6722 1-2 N SIMPSON AVE 91606
Certificate Information: 6722 1-2 N SIMPSON AVE 91606
- Application / Permit
- 21010-20000-04931
- Plan Check / Job No.
- B21VN12881
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX (37'-0"x40'-4"), 3136 SQFT WITH 2 ATTACHED 2-CAR GARAGES,700 SQFT W/NFPA-13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- CofO in Progress on 3/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
Submitted | 9/22/2021 | APPLICANT |
Assigned to Plan Check Engineer | 10/14/2021 | PETER MOSESIAN |
Corrections Issued | 10/16/2021 | PETER MOSESIAN |
Quality Review Completed | 11/2/2021 | OMID HEDAYAT |
Building Plans Picked Up | 11/9/2021 | APPLICANT |
Plan Check Approved | 4/18/2022 | PETER MOSESIAN |
Issued | 5/24/2022 | APPLICANT |
CofO in Progress | 1/29/2025 | ROBERTO PALACIOS-LOPEZ |
No Progress | 3/6/2025 | ROBERTO PALACIOS-LOPEZ |
CofO in Progress | 3/6/2025 | ROBERTO PALACIOS-LOPEZ |
Permit Application Clearance Information
Address approval | Cleared | 10/27/2021 | DAGOVERTO GUERRERO |
Eng Process Fee Ord 176,300 | Cleared | 10/27/2021 | DAGOVERTO GUERRERO |
Low Impact Development | Cleared | 12/27/2021 | JONATAN VELASQUEZ |
Roof/Waste drainage to street | Cleared | 1/11/2022 | DAGOVERTO GUERRERO |
Hydrant and Access approval | Cleared | 1/29/2022 | RUEL COLE |
Frnt yard landscape/Water mgmt | Cleared | 2/22/2022 | MIGUEL GAMBOA |
Sewer availability | Cleared | 3/30/2022 | DAGOVERTO GUERRERO |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
JOSE AVILA, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 6/1/2022 | Partial Inspection | ARAM AVEDISIAN |
Excavation/Setback/Form/Re-Bar | 1/30/2023 | Partial Approval | JOHN HAYES |
Underground Mechanical | 1/30/2023 | Partial Approval | JOHN HAYES |
Excavation/Setback/Form/Re-Bar | 2/6/2023 | Partial Approval | JOHN HAYES |
Footing/Foundation/Slab | 2/6/2023 | Partial Approval | JOHN HAYES |
Deputy Drilled-In Anchors | 3/10/2023 | Conditional Approval | JUAN VALENZUELA |
Footing/Foundation/Slab | 3/14/2023 | Approved | JOHN HAYES |
Structural Steel Frame | 3/14/2023 | Approved | JOHN HAYES |
Deputy Reinf. Concrete | 3/17/2023 | Conditional Approval | JUAN VALENZUELA |
Floor/Roof Diaphrgm/Shear Wall | 4/12/2023 | Corrections Issued | JOHN HAYES |
Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Partial Approval | THOMAS FINNILA |
Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Corrections Issued | JOHN HAYES |
ELECTRICAL-Rough | 5/22/2023 | Not Ready for Inspection | JOHN HAYES |
Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Corrections Issued | JOHN HAYES |
Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | JOHN HAYES |
Insulation | 6/12/2023 | Partial Approval | JOHN HAYES |
Deputy Wood Construction | 7/7/2023 | Conditional Approval | ROBERT GOLD |
Floor/Roof Diaphrgm/Shear Wall | 7/12/2023 | Partial Approval | JOHN HAYES |
HVAC-Rough | 7/12/2023 | Approved | JOHN HAYES |
PLUMBING-Rough | 7/12/2023 | Approved | JOHN HAYES |
Interior/Exterior Lathing | 8/22/2023 | Partial Approval | JOHN HAYES |
Shower Pan | 8/25/2023 | Approved | JOHN HAYES |
Interior/Exterior Lathing | 8/30/2023 | Approved | JENNIFER RABUCHIN |
BUILDING-Rough-Frame | 9/5/2023 | Approved | JOHN HAYES |
Green Building Rough | 9/5/2023 | Approved | JOHN HAYES |
Rough-Elec/Plmb/HVAC | 9/5/2023 | Approved | JOHN HAYES |
Verify Sprinkler Sign Off | 9/5/2023 | Approved | JOHN HAYES |
Insulation | 9/11/2023 | Approved | JOHN HAYES |
Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Approved | JOHN HAYES |
Drywall Nailing | 9/28/2023 | Approved | CHRISTOPHER ROJAS |
Sewer | 12/5/2023 | Approved | JOHN HAYES |
Underground Mechanical | 12/5/2023 | Partial Approval | JOHN HAYES |
Underground Mechanical | 9/24/2024 | Partial Approval | JOSE AVILA |
Final | 10/9/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
PLUMBING-Final | 10/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
Special/Order Compliance | 10/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
ELECTRICAL-Final | 10/10/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
Gas Test | 10/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
HVAC-Final | 10/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
Final | 1/13/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
Green Building Final | 1/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
SGSOV-Seismic Gas S/O Valve | 1/13/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
Service/Power Release | 1/13/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
Smoke Detectors | 1/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
Final | 1/17/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
Service/Power Release | 1/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
Final | 1/24/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |