2614 W 73RD ST 90043
Certificate Information: 2614 W 73RD ST 90043
- Application / Permit
- 23010-10000-03333
- Plan Check / Job No.
- B23LA15479
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22'-6"x42'-0" IRREGULAR SHAPE ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 12/5/2023
- Issuing Office
- Current Status
- CofO Issued on 3/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 8/18/2023 | APPLICANT |
Assigned to Plan Check Engineer | 8/22/2023 | KAMYAR EMAMI |
Corrections Issued | 8/23/2023 | KAMYAR EMAMI |
Applicant returned to address corrections | 10/14/2023 | MOHAMMAD ESMAILI |
Applicant returned to address corrections | 11/23/2023 | LUISANGEL VALENZUELA |
Plan Check Approved | 12/3/2023 | LUISANGEL VALENZUELA |
Issued | 12/5/2023 | APPLICANT |
CofO in Progress | 3/7/2025 | MICHAEL LEWIS |
Permit Finaled | 3/12/2025 | DEROLD HAUFF |
Permit Finaled | 3/12/2025 | DEROLD HAUFF |
CofO Issued | 3/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
Sewer availability | Cleared | 8/28/2023 | NEIL TUANO |
Address approval | Cleared | 8/29/2023 | NEIL TUANO |
Eng Process Fee Ord 176,300 | Cleared | 8/29/2023 | NEIL TUANO |
Low Impact Development (LID) | Cleared | 10/3/2023 | TOMMY YIN |
Roof/Waste drainage to street | Cleared | 10/12/2023 | JEANIE LAM |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Herrera,, Edgar E; Lic. No.: NA67603 | , |
Inspector Information
WAYNE REGESTER, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
AMIR NAZARIAN, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 12/13/2023 | Approved | ENRIQUE MIRELES |
Underground Mechanical | 12/13/2023 | Approved | ENRIQUE MIRELES |
Underground Mechanical | 12/15/2023 | Approved | BRENDAN MORELLI |
Underground Mechanical | 12/19/2023 | Corrections Issued | ENRIQUE MIRELES |
Excavation/Setback/Form/Re-Bar | 1/2/2024 | No Access for Inspection | ENRIQUE MIRELES |
Excavation/Setback/Form/Re-Bar | 1/8/2024 | Corrections Issued | ENRIQUE MIRELES |
Excavation/Setback/Form/Re-Bar | 1/12/2024 | Approved | ENRIQUE MIRELES |
Deputy Wood Construction | 2/9/2024 | Approved | ENRIQUE MIRELES |
Deputy Wood Construction | 2/12/2024 | Approved | JOSE MACIAS |
Wood Frame | 2/13/2024 | Partial Approval | JOSE MACIAS |
Floor/Roof Diaphrgm/Shear Wall | 2/21/2024 | Approved | JOSE MACIAS |
ELECTRICAL-Rough | 6/21/2024 | Approved | JOSE MACIAS |
HVAC-Rough | 6/21/2024 | Approved | JOSE MACIAS |
PLUMBING-Rough | 6/21/2024 | Approved | JOSE MACIAS |
Wood Frame | 6/21/2024 | Corrections Issued | JOSE MACIAS |
BUILDING-Rough-Frame | 6/24/2024 | Approved | JOSE MACIAS |
Green Building Rough | 6/24/2024 | Approved | JOSE MACIAS |
Interior/Exterior Lathing | 6/24/2024 | Approved | JOSE MACIAS |
Verify Sprinkler Sign Off | 6/24/2024 | Approved | JOSE MACIAS |
Insulation | 7/5/2024 | Approved | JOSE MACIAS |
Shower Pan | 7/12/2024 | Corrections Issued | JOSE MACIAS |
Drywall Nailing | 7/19/2024 | Approved | JOSE MACIAS |
Shower Pan | 7/19/2024 | Approved | JOSE MACIAS |
Interior/Exterior Lathing | 8/6/2024 | Not Ready for Inspection | JOSH MEISTER |
Interior/Exterior Lathing | 8/8/2024 | Approved | JOSE MACIAS |
Special/Order Compliance | 8/8/2024 | Partial Inspection | ALEX COLIN |
Sewer | 9/6/2024 | Corrections Issued | AMIR NAZARIAN |
Sewer | 9/10/2024 | Approved | AMIR NAZARIAN |
ELECTRICAL-Final | 10/30/2024 | Corrections Issued | AMIR NAZARIAN |
Final | 10/30/2024 | Corrections Issued | AMIR NAZARIAN |
Footing/Foundation/Slab | 10/30/2024 | Approved | AMIR NAZARIAN |
Green Building Final | 10/30/2024 | Corrections Issued | AMIR NAZARIAN |
HVAC-Final | 10/30/2024 | Corrections Issued | AMIR NAZARIAN |
PLUMBING-Final | 10/30/2024 | Approved | AMIR NAZARIAN |
SGSOV-Seismic Gas S/O Valve | 10/30/2024 | SGSOV Approved | AMIR NAZARIAN |
Service/Power Release | 10/30/2024 | Not Ready for Inspection | AMIR NAZARIAN |
Smoke Detectors | 10/30/2024 | Corrections Issued | AMIR NAZARIAN |
ELECTRICAL-Final | 11/13/2024 | Corrections Issued | AMIR NAZARIAN |
Final | 11/13/2024 | Corrections Issued | AMIR NAZARIAN |
Green Building Final | 11/13/2024 | Corrections Issued | AMIR NAZARIAN |
HVAC-Final | 11/13/2024 | Corrections Issued | AMIR NAZARIAN |
Service/Power Release | 11/13/2024 | Corrections Issued | AMIR NAZARIAN |
Smoke Detectors | 11/13/2024 | Approved | AMIR NAZARIAN |
Interior/Exterior Lathing | 11/19/2024 | Approved | ALEX COLIN |
ELECTRICAL-Final | 11/25/2024 | Corrections Issued | AMIR NAZARIAN |
Final | 11/25/2024 | Corrections Issued | AMIR NAZARIAN |
Green Building Final | 11/25/2024 | Approved | AMIR NAZARIAN |
HVAC-Final | 11/25/2024 | Approved | AMIR NAZARIAN |
Service/Power Release | 11/25/2024 | Corrections Issued | AMIR NAZARIAN |
ELECTRICAL-Final | 12/6/2024 | Approved | LUIS CASTRO |
Final | 12/6/2024 | Corrections Issued | LUIS CASTRO |
HVAC-Final | 12/6/2024 | Approved | LUIS CASTRO |
Service/Power Release | 12/6/2024 | Approved | LUIS CASTRO |
Final | 3/5/2025 | Conditional Approval | BARRY HACHE |
Final | 3/7/2025 | OK to Issue CofO | MICHAEL LEWIS |