3700 W BOYCE AVE 90039

Certificate Information: 3700 W BOYCE AVE 90039

Application / Permit
22010-10000-01401
Plan Check / Job No.
B22LA04847
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 9/2/2022
Issuing Office
Current Status
CofO Issued on 8/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/21/2022 SELLA BENYAMIN
Corrections Issued 3/21/2022 SELLA BENYAMIN
Applicant returned to address corrections 8/2/2022 SELLA BENYAMIN
Applicant returned to address corrections 8/6/2022 SELLA BENYAMIN
Applicant returned to address corrections 8/9/2022 KEVIN MORALES
Plan Check Approved 8/17/2022 SELLA BENYAMIN
Issued 9/2/2022 APPLICANT
CofO in Progress 5/24/2023 JEFFREY MEAD
Permit Finaled 8/6/2023 DEROLD HAUFF
CofO Issued 8/6/2023 DEROLD HAUFF
Permit Finaled 8/6/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/4/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 4/4/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 4/4/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 4/4/2022 CHRISTOPHER ROCHA
Construction near power lines Cleared 6/1/2022 RIDWAN HARDY

Contact Information

Architect Lehrer,, Michael Berryl; Lic. No.: NA12115       ,
Contractor Owner-Builder       ,

Inspector Information

THOMAS LOGRASSO, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/13/2022 Partial Inspection THOMAS LOGRASSO
Pre-Inspection 10/4/2022 Partial Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/15/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/22/2022 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 12/16/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/11/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/18/2023 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 1/18/2023 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 1/24/2023 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/27/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/27/2023 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/27/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 1/27/2023 Approved HAMIK HARTOUNIAN
Insulation 2/3/2023 Approved HAMIK HARTOUNIAN
Shower Pan 2/3/2023 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/23/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Drywall Nailing 2/23/2023 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/1/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 3/1/2023 Approved HAMIK HARTOUNIAN
Final 4/25/2023 Corrections Issued JEFFREY MEAD
Green Building Final 4/25/2023 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 4/25/2023 SGSOV Approved JEFFREY MEAD
Smoke Detectors 4/25/2023 Approved JEFFREY MEAD
ELECTRICAL-Final 5/23/2023 Approved JEFFREY MEAD
Final 5/23/2023 OK to Issue CofO JEFFREY MEAD
HVAC-Final 5/23/2023 Approved JEFFREY MEAD
PLUMBING-Final 5/23/2023 Approved JEFFREY MEAD