6401 W WILSHIRE BLVD 90048
Certificate Information: 6401 W WILSHIRE BLVD 90048
- Application / Permit
- 21047-20000-00391
- Plan Check / Job No.
- B21VN02145
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- Apartment
- Primary Use
- (4) Pool/Spa - Public
- Work Description
- NEW 20'1-1/2"X13'10-1/2" IRREGULAR SHAPED SPA
- Permit Issued
- Issued on 8/4/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/5/2024
- Certificate of Occupancy
- TCO Issued More Information
Permit Application Status History
Submitted | 2/23/2021 | APPLICANT |
Assigned to Plan Check Engineer | 3/11/2021 | MARVEL DELACRUZ |
Disabled Access Plans Picked Up | 3/17/2021 | APPLICANT |
Corrections Issued | 3/18/2021 | MARVEL DELACRUZ |
Quality Review Completed | 3/26/2021 | STEVEN KIM |
Applicant returned to address corrections | 8/2/2021 | MARVEL DELACRUZ |
Plan Check Approved | 8/4/2021 | MARVEL DELACRUZ |
Issued | 8/4/2021 | APPLICANT |
CofO in Progress | 7/16/2024 | EDWIN GREGORYONA |
No Progress | 11/8/2024 | EDWIN GREGORYONA |
CofO in Progress | 11/8/2024 | EDWIN GREGORYONA |
Permit Finaled | 12/5/2024 | ADAM BURGESS |
Permit Application Clearance Information
"Q" conditions | Cleared | 6/15/2021 | PABLO ESTRADA |
DAS Clearance | Cleared | 6/15/2021 | NORLITO MEDRANO |
Tract Map conditions | Cleared | 6/15/2021 | PABLO ESTRADA |
ZA Case | Cleared | 6/15/2021 | PABLO ESTRADA |
ZA Case | Cleared | 6/15/2021 | PABLO ESTRADA |
ZA Case | Cleared | 6/15/2021 | PABLO ESTRADA |
ZI | Cleared | 6/15/2021 | PABLO ESTRADA |
ZI | Cleared | 6/15/2021 | PABLO ESTRADA |
Sewer availability | Cleared | 7/9/2021 | CECILIO NAVARRO |
Eng Process Fee Ord 176,300 | Cleared | 7/12/2021 | CECILIO NAVARRO |
Public Swimming Pool approval | Cleared | 8/2/2021 | LACDHS APPROVED |
Contact Information
Architect | Ferrell,, Scott J; Lic. No.: C26222 | 4240 SKYLINE ROAD CARLSBAD, CA 92008 |
Contractor | Addison Pools Inc; Lic. No.: 753417-C53 | 4363 WOODMAN AVENUE SHERMAN OAKS, CA 91423 |
Inspector Information
EDWIN GREGORYONA, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Gunite | 8/18/2021 | Approved | EDWIN GREGORYONA |
METHANE-Barrier | 8/18/2021 | Approved | EDWIN GREGORYONA |
METHANE-Rough | 8/18/2021 | Approved | EDWIN GREGORYONA |
METHANE-Subgrade | 8/18/2021 | Approved | EDWIN GREGORYONA |
Pre-Gunite | 8/18/2021 | Approved | EDWIN GREGORYONA |
Enclosure/Fence | 10/13/2022 | Approved | EDWIN GREGORYONA |
Excavation/Setback/Form/Re-Bar | 1/12/2023 | Approved | GREGORY POMISH |
Final | 1/12/2023 | Conditional Approval | GREGORY POMISH |
Final | 6/11/2024 | Partial Inspection | EDWIN GREGORYONA |
Final | 7/16/2024 | Partial Inspection | EDWIN GREGORYONA |