1813-1813 1/2 N WORKMAN ST 90031
Certificate Information: 1813-1813 1/2 N WORKMAN ST 90031
- Application / Permit
- 21010-10000-03051
- Plan Check / Job No.
- B21LA11503
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY (45.5' X 31.5') DUPLEX WITH ATTACHED 1-CAR GARAGE (FRONT) 1 OF 2
- Permit Issued
- Issued on 11/17/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 7/12/2021 | APPLICANT |
Assigned to Plan Check Engineer | 8/19/2021 | VIVIAN LAO |
Corrections Issued | 8/27/2021 | VIVIAN LAO |
Quality Review Completed | 9/9/2021 | MICHAEL PEREZ |
Building Plans Picked Up | 9/20/2021 | APPLICANT |
Applicant returned to address corrections | 11/18/2021 | VIVIAN LAO |
Applicant returned to address corrections | 7/22/2022 | VIVIAN LAO |
Plan Check Approved | 8/2/2022 | VIVIAN LAO |
Issued | 11/17/2022 | APPLICANT |
CofO in Progress | 11/13/2024 | OSVALDO PARAMO |
Permit Finaled | 11/16/2024 | DEROLD HAUFF |
CofO Issued | 11/16/2024 | DEROLD HAUFF |
Permit Finaled | 11/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
Address approval | Cleared | 9/7/2021 | WALLIE JONG |
Sewer availability | Cleared | 9/10/2021 | WALLIE JONG |
Eng Process Fee Ord 176,300 | Cleared | 9/23/2021 | WALLIE JONG |
Hydrant and Access approval | Cleared | 10/11/2021 | MATTHEW CRAIG |
Frnt yard landscape/Water mgmt | Cleared | 11/3/2021 | LAUREN PADICK |
Low Impact Development | Cleared | 3/10/2022 | SUNG JOON WON |
Roof/Waste drainage to street | Cleared | 4/4/2022 | WALLIE JONG |
Contact Information
Architect | , ; Lic. No.: C27009 | , |
Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
Engineer | Xiao,, Qiang; Lic. No.: S5289 | 1520 BROOKHOLLOW #45 SANTA ANA, CA 92705 |
Inspector Information
ALIZAH MAYAGOITIA, (213) 202-3124 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Excavation/Setback/Form/Re-Bar | 4/10/2023 | Approved | OSVALDO PARAMO |
PLUMBING-Rough | 4/10/2023 | Partial Approval | OSVALDO PARAMO |
Footing/Foundation/Slab | 4/20/2023 | Partial Approval | OSVALDO PARAMO |
Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Partial Approval | OSVALDO PARAMO |
Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Partial Approval | OSVALDO PARAMO |
Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | OSVALDO PARAMO |
Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Approved | OSVALDO PARAMO |
ELECTRICAL-Rough | 3/12/2024 | Approved | OSVALDO PARAMO |
PLUMBING-Rough | 3/12/2024 | Approved | OSVALDO PARAMO |
BUILDING-Rough-Frame | 3/21/2024 | Approved | OSVALDO PARAMO |
Green Building Rough | 3/21/2024 | Approved | OSVALDO PARAMO |
HVAC-Rough | 3/21/2024 | Approved | OSVALDO PARAMO |
MERV13>=Rough | 3/21/2024 | Approved | OSVALDO PARAMO |
Verify Sprinkler Sign Off | 3/21/2024 | Approved | OSVALDO PARAMO |
Interior/Exterior Lathing | 3/26/2024 | Partial Approval | OSVALDO PARAMO |
Wood Frame | 3/26/2024 | Approved | OSVALDO PARAMO |
Insulation | 4/4/2024 | Approved | OSVALDO PARAMO |
Drywall Nailing | 4/15/2024 | Approved | JOSEPH MCGARRY |
Interior/Exterior Lathing | 4/15/2024 | Approved | JOSEPH MCGARRY |
Sewer | 5/31/2024 | Approved | OSVALDO PARAMO |
Underground Mechanical | 5/31/2024 | Partial Approval | OSVALDO PARAMO |
Underground Mechanical | 6/6/2024 | Partial Approval | ALIZAH MAYAGOITIA |
Gas Test | 6/27/2024 | Approved | ALIZAH MAYAGOITIA |
SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
Verify Rec and Parks Fee Memo | 6/27/2024 | Partial Approval | ALIZAH MAYAGOITIA |
ELECTRICAL-Final | 9/9/2024 | Not Ready for Inspection | OSVALDO PARAMO |
HVAC-Final | 9/9/2024 | Corrections Issued | OSVALDO PARAMO |
ELECTRICAL-Final | 9/16/2024 | Approved | OSVALDO PARAMO |
HVAC-Final | 9/16/2024 | Approved | OSVALDO PARAMO |
ELECTRICAL-Final | 10/29/2024 | Approved | WILLIAM SIERRA |
Final | 10/29/2024 | Corrections Issued | WILLIAM SIERRA |
Footing/Foundation/Slab | 10/29/2024 | Approved | WILLIAM SIERRA |
Green Building Final | 10/29/2024 | Corrections Issued | WILLIAM SIERRA |
HVAC-Final | 10/29/2024 | Approved | WILLIAM SIERRA |
MERV13>=Final | 10/29/2024 | Corrections Issued | WILLIAM SIERRA |
PLUMBING-Final | 10/29/2024 | Corrections Issued | WILLIAM SIERRA |
Service/Power Release | 10/29/2024 | Approved | WILLIAM SIERRA |
Smoke Detectors | 10/29/2024 | Approved | WILLIAM SIERRA |
Final | 11/4/2024 | Not Ready for Inspection | LUIS CASTRO |
Green Building Final | 11/4/2024 | Not Ready for Inspection | LUIS CASTRO |
MERV13>=Final | 11/4/2024 | Approved | LUIS CASTRO |
PLUMBING-Final | 11/4/2024 | Approved | LUIS CASTRO |
Final | 11/8/2024 | OK to Issue CofO | OSVALDO PARAMO |
Green Building Final | 11/8/2024 | Approved | OSVALDO PARAMO |
Service/Power Release | 11/8/2024 | Approved | OSVALDO PARAMO |