3519 S BARRY AVE 90066
Certificate Information: 3519 S BARRY AVE 90066
- Application / Permit
- 20014-30000-04665
- Plan Check / Job No.
- B20WL04641
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY MAJOR ADDITION KEEPING ONLY 2-FT OF WALL AND FOUNDATION WITH ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 1/26/2021
- Issuing Office
- Current Status
- CofO Issued on 4/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 10/22/2020 | APPLICANT |
Assigned to Plan Check Engineer | 10/29/2020 | TARIK SAOUD |
Corrections Issued | 11/2/2020 | TARIK SAOUD |
Quality Review Completed | 11/4/2020 | KAMRAN GHOTBI RAVANDI |
Plan Check Approved | 1/4/2021 | TARIK SAOUD |
Issued | 1/26/2021 | APPLICANT |
Building Plans Picked Up | 1/27/2021 | APPLICANT |
CofO in Progress | 4/1/2022 | JOHNNY MIRANDA |
Permit Finaled | 4/15/2022 | DANIEL ORRANTE |
CofO Issued | 4/15/2022 | DANIEL ORRANTE |
Permit Finaled | 4/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
Permit | Cleared | 11/17/2020 | DINAH GARIN |
Low Impact Development | Cleared | 11/18/2020 | ROBIN YAMADA |
Specific Plan | Cleared | 11/18/2020 | FREDDY GARCIA |
Eng Process Fee Ord 176,300 | Cleared | 11/25/2020 | DINAH GARIN |
Roof/Waste drainage to street | Cleared | 11/25/2020 | DINAH GARIN |
Sewer availability | Cleared | 11/25/2020 | DINAH GARIN |
Trees in Parkway | Cleared | 12/28/2020 | JOHN KIM |
Grading Pre-Inspection | Cleared | 1/4/2021 | TARIK SAOUD |
Contact Information
Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
Contractor | Southland Building & Remodel Company; Lic. No.: 894311-B | 1324 WEST ROSECRANS AVENUE COMPTON, CA 90222 |
Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
DANIEL VERA, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
PLUMBING-Rough | 3/15/2021 | Partial Approval | EVAN COOPER |
Sewer | 3/15/2021 | Approved | EVAN COOPER |
Excavation/Setback/Form/Re-Bar | 3/24/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
Footing/Foundation/Slab | 3/24/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
Footing/Foundation/Slab | 3/25/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
Deputy Wood Construction | 4/13/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
Floor/Roof Diaphrgm/Shear Wall | 4/13/2021 | Partial Approval | OGANES TARAKHCHYAN |
BUILDING-Rough-Frame | 7/12/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
ELECTRICAL-Rough | 7/12/2021 | Partial Approval | OGANES TARAKHCHYAN |
Floor/Roof Diaphrgm/Shear Wall | 7/12/2021 | Partial Approval | OGANES TARAKHCHYAN |
Green Building Rough | 7/12/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
HVAC-Rough | 7/12/2021 | Approved | OGANES TARAKHCHYAN |
PLUMBING-Rough | 7/12/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
BUILDING-Rough-Frame | 7/15/2021 | Partial Approval | OGANES TARAKHCHYAN |
Green Building Rough | 7/15/2021 | Approved | OGANES TARAKHCHYAN |
PLUMBING-Rough | 7/15/2021 | Approved | OGANES TARAKHCHYAN |
Insulation | 8/23/2021 | Approved | JUAN VALENZUELA |
Interior/Exterior Lathing | 8/23/2021 | Partial Approval | JUAN VALENZUELA |
Drywall Nailing | 9/13/2021 | Approved | MORRIS JACKSON |
Shower Pan | 9/13/2021 | Approved | MORRIS JACKSON |
Interior/Exterior Lathing | 10/12/2021 | Approved | OGANES TARAKHCHYAN |
BUILDING-Rough-Frame | 2/25/2022 | Approved | JOHNNY MIRANDA |
ELECTRICAL-Final | 2/25/2022 | Corrections Issued | JOHNNY MIRANDA |
Final | 2/25/2022 | Corrections Issued | JOHNNY MIRANDA |
Footing/Foundation/Slab | 2/25/2022 | Approved | JOHNNY MIRANDA |
Green Building Final | 2/25/2022 | Approved | JOHNNY MIRANDA |
HVAC-Final | 2/25/2022 | Corrections Issued | JOHNNY MIRANDA |
PLUMBING-Final | 2/25/2022 | Corrections Issued | JOHNNY MIRANDA |
SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Not Ready | JOHNNY MIRANDA |
Smoke Detectors | 2/25/2022 | Approved | JOHNNY MIRANDA |
ELECTRICAL-Final | 2/28/2022 | Approved | JOHNNY MIRANDA |
Gas Test | 2/28/2022 | Approved | JOHNNY MIRANDA |
HVAC-Final | 2/28/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
PLUMBING-Final | 2/28/2022 | Corrections Issued | JOHNNY MIRANDA |
Service/Power Release | 3/4/2022 | Approved | KENNETH NAGLE |
Final | 3/24/2022 | OK to Issue CofO | JOHNNY MIRANDA |
SGSOV-Seismic Gas S/O Valve | 3/24/2022 | SGSOV Approved | JOHNNY MIRANDA |