6324 N MURIETTA AVE 91401
Certificate Information: 6324 N MURIETTA AVE 91401
- Application / Permit
- 20014-20000-05046
- Plan Check / Job No.
- B20VN14818
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMOLISH 8' 9" X 20' 1" PORTION OF (E) SFD, ADD 36' 4" X 3' 2" TO SIDE OF 1ST FLOOR, 16' 1" X 3' TO REAR OF 1ST FLOOR AND 8' 9" X 23' 4" TO FRONT OF 1ST FLOOR WITH ATTACHED NEW 3' 10" X 8' 5" PORCH, NEW 10' 6" X 19' 1-CAR GARAGE AND 33' 6" X 43' 1" IRR.-SHAPE 2ND STORY ADDITION TO (E) SFD. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 11/16/2021
- Issuing Office
- Current Status
- CofO Issued on 5/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 11/13/2020 | APPLICANT |
Assigned to Plan Check Engineer | 11/19/2020 | GURUNATH NESARAJAH |
Corrections Issued | 11/21/2020 | GURUNATH NESARAJAH |
Quality Review Completed | 11/25/2020 | OMID HEDAYAT |
Applicant returned to address corrections | 10/27/2021 | GURUNATH NESARAJAH |
Plan Check Approved | 11/16/2021 | GURUNATH NESARAJAH |
Issued | 11/16/2021 | APPLICANT |
Building Plans Picked Up | 11/18/2021 | APPLICANT |
CofO in Progress | 5/19/2023 | RYAN SALAZAR |
Permit Finaled | 5/25/2023 | MICHAEL SMITH |
CofO Issued | 5/25/2023 | MICHAEL SMITH |
Permit Finaled | 5/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
Eng Process Fee Ord 176,300 | Cleared | 12/17/2020 | ADRIAN CASTRO |
Low Impact Development | Cleared | 3/18/2021 | SARAH YOUSSEF |
Roof/Waste drainage to street | Cleared | 3/19/2021 | ADRIAN CASTRO |
Sewer availability | Cleared | 3/19/2021 | ADRIAN CASTRO |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
RYAN SALAZAR, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 12/1/2021 | Approved | WILLIAM KUEHN |
Floor/Roof Diaphrgm/Shear Wall | 1/6/2022 | Corrections Issued | RICHARD DOCKUS |
BUILDING-Rough-Frame | 2/7/2022 | No Access for Inspection | RICHARD DOCKUS |
Green Building Rough | 2/7/2022 | No Access for Inspection | RICHARD DOCKUS |
Wood Frame | 2/7/2022 | No Access for Inspection | RICHARD DOCKUS |
BUILDING-Rough-Frame | 2/15/2022 | Partial Approval | RICHARD DOCKUS |
Green Building Rough | 2/15/2022 | Not Ready for Inspection | RICHARD DOCKUS |
Wood Frame | 2/15/2022 | Partial Approval | RICHARD DOCKUS |
Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Approved | RICHARD DOCKUS |
HVAC-Rough | 3/2/2022 | Approved | ALAN MORELOS |
Interior/Exterior Lathing | 3/2/2022 | Partial Approval | ALAN MORELOS |
PLUMBING-Rough | 3/2/2022 | Approved | ALAN MORELOS |
ELECTRICAL-Rough | 3/8/2022 | Approved | RICHARD DOCKUS |
BUILDING-Rough-Frame | 3/11/2022 | Approved | JOHN HAYES |
Green Building Rough | 3/11/2022 | Approved | JOHN HAYES |
Insulation | 3/24/2022 | Conditional Approval | DEANDRE HOFFMAN |
Drywall Nailing | 4/4/2022 | Approved | ALAN MORELOS |
Insulation | 4/4/2022 | Approved | ALAN MORELOS |
Shower Pan | 5/4/2022 | Approved | RICHARD DOCKUS |
Interior/Exterior Lathing | 5/16/2022 | Approved | DEANDRE HOFFMAN |
ELECTRICAL-Final | 3/7/2023 | No Access for Inspection | RYAN SALAZAR |
ELECTRICAL-Final | 3/17/2023 | Approved | RYAN SALAZAR |
Final | 3/17/2023 | Corrections Issued | RYAN SALAZAR |
Green Building Final | 3/17/2023 | Not Ready for Inspection | RYAN SALAZAR |
HVAC-Final | 3/17/2023 | Approved | RYAN SALAZAR |
PLUMBING-Final | 3/17/2023 | Approved | RYAN SALAZAR |
SGSOV-Seismic Gas S/O Valve | 3/17/2023 | SGSOV Approved | RYAN SALAZAR |
Smoke Detectors | 3/17/2023 | Approved | RYAN SALAZAR |
Final | 5/18/2023 | OK to Issue CofO | RYAN SALAZAR |
Green Building Final | 5/18/2023 | Approved | RYAN SALAZAR |