6324 N MURIETTA AVE 91401

Certificate Information: 6324 N MURIETTA AVE 91401

Application / Permit
20014-20000-05046
Plan Check / Job No.
B20VN14818
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
DEMOLISH 8' 9" X 20' 1" PORTION OF (E) SFD, ADD 36' 4" X 3' 2" TO SIDE OF 1ST FLOOR, 16' 1" X 3' TO REAR OF 1ST FLOOR AND 8' 9" X 23' 4" TO FRONT OF 1ST FLOOR WITH ATTACHED NEW 3' 10" X 8' 5" PORCH, NEW 10' 6" X 19' 1-CAR GARAGE AND 33' 6" X 43' 1" IRR.-SHAPE 2ND STORY ADDITION TO (E) SFD. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 11/16/2021
Issuing Office
Current Status
CofO Issued on 5/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2020 APPLICANT
Assigned to Plan Check Engineer 11/19/2020 GURUNATH NESARAJAH
Corrections Issued 11/21/2020 GURUNATH NESARAJAH
Quality Review Completed 11/25/2020 OMID HEDAYAT
Applicant returned to address corrections 10/27/2021 GURUNATH NESARAJAH
Plan Check Approved 11/16/2021 GURUNATH NESARAJAH
Issued 11/16/2021 APPLICANT
Building Plans Picked Up 11/18/2021 APPLICANT
CofO in Progress 5/19/2023 RYAN SALAZAR
Permit Finaled 5/25/2023 MICHAEL SMITH
CofO Issued 5/25/2023 MICHAEL SMITH
Permit Finaled 5/25/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/17/2020 ADRIAN CASTRO
Low Impact Development Cleared 3/18/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/19/2021 ADRIAN CASTRO
Sewer availability Cleared 3/19/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

RYAN SALAZAR, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/1/2021 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 2/7/2022 No Access for Inspection RICHARD DOCKUS
Green Building Rough 2/7/2022 No Access for Inspection RICHARD DOCKUS
Wood Frame 2/7/2022 No Access for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 2/15/2022 Partial Approval RICHARD DOCKUS
Green Building Rough 2/15/2022 Not Ready for Inspection RICHARD DOCKUS
Wood Frame 2/15/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Approved RICHARD DOCKUS
HVAC-Rough 3/2/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 3/2/2022 Partial Approval ALAN MORELOS
PLUMBING-Rough 3/2/2022 Approved ALAN MORELOS
ELECTRICAL-Rough 3/8/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 3/11/2022 Approved JOHN HAYES
Green Building Rough 3/11/2022 Approved JOHN HAYES
Insulation 3/24/2022 Conditional Approval DEANDRE HOFFMAN
Drywall Nailing 4/4/2022 Approved ALAN MORELOS
Insulation 4/4/2022 Approved ALAN MORELOS
Shower Pan 5/4/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 5/16/2022 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 3/7/2023 No Access for Inspection RYAN SALAZAR
ELECTRICAL-Final 3/17/2023 Approved RYAN SALAZAR
Final 3/17/2023 Corrections Issued RYAN SALAZAR
Green Building Final 3/17/2023 Not Ready for Inspection RYAN SALAZAR
HVAC-Final 3/17/2023 Approved RYAN SALAZAR
PLUMBING-Final 3/17/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 3/17/2023 Approved RYAN SALAZAR
Final 5/18/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 5/18/2023 Approved RYAN SALAZAR