Approved | STUART CHAPMAN |
Interior/Exterior Lathing | 1/24/2022 | Partial Approval | STUART CHAPMAN |
PLUMBING-Rough | 1/24/2022 | Approved | STUART CHAPMAN |
Deputy Drilled-In Anchors | 2/25/2022 | Conditional Approval | STUART CHAPMAN |
Interior/Exterior Lathing | 3/11/2022 | Partial Approval | STUART CHAPMAN |
Sewer | 3/11/2022 | Not Ready for Inspection | STUART CHAPMAN |
Wood Frame | 3/11/2022 | Partial Approval | STUART CHAPMAN |
Deputy Wood Construction | 3/25/2022 | Approved | STUART CHAPMAN |
Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Partial Approval | STUART CHAPMAN |
Insulation | 3/25/2022 | Partial Approval | STUART CHAPMAN |
Wood Frame | 3/25/2022 | Approved | STUART CHAPMAN |
Insulation | 4/1/2022 | Approved | KATHRYN BUTTERWORTH |
Drywall Nailing | 5/2/2022 | Approved | STUART CHAPMAN |
ELECTRICAL-Final | 12/8/2022 | Not Ready for Inspection | STUART CHAPMAN |
Final | 12/8/2022 | Corrections Issued | STUART CHAPMAN |
HVAC-Final | 12/8/2022 | Not Ready for Inspection | STUART CHAPMAN |
PLUMBING-Final | 12/8/2022 | Not Ready for Inspection | STUART CHAPMAN |
ELECTRICAL-Final | 1/19/2023 | Approved | CALEB MEISTER |
HVAC-Final | 1/19/2023 | Approved | CALEB MEISTER |
PLUMBING-Final | 1/19/2023 | Approved | CALEB MEISTER |
BUILDING-Rough-Frame | 5/31/2023 | Approved | CALEB MEISTER |
FLOOD-Elevation Certificate | 5/31/2023 | Approved | CALEB MEISTER |
FLOOD-Proofing Certificate | 5/31/2023 | Approved | CALEB MEISTER |
Footing/Foundation/Slab | 5/31/2023 | Approved | CALEB MEISTER |
Green Building Final | 5/31/2023 | Approved | CALEB MEISTER |
Green Building Rough | 5/31/2023 | Approved | CALEB MEISTER |
METHANE-Barrier | 5/31/2023 | Approved | CALEB MEISTER |
METHANE-Final | 5/31/2023 | Approved | CALEB MEISTER |
METHANE-Rough | 5/31/2023 | Approved | CALEB MEISTER |
METHANE-Subgrade | 5/31/2023 | Approved | CALEB MEISTER |
SGSOV-Seismic Gas S/O Valve | 5/31/2023 | SGSOV Approved | CALEB MEISTER |
Smoke Detectors | 5/31/2023 | Approved | CALEB MEISTER |
Final | 6/5/2023 | OK to Issue CofO | CALEB MEISTER |