19098-19102 W WELBY WAY 91335

Certificate Information: 19098-19102 W WELBY WAY 91335

Application / Permit
22016-20000-07370
Plan Check / Job No.
B22VN03834
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22- NO CHANGE TO STRUCTURAL
Permit Issued
Issued on 6/10/2022
Issuing Office
Current Status
CofO Issued on 4/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2022 APPLICANT
Assigned to Plan Check Engineer 3/19/2022 DANIEL ABRAMYAN
Corrections Issued 3/19/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 4/5/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 4/19/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 5/26/2022 DANIEL ABRAMYAN
Plan Check Approved 6/8/2022 DANIEL ABRAMYAN
Issued 6/10/2022 APPLICANT
Building Plans Picked Up 6/15/2022 APPLICANT
CofO in Progress 1/19/2023 JEFFREY BULL
No Progress 4/4/2023 RONALD MYRICK
CofO in Progress 4/6/2023 MICHAEL SMITH
Permit Finaled 4/6/2023 MICHAEL SMITH
CofO Issued 4/6/2023 MICHAEL SMITH
Permit Finaled 4/6/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/18/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 5/18/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 5/18/2022 JOSE DUARTE-DIAZ
Miscellaneous Cleared 6/3/2022 NELSON RODRIGUEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/21/2022 Approved JEFFREY BULL
ELECTRICAL-Rough 9/9/2022 Approved JEFFREY BULL
HVAC-Rough 9/9/2022 Approved JEFFREY BULL
PLUMBING-Rough 9/9/2022 Approved JEFFREY BULL
PLUMBING-Rough 10/24/2022 Approved JEFFREY BULL
ELECTRICAL-Final 12/6/2022 Partial Inspection JUSTIN HAWLEY
PLUMBING-Final 12/6/2022 Approved JUSTIN HAWLEY
Pre-Inspection 12/6/2022 Partial Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 12/6/2022 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 12/7/2022 Approved JUSTIN HAWLEY
ELECTRICAL-Final 12/7/2022 Corrections Issued JUSTIN HAWLEY
Final 12/7/2022 Not Ready for Inspection JUSTIN HAWLEY
Green Building Final 12/7/2022 Approved JUSTIN HAWLEY
Green Building Rough 12/7/2022 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Approved JUSTIN HAWLEY
ELECTRICAL-Final 12/28/2022 Approved JEFFREY BULL
Special/Order Compliance 12/28/2022 Partial Inspection MORRIS JACKSON
Final 1/19/2023 OK to Issue CofO JEFFREY BULL