6722 1-2 N SIMPSON AVE 91606

Certificate Information: 6722 1-2 N SIMPSON AVE 91606

Application / Permit
21010-20000-04931
Plan Check / Job No.
B21VN12881
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX (37'-0"x40'-4"), 3136 SQFT WITH 2 ATTACHED 2-CAR GARAGES,700 SQFT W/NFPA-13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/24/2022
Issuing Office
Current Status
CofO in Progress on 3/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/22/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 PETER MOSESIAN
Corrections Issued 10/16/2021 PETER MOSESIAN
Quality Review Completed 11/2/2021 OMID HEDAYAT
Building Plans Picked Up 11/9/2021 APPLICANT
Plan Check Approved 4/18/2022 PETER MOSESIAN
Issued 5/24/2022 APPLICANT
CofO in Progress 1/29/2025 ROBERTO PALACIOS-LOPEZ
No Progress 3/6/2025 ROBERTO PALACIOS-LOPEZ
CofO in Progress 3/6/2025 ROBERTO PALACIOS-LOPEZ

Permit Application Clearance Information

Address approval Cleared 10/27/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 10/27/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 12/27/2021 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 1/11/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 1/29/2022 RUEL COLE
Frnt yard landscape/Water mgmt Cleared 2/22/2022 MIGUEL GAMBOA
Sewer availability Cleared 3/30/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JOSE AVILA, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/1/2022 Partial Inspection ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 1/30/2023 Partial Approval JOHN HAYES
Underground Mechanical 1/30/2023 Partial Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 2/6/2023 Partial Approval JOHN HAYES
Footing/Foundation/Slab 2/6/2023 Partial Approval JOHN HAYES
Deputy Drilled-In Anchors 3/10/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 3/14/2023 Approved JOHN HAYES
Structural Steel Frame 3/14/2023 Approved JOHN HAYES
Deputy Reinf. Concrete 3/17/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/12/2023 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 5/22/2023 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Partial Approval JOHN HAYES
Insulation 6/12/2023 Partial Approval JOHN HAYES
Deputy Wood Construction 7/7/2023 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Partial Approval JOHN HAYES
HVAC-Rough 7/12/2023 Approved JOHN HAYES
PLUMBING-Rough 7/12/2023 Approved JOHN HAYES
Interior/Exterior Lathing 8/22/2023 Partial Approval JOHN HAYES
Shower Pan 8/25/2023 Approved JOHN HAYES
Interior/Exterior Lathing 8/30/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/5/2023 Approved JOHN HAYES
Green Building Rough 9/5/2023 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 9/5/2023 Approved JOHN HAYES
Verify Sprinkler Sign Off 9/5/2023 Approved JOHN HAYES
Insulation 9/11/2023 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Approved JOHN HAYES
Drywall Nailing 9/28/2023 Approved CHRISTOPHER ROJAS
Sewer 12/5/2023 Approved JOHN HAYES
Underground Mechanical 12/5/2023 Partial Approval JOHN HAYES
Underground Mechanical 9/24/2024 Partial Approval JOSE AVILA
Final 10/9/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 10/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 10/9/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 10/10/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Gas Test 10/10/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 10/10/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 1/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 1/13/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 1/13/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 1/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 1/17/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 1/17/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/17/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 1/24/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ